01501Mobilization

UT · 2025 Standard Specifications✓ Full text on BuildSpecRev. September 14, 2023Book pages 172–172 Save this section

Ask about Section 01501

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Part 1 — General

1.1 Section Includes

A.Mobilization and preparatory work necessary to become ready to perform the work and final cleanup necessary to complete the work.

1.2 Related Sections

A.Section 01741: Final Cleanup

1.3 REFERENCES Not Used

1.4 DEFINITIONS Not Used

1.5 SUBMITTALS Not Used

1.6 General

A.Includes the moving of personnel, equipment, supplies and incidentals to each work site before beginning the work.
B.Includes the establishment of offices, buildings, and other facilities necessary for the work.
C.Includes labor and operations that must be performed before beginning other items under the Contract.
D.Includes removal of personnel, equipment, and supplies from each work site at the completion of the work.
E.Includes work that is not included with other items under the Contract such as cleanup and restoration of disturbed areas. Refer to Section 01741.

Part 2 — PRODUCTS Not Used

Part 3 — EXECUTION Not Used

Get an email when 01501 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2025 Edition. Pages 172–172 of 1,311. View official source ↗