RIGID PAVEMENTS

527DOWEL RETROFIT

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 432–0 Save this section

Ask about Section 527

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

527.1DESCRIPTION—This work is the installation of epoxy-coated, smooth dowel bars into existing concrete

pavement across cracks or transverse joints without dowels.

527.2MATERIAL—

(a)Load-Transfer Units. Section 705.3(a), (b) and (g)
(b)Caulking Compound. Section 705.8(b)
(c)Preformed Cellular Polystyrene. ASTM C578
(d)Rapid-Set Concrete Patching Material. Section 525.2(c).

Use within the shelf life and temperature limitations set by the manufacturer.

(e)Concrete Curing Materials. Section 711.1 and 711.2(b)
(f)Intermediate Curing Compound. Section 711.2(d)
(g)Concrete Admixtures. Section 711.3

If accelerating admixtures are used, provide only accelerating admixtures that contain no chlorides.

(h)Joint Sealing Material. Section 705.4(a), (b) and (c)
(i)Bond Breaker Lubricant. Provide a commercially available bond breaking lub ricant with a flash

point of not less than 149F, and recommended for contact with steel materials according to manufacturer’s recommendations. Do not use graphite-based lubricants.

(j)Expansion Joint Filler. Section 705.1

527.3CONSTRUCTION—As shown on Standard Drawings and as follows:

(a)Equipment. Provide a power driven, self propelled saw capable of making two parallel cuts per dowel

bar slot. Do not use equipment that may cause pavement to spall or cause surface aggregates to fracture.

(b)Slot Preparation and Cleaning. Saw cut pavement to place center of dowel at mid-depth of pavement

slab. If repair area spans different pavement thicknesses, e.g. mainline to ramp transitions, place at the mid- depth of the thinner thickness. Align saw cuts parallel to roadway centerline. Cut three dowel slots (six saw cuts) per wheel path and centered over the crack or transverse joint. Provide three dowel bar slots in each wheel path. Use a jackhammer weighing not more than 30 pounds to remove concrete between saw cuts. If pavement damage occurs from a 30-pound jackhammer, remove the damaged pavement and use a 15- pound jackhammer. Clean and backfill the damaged pavement area as specified in Sections 525.3(c) and 525.3(d). Create a level surface at bottom of slot parallel to roadway surface.

(c)Clean Slots. Clean exposed surfaces of slots. Remove all loose and foreign material within 24 hours

before concrete placement and remove all slurry to prevent debris from emerging once dried. Final cleaning must be completed within 30 minutes before concrete placement. Reclean areas not repaired within 30 minutes of final cleaning or if contamination occurs before concrete placement. When cleaning by air blasting, use a compressed air stream of at least 100 pounds per square inch measured at the source, free of oil, moisture, and other contaminates.

(d)Dowel Preparation and Placement.
1.Prepare Dowels. Cut 1/4-inch-thick preformed cellular polystyrene material to the cross-section

dimensions of the slot at the joint. Cut an opening in the polystyrene joint material to allow the dowel to fit without stretching and without gaps. Place the material centered on the dowel to form a temporary joint. Apply bond-breaker lubricant to Type B coated dowel bars, unless a bond breaker lubricant has been applied in the shop. Stir the lubricant and apply by daubing, mopping, or with a gloved hand, to produce a thorough coating. Do not use brushes for lubricant application. Apply the lubricant, as specified, at least 1 hour before placing the concrete around the dowel assembly. Type A coated dowel bars do not require lubricant as specified in Section 501.3(i). Place 1 1/2-inch non-metallic expansion caps with 1/4-inch clearance from the end of the dowel to the bottom of the cap. For crack or joint widths greater than 1/4 inch, use expansion joint material instead of the preformed cellular polystyrene material with a thickness matching the crack or joint width.

2.Place Dowels. Provide plastic or non-metallic chairs with a minimum 1/2-inch clearance between

dowel bar cap and all slot surfaces, including end, both sides and bottom. Place chairs on the bottom of the slot. Place coated dowel bars parallel to roadway centerline and pavement surface not to exceed the following limits:

• Vertical tilt or horizontal skew (relative to the plane of the grade and the centerline of the constructed pavement): 0.25-inch maximum displacement of each end of the dowel relative to the midpoint of the dowel.

• Longitudinal translation (relative to the intended crack or transverse joint location, along the direction of travel): 1 inch maximum

• Horizontal translation (relative to the intended location, across the crack or joint): 1 inch

Place dowels to align the temporary j oint material with the existing joint or crack. Seal the temporary joint material at the sides and bottom of transverse joint or crack with caulking compound to prevent concrete patching material from entering into existing joint or crack.

3.Epoxy Bonding Compound. Apply according to the manufacturer’s recommendations.
4.Fill Slot. Fill slot with concrete patching material. Vibrate to thoroughly consolidate the material in

the slot and around dowel bar. Do not allow the dowel bar to move from the specified position.

(e)Final Finish for Pavements not being Overlaid or Diamond Ground. Finish the surface of the

slots to match the existing pavement surface profile, including any existing wheel ruts.

(f)Curing of Concrete. Section 516.3(j).
(g)Saw and Seal Joint. Saw and seal transverse contraction joint sealant reservoirs for entire lane width

as required.

(h)Opening to Traffic. Section 516.3(q).
(i)Defective Work. Remove and replace dowel retrofits that are considered defective, at no additional

cost to the Department.

527.4MEASUREMENT AND PAYMENT—Each

For the existing joint or crack preparation, patching, curing and sealing operations. Includes six dowel bars per joint or crack.

Get an email when 527 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 432–0 of 1,522. View official source ↗