TRAFFIC ACCOMODATION AND CONTROL

902MAINTENANCE AND PROTECTION DURING TEMPORARY SUSPENSION OF WORK

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 823–0 Save this section

Ask about Section 902

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SUSPENSION OF WORK

902.1DESCRIPTION—This work is maintenance and protection of traffic on the project and the maintenance

and protection of the project during a temporary work suspension.

902.2MATERIAL—Section 901.2

902.3CONSTRUCTION—Maintain and protect the project during suspension, as specified in Section 105.13(b),

as directed, and as follows:

• Shape and maintain the existing roadway if existing roadway pavements are broken up and removed in advance of a reasonable paving schedule.

• Surface roadways, as directed, with acceptable commercial material or with acceptable local material secured beyond the project limits. If necessary, remove this material when project operation resumes.

• Apply a calcium chloride dust control solution or other approved dust control palliative in the manner and at the rate of application directed. If necessary, remove this material when project operations resume.

• Remove all protective signs and devices previously installed on the project.

If necessary, remove material placed by Department forces when operations resume. Maintain and protect traffic during suspension, as specified in Section 901. The Department reserves the right to maintain traffic through the entire project or portions of the project and to perform necessary maintenance of traffic work. This Department work will be performed if agreement, as specified below, cannot be made upon a price, or if the Department work performed is in the interest of the State.

902.4MEASUREMENT AND PAYMENT—

(a)Lump Sum Basis. Section 901.4

If this item is extra work, then the Department will pay for this item at a negotiated price as specified in Section 110.03(c).

(b)Acceptable Commercial and/or Local Material. Cubic Yard or Ton

If this material is extra work, then the Department will make payment as specified in Section 110.03(c).

(c)Calcium Chloride or Other Dust-Control Palliatives. Gallon or Ton

If these materials are extra work, then the Department will make payment as specified in Section 110.03(c).

(d)Removal of Material Placed by Department Forces. Cubic Yard

The Department will pay for this work as Class 1 Excavation.

Get an email when 902 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 823–0 of 1,522. View official source ↗