MOBILIZATION

PART 1 GENERAL

1.1SECTION INCLUDES

A.Mobilization and preparatory work necessary to become ready to perform

the work and final cleanup necessary to complete the work.

1.2RELATED SECTIONS

A.Section 01741: Final Cleanup

1.3REFERENCES Not Used

1.4DEFINITIONS Not Used

1.5SUBMITTALS Not Used

1.6GENERAL

A.Includes the moving of personnel, equipment, supplies and incidentals to

each work site before beginning the work.

B.Includes the establishment of offices, buildings, and other facilities

necessary for the work.

C.Includes labor and operations that must be performed before beginning

other items under the Contract.

D.Includes removal of personnel, equipment, and supplies from each work

site at the completion of the work.

E.Includes work that is not included with other items under the Contract such

as cleanup and restoration of disturbed areas. Refer to Section 01741.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION Not Used

END OF SECTION

Mobilization

Get an email when 01501 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 171–171 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 01501 — Mobilization. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.