104.0 4 104.0 6(a) the remainder of the contract, noting any effect on the Required Completion Date or any specified Milestone Date(s) and any other schedule impacts , and
• The contract items of work affected by the proposed change, including quantity changes and extra work items to be established, including prices and back -up data.
Continue to perform the work according to the requirements of the contract until the Department processes a work authorization incorporating the value engineering proposal, in to the project. Acceptance and/or preparation of the value engineering proposal and performance of the work will not extend the Required Completion Date and/or any specified Milestone Date(s) unless a request for an adjustment is submitted, as specified in Section 108.03(b), and accepted by the Representative. Construction acceleration will not be allowed as part of any value engineering proposal. No cont ract adjustment as specified in Section 110.02(d) will be allowed for changes in quantities of original contract items affected by the acceptance of the value engineering proposal. If the value engineering proposal results in contract time savings, the time saved due to the implementation of the value engineering proposal will be shared evenly between the contractor and the Department. A time reduction with or without Milestone adjustments for half of the saved time will be submitted by the Department. The Department reserves the right to adopt all, or any part, of a value engineering proposal for general use on other contracts. Value engineering proposals that are either identical or similar to previously submitted proposals, will be eligible for consideration and compensation under the provisions of this section if the previously submitted proposals were not adopted for general application to other contracts administered by the Department. Compensation for the Contractor’s share of the actual net cost savings associated with a value engineering proposal will be as specified in Section 110.07.
104.05CLEANING OF PROJECT SITE —Remove silt and other deposits from newly constructed culverts,
inlet, outlet and parallel ditches, bridges, and other drainage structures, including stream channels. Clean and remove surplus and discarded material, equipment, and temporary structures from the project and adjacent properties, including waste and borrow areas. Remove deb ris and objectionable material from areas used or disturbed by the construction operations on, or within sight of, the highway. Remove paint marks or spills, stains, rust marks, oil, or any other unsuitable marks, as directed. Restore waste and borrow areas, as specified in Section 105.14. Maintain the vegetation within the constructed slope limits, including waste and borrow a