POST-TENSIONING CONCRETE
PART 1 GENERAL
1.1SECTION INCLUDES
A.Post-tensioning (PT) system and grouting of prestressing steel for
concrete elements.
B.Items necessary for the particular prestressing PT system used, including
but not limited to ducts, anchorage assemblies, supplementary reinforcing bars, and grout used for pressure grouting ducts.
1.2RELATED SECTIONS
A.Section 03211: Reinforcing Steel and Welded Wire
1.3REFERENCES
A.AASHTO M 203: Steel Strand, Uncoated Seven-Wire for Concrete
Reinforcement
B.AASHTO M 204: Uncoated, Stress-Relieved Steel Wire for Prestressed
Concrete
C.AASHTO M 275: Uncoated High-Strength Steel Bars for Prestressed
Concrete
D.AASHTO LRFD Bridge Construction Specifications, current edition
E.AASHTO LRFD Bridge Design Specifications, current edition
F.ASTM A 53: Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and
Seamless
G.ASTM A 240: Chromium and Chromium-Nickel Stainless Steel Plate,
Sheet, and Strip for Pressure Vessels and General Applications
H.ASTM A 653: Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-
Coated (Galvannealed) by the Hot-Dip Process
Post-Tensioning Concrete
I.ASTM C 307: Tensile Strength of Chemical-Resistant Mortar, Grouts, and
Monolithic Surfacings
J.ASTM C 531: Linear Shrinkage and Coefficient of Thermal Expansion of
Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes
K.ASTM C 579: Compressive Strength of Chemical-Resistant Mortars,
Grouts, Monolithic Surfacings, and Polymer Concretes
L.ASTM C 881: Epoxy-Resin-Base Bonding Systems for Concrete
M.ASTM C 882: Bond Strength of Epoxy-Resin Systems Used With
Concrete by Slant Shear
N.ASTM C 1583: Tensile Strength of Concrete Surfaces and the Bond
Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-Off Method)
O.ASTM D 3035: Polyethylene (PE) Plastic Pipe (DR-PR) Based on
Controlled Outside Diameter
P.ASTM D 3350: Polyethylene Plastics Pipe and Fittings Materials
Q.ASTM D 3895: Oxidative-Induction Time of Polyolefins by Differential
Scanning Calorimetry
R.ASTM D 4285: Indicating Oil or Water in Compressed Air
S.ASTM D 5989: Extruded and Monomer Cast Shapes Made From Nylon
(PA)
T.ASTM F 593: Stainless Steel Bolts, Hex Cap Screws, and Studs
U.ASTM F 714: Polyethylene (PE) Plastic Pipe (DR-PR) Based on Outside
Diameter
V.ASTM F 2136: Notched, Constant Ligament-Stress (NCLS) Test to
Determine Slow-Crack-Growth Resistance of HDPE Resins or HDPE Corrugated Pipe
W.MIL-PRF-3420: Wrapping Materials, Volatile Corrosion Inhibitor Treated,
Opaque
X.PTI M50.3: Post-Tensioning Institute (PTI) Guide Specification for Grouted
Post-Tensioning Post-Tensioning Concrete
Y.PTI M55.1: Post-Tensioning Institute (PTI) Specification for Grouting of
Post-Tensioned Structures
1.4DEFINITIONS
A.Inlet and outlet pipes – The terms inlet pipes and outlet pipes are
synonymous with vents, drains, injection, ejection, or inlet/outlet ports. Inlet and outlet pipes are devices connected to the PT system used for the injection of materials into or the ejection of materials from inside the ducts.
B.Jacking force – The force applied to the tendon before anchorage and the
occurrence of losses, including the anchor set loss.
C.Permanent force – The force remaining in the prestressing steel after all
losses, including long term creep and shrinkage of concrete, elastic shortening of concrete, relaxation of steel, losses in prestressing steel due to sequence of stressing, friction, unintended wobble of ducts, anchor set, friction in anchorages, and all other losses particular to the method or system of prestressing have taken place or have been provided for.
D.Torpedo – A rigid object sized to fit through undamaged post-tensioning
ducts. Used to prove that installed ducts have not been blocked or damaged during the concrete pour.
1.5SUBMITTALS
A.Working Drawings
1.Detailed drawings of the PT system for review. Include at least the
following:
a.Anchorage and bearing details including local zone and
grillage reinforcement
b.Duct placement including individual tendon center of gravity
(CG)locations and combined tendon CG location at
anchorages, low points, and high points 1) Not required for segmental bridges or precast deck panels 2) Distribute the prestressing force in cast-in-place post- tensioned bridge girders with approximately equal quantity in each girder and place the force symmetrically about the centerline of the structure
c.Method and spacing of duct supports
d.Duct ties and stirrup ties
e.Inlet and outlet pipe locations
f.Expected friction coefficient, wobble coefficient, and anchor
set Post-Tensioning Concrete
g.Jacking forces, jacking ends, initial stresses, and sequence
h.Permanent grout cap detail
i.Material data sheets for tendons, ducts, and permanent
grout cap
j.Calculated elongations and tolerances
k.Bar couplers when shown
l.High point outlet inspection details
m.Anchorage inspection details
2.Include supporting engineering calculations.
a.Design the post-tensioning system according to AASHTO
LRFD Bridge Design Specifications
b.Include computations and a typical tendon force diagram
after friction and anchor set losses based upon expected actual coefficients and values for the PT system to be used.
3.Provide detailed congestion drawings integrating PT system and
concrete reinforcing at locations where duct or anchorage passes through grids of reinforcing steel, such as at anchorage zones, diaphragms, bents, and other highly congested areas.
a.Indicate additions or rearrangement of reinforcing steel and
revisions to concrete dimensions from that shown.
B.Personnel Qualifications
1.Provide names and current certifications of qualified supervisors for
approval.
a.Refer to this Section, article 1.6
C.Grouting Procedures and Safety Procedures
1.Submit grouting procedures at least 45 calendar days in advance of
scheduled grouting operations for review.
a.Include the following:
1) Names, proof of training and experience records for the grouting crew and the crew supervisor in conformance with this Specification 2) Type, quantity, brand, and certifications for materials used in grouting, include product data sheets 3) Equipment data, including capacity in relation to demand, as well as provisions for back-up equipment 4) General grouting procedure 5) Duct cleaning procedure 6) Duct pressure test and repair procedure. 7) Mixing and pumping procedure 8) Method to be used to control the rate of flow within ducts 9) Theoretical grout volume calculations 10) Direction of grouting and sequence of inlet and outlet pipe usage Post-Tensioning Concrete
11) Procedures for handling blockages and potential regrouting and post grouting repair.
2.Submit safety procedures for information.
D.Prestressing Steel
1.Accompany each lot of prestressing steel with a mill certificate and
a test report including the following:
a.Chemical composition (not required for strand)
b.Cross-sectional area
c.Yield and ultimate strengths
d.Elongation at rupture
e.Modulus of elasticity
f.Stress strain curve for the actual prestressing steel intended
for use
2.Supply a certificate of conformance stating the manufacturer’s
minimum guaranteed ultimate tensile strengths and actual ultimate strengths with each reel or heat of prestressing steel wires, bars, or strands. Refer to this Section, Article 2.2.
3.Samples for prestressing steel testing
a.Provide samples to the Department for verification testing
from each manufactured reel of prestressing steel strand, from each size and each heat of prestressing bars, from each coil of prestressing wire, and from each lot of anchorage assemblies and bar couplers to be used. 1) Provide three 5 ft long samples of each size from each reel for strand. 2) Provide three 7 ft long samples from each heat or reel for wire or bars.
E.Post-Tensioning Anchorages
1.Submit a test report and certificate of conformance provided by an
independent testing laboratory for review which indicates that the anchorages meet the testing requirements in Section 10.3.2.3 of the AASHTO LRFD Bridge Construction Specifications.
a.Indicate that anchorages satisfy the requirements stated in
this Section, Article 2.3, paragraph A.
F.Stressing Jacks
1.Refer to this Section, Article 3.4, paragraph B.
2.Furnish calibration charts certified by an independent laboratory
with each jack and associated gauge or load cell used on the project.
a.Calibrate jack and its gauge or load cell as a unit with the
cylinder extension in the approximate position that it will be at final jacking force.
Post-Tensioning Concrete
b.Provide certification for accuracy of the jack and associated
gauge or load cell at the start of the work, after repair or adjustment, and every 180 days thereafter or as requested by the Department.
c.Provide pressure gauge calibration charts that are done
while the jack is in the identical configuration as will be used on site including same length of hydraulic lines.
G.Duct Pressure Field Test Records
1.Submit a copy of the duct pressure field test records specified in
this Section, Article 3.3, paragraph B for information.
H.Elongation Records Record elongations of each tendon at time of
stressing along with jacking force and target elongation. Refer to this Section, Article 3.4.
1.Submit record of elongation of each tendon at time of stressing
along with jacking force, gauge pressure, and target elongation for information within five days of completed tendon installation. Refer to this Section, Article 3.4, paragraph D.
I.Stressing Operation Records
1.Submit a copy of the stressing operation records specified in this
Section, Article 3.4, paragraph A5 for information.
J.Post-Tensioning Grout Test Reports
1.Submit certified test reports for review from an independent
Laboratory, Cement Concrete Reference Laboratory (CCRL) approved, which show that the post-tensioning grout material meets the requirements specified in this Section, Article 2.6.
K.Grouting Operation Reports
1.Submit for information:
a.Progress of grouting operations for each duct signed by
grouting operation supervisor in control of the work for information within five calendar days after grouting
b.Information per duct indicating dates of tendon installation
and grouting
c.Copy of the grouting operation records specified in this
Section, Article 3.5, paragraph E11
1.6SUPERVISOR REQUIREMENTS
A.PT system manufacturer’s representative must:
1.Be certified as a PTI Level 2 Bonded PT Field Specialist
2.Attend the preconstruction meeting
Post-Tensioning Concrete
3.Be present at all times during installation of PT system components
to:
a.Inspect and approve installation of hardware, including ducts
b.Provide instructions to the Contractor regarding concrete
placement around the ducts, end-anchorage assemblies, and other appurtenances
4.Provide close observation and control of:
a.Duct pressure field test
b.Stressing and anchoring of tendons
c.Post-grout inspections and repairs
d.Record keeping, certification of stressing results, and
approval of elongations
5.Be present for grouting operations
6.Review and sign:
a.Duct pressure field tests records
b.Elongation records
c.Stressing operation records
7.More than one representative is required when multiple PT
operations are occurring simultaneously.
B.Grouting operation supervisor must:
1.Be certified as either an ASBI Certified Grouting Technician or a
PTI Level 2 Bonded PT Field Specialist
2.Attend the preconstruction meeting
3.Provide close observation and control of grouting operations,
including:
a.Mixing and placing
b.Field trial tests
c.Field mockup tests
d.Production tests
4.Review and sign:
a.Grouting Procedures
b.Safety Procedures
c.Grouting operation reports
PART 2 PRODUCTS
2.1GENERAL
A.Store materials in a weatherproof building, shed, covering, or container
until time of use.
B.Equipment for oil-free and water-free compressed air.
1.Refer to ASTM D 4285.
Post-Tensioning Concrete
2.2PRESTRESSING STEEL
A.Materials:
1.Strand
a.Uncoated, Grade 270, low-relaxation, 7-wire strand
conforming to AASHTO M 203
2.Bar
a.Uncoated deformed (Type II) conforming to AASHTO M 275
3.Wire
a.Uncoated, low-relaxation conforming to AASHTO M 204
B.Attach tags for strand from each manufactured reel, bars of each size from
each mill heat, wire from each coil, anchorage assemblies, PT system components and bar couplers to be shipped to the site.
1.Assign the individual lot number and tag in such a manner that
each lot can be accurately identified at the job site.
2.Unidentified prestressing steel, anchorage assemblies, or bar
couplers received at the site will be rejected if there is a loss of positive identification of these items at any time.
C.Use bar couplers only at the locations shown.
1.Use mechanical couplers that develop at least 96 percent of the
actual ultimate strength of the bar, tested in an unbonded state, without exceeding anticipated set.
2.Use couplers for bars that do not reduce the elongation at rupture
below the anticipated elongation of an uncoupled bar.
D.Protect prestressing steel against physical damage and rust or other
results of corrosion at all times from manufacture to grouting or encasing in concrete.
1.Do not use prestressing steel that has sustained physical damage.
2.Remove and discard lengths of strand containing broken wire.
3.Use wire that is bright and uniformly colored, having no foreign
matter or pitting on its surface.
4.Package prestressing steel in containers or shipping forms to
protect the steel against physical damage and corrosion during shipping and storage.
a.Use a corrosion inhibitor which prevents rust or other results
of corrosion, placed in the package or form, 1) Use a corrosion inhibitor either placed in the package form, or applied directly to the steel that has no deleterious effect on the steel, grout, concrete or bond strength of steel to grout. 2) Use inhibitor carrier type packaging material that conforms to the provisions of Federal Specification MIL-PRF-3420. Post-Tensioning Concrete
b.Immediately rejuvenate or replace the corrosion inhibitor if its
useful life expires.
5.Use shipping package or form that is clearly marked with a
statement that the package contains high-strength prestressing steel, care to be used in handling, the type, kind, and amount of corrosion inhibitor used including the date when placed, safety orders, and instructions for use.
a.Immediately replace damaged packaging or forms or restore
to original condition.
2.3POST-TENSIONING ANCHORAGES
A.Use anchoring devices that develop at least 96 percent of the actual
ultimate tensile strength of the prestressing steel, tested in an unbonded state, without exceeding the anticipated set.
2.4DUCTS
A.General
1.Use corrugated galvanized metal ducts, corrugated plastic ducts,
rigid steel pipe ducts or smooth plastic ducts.
a.Use ducts that are mortar tight, and capable of withstanding
concrete pressures without deforming or permitting the entrance of cement paste during the placing of concrete.
b.Use ducts that can be accurately bent and placed at the
locations shown.
2.Minimum internal dimensions for:
a.Multi-strand tendons: cross-sectional area 2½ times the
cross-sectional area of the prestressing steel
b.Prestressing bars: diameter ½ inches larger than bar outside
diameter, measured across deformations
c.Prestressing bars with couplers: diameter ½ inches larger
than largest dimension of the largest enclosed element 1) Enclose bar couplers and coupler components in housings long enough to permit the necessary movements
3.Use ducts that have properties compatible with the assumed design
values shown.
4.Use ducts that can be bent as shown without crimping or flattening
and have sufficient strength to maintain their correct alignment during placing of concrete.
5.Use duct splices at joints between precast segments that are
capable of positively preventing the entrance of cement paste and water from concrete.
a.Use duct splices that do not cause electrolytic action or
deteriorate. Post-Tensioning Concrete
6.Provide reference marks on rigid ducts to facilitate orientation
during placement.
7.Provide hold down ties to the forms when the buoyancy of the ducts
in the fluid concrete would lift the reinforcing steel.
B.Metal Ducts:
1.Fabricate corrugated semi-rigid ducts from ASTM A 653 galvanized
sheet steel, coating designation G90.
a.Use a minimum wall thickness of:
1) 26 gauge for semi-rigid ducts less than or equal to 2.625 inches in diameter 2) 24 gauge for semi-rigid ducts greater than 2.625 inches in diameter 3) 31 gauge when bar tendons are preassembled with semi-rigid ducts
b.Fabricate with either welded or interlocked seams.
1) Galvanize welded seams.
2.Fabricate rigid steel pipe ducts from galvanized ASTM A 53
Grade B schedule 40 steel pipe.
a.Use pipe with smooth inner walls capable of being curved to
the proper configuration without crimping or flattening.
3.Provide joints between sections of ducts that have positive metallic
connections which do not result in angle changes at the joints.
C.Plastic Ducts
1.Refer to Section 10.8.3 of the AASHTO LRFD Bridge Construction
Specifications for the fabrication and testing requirements of corrugated plastic ducts.
a.Use seamless fabrication methods to manufacture
corrugated plastic duct.
2.Use rigid smooth black polyethylene ducts manufactured from 100
percent virgin polyethylene resin meeting the requirements of ASTM D 3350 with a minimum cell class of 445574C where the tendon is not embedded in concrete.
a.Use a resin containing antioxidant(s) with a minimum
oxidation induction time (OIT) according to ASTM D 3895 of not less than 40 minutes.
b.Manufacture smooth duct with a dimensional ratio (D/R) of
17.0 as established by either ASTM D 3035 or ASTM F 714 as appropriate for the manufacturing process used.
c.Use duct meeting the minimum pressure rating of 100 psi.
Post-Tensioning Concrete
D.Exceptions
1.Use plastic ducts that are leak tight, vapor tight and impermeable
where special corrosion protection is required, such as in bridge decks, external tendons, and bridge elements subjected to corrosive environments.
2.Use plastic ducts where stray electrical currents may cause
corrosion damage to tendon materials.
3.Do not use plastic ducts when the radius of curvature of the tendon
is less than 30 ft.
E.Splices, Joints, Couplings, Connections, and Inlet and Outlet Pipes
1.Use stainless steel, nylon, or polyolefin materials.
a.Stainless steel products other than bolts, conform to ASTM
A 240 Type 316. 1) ASTM F593 Type 316 for bolts
b.Nylon products, use one of the following cell classes
according to ASTM D 5989: 1) S-PA0141 (weather resistant) 2) S-PA-0231 (heat stabilized) 3) S-PA0401 (ultimate strength not less than 10,000 psi with UV stabilizers added)
c.Polyolefin products, conform to the following:
1) Contains antioxidants with a minimum induction time of 20 minutes according to ASTM D 3895 2) Remolded finished polyolefin material has a stress crack resistance minimum failure time of 3 hours at an applied stress of 348 psi using ASTM F 2136
2.Make splices, joints, couplings, and connection to duct and
anchorage with devices or methods (mechanical couplers, plastic sleeves, heat-shrink sleeves) producing a smooth interior alignment with no lips or kinks.
a.Provide connections and fittings that are airtight and
watertight.
b.Tape sealed connections or repairs are not permitted
c.Heat-shrink sleeves requirements, refer to PTI M50.3,
Section 4.3.7.
d.Provide connections that are external to the concrete with a
minimum pressure rating of 100 psi.
3.Plastic components, including fasteners, must be free of water
soluble chlorides and not react with the concrete or enhance corrosion of the prestressing steel.
Post-Tensioning Concrete
4.Use inlet and outlet pipes that are ¾ inch minimum inside diameter
for strand tendons, or ⅜ inch for single bar tendons.
a.Use inlet and outlet pipes that are fitted with positive
mechanical shut-off valves or plugs. 1) Design and test inlets, outlets, valves, and plugs to resist a minimum pressure of 150 psi.
b.Extend pipes a sufficient distance out of the concrete
member to allow for proper closing of the valves
2.5REINFORCING STEEL
A.Use coated reinforcing steel according to Section 03211.
2.6PT GROUT
A.Use a commercial, prepackaged, anti-bleed, post-tensioning grout
conforming to the requirements for a Class C grout as defined by PTI M55.1.
1.Furnish grout capable of meeting the vertical rise requirements for
the project tendons.
2.Deliver grout in plastic lined or coated moisture proof containers,
stamped with the application type, date of manufacture, lot number and mixing and pumping instructions.
a.Use grout within 6 months of manufacture.
3.Use water that is potable, clean, and free of injurious quantities of
substances known to be harmful to Portland cement or prestressing steel.
2.7EPOXY GROUT
A.Refer to Table 1 for properties
Table 1 Epoxy Grout Properties Property Test Method Requirements ASTM C 579 Compressive Strength Method B, 2 inch > 10,000 psi (7 day) cubes, Load Rate II Tensile Strength (7 day) ASTM C 307 > 2,000 psi Slant Shear Bond Strength ASTM C 882 > 1,500 psi Linear Shrinkage ASTM C 531 0.025%
Post-Tensioning Concrete
2.8PERMANENT GROUT CAP
A.Use permanent grout caps made of one of the following:
1.Fiber reinforced polymers using nylon, Acrylonitrile Butadiene
Styrene (ABS), or polyester resins:
a.Use one of the following cell classes for products made from
nylon: 1) S-PA0401 (weather resistant) 2) S-PA0231 3) S-PA0401 (ultimate strength not less than 10,000 psi with ultraviolet stabilizer added) according to ASTM D 5989
2.ASTM A 240 Type 316L stainless steel
B.Use caps rated for a minimum pressure of 150 psi.
C.Seal caps against the anchor bearing plate with neoprene “O”-ring seals
and ASTM F 593 Type 316 stainless steel bolts.
D.Provide an inlet port at the top of the cap or front of cap as appropriate.
2.9EPOXY COMPOUND
A.Comply with ASTM C 881 Type IV.
PART 3 EXECUTION
3.1ANCHORAGE INSTALLATION
A.Arrange the anchorage so that the prestressing force in the tendon can be
verified before removal of the stressing equipment.
B.Set anchorage devices or block-out templates for anchorages in a plane
normal to the axis of the tendons so that anchor plates are normal in all directions of the tendon and bear uniformly on the concrete.
C.Recess the anchoring devices so that the ends of the prestressing steel
and parts of anchoring devices including permanent grout caps are embedded at least 2 inches inside the end surface of the element.
D.Locate anchorages within plus or minus ¼ inch of the desired position
laterally and plus or minus 1 inch along the tendon.
1.Maintain minimum cover requirements.
Post-Tensioning Concrete
E.Verify entrance and exit angles of tendon paths at anchorages and at
faces of concrete so they are within plus or minus 3 degrees of desired angle measured in any direction, and deviations in the alignment are accomplished with smooth transitions without kinks.
3.2DUCT INSTALLATION
A.Securely tie ducts in position, inspect, and repair before concrete
placement is started.
1.Use supplementary support bars where needed to maintain proper
alignment of the duct.
B.Securely fasten internal ducts to avoid displacing or damaging the ducts
during concrete placement.
1.Support polyethylene duct and metal duct for longitudinal PT in the
flanges at intervals not to exceed 2 ft.
2.Tie polyethylene duct in webs for longitudinal PT to stirrups at
intervals not to exceed 2ft.
3.Support flat ducts for transverse PT at intervals of not more than 12
inches.
4.Tie metal duct for longitudinal PT in webs to stirrups at intervals not
to exceed 4 ft.
C.Verify final position of PT duct is within the tolerances shown in Table
10.4.1.1-1 of the AASHTO LRFD Construction Specifications.
1.Position the duct as shown and adjust the reinforcement as
determined by the Engineer if conflicts exist between the reinforcement and post-tensioning duct.
D.Provide inlet/outlet ports at the following locations:
1.Anchorage areas of tendon
2.The high points of the duct, when there is more than a 20 inch
variation in the vertical position of the duct
a.Locate additional outlet ports 3 ft to either side of the high
point
3.Low points of the duct. Verify outlet port is free draining
4.Major changes in the cross section of the duct, such as coupler
locations
5.Locations as shown
E.Verify that ducts, anchorage blockouts, openings, inlets, and outlets are
kept clean and free of debris, fuel, oils, other contaminants, and site trash.
1.Seal the ends of ducts after installation in the forms.
2.Leave low point outlets open.
Post-Tensioning Concrete
F.Verify angle changes at duct joints are within plus or minus 3 degrees of
desired angle measured in any direction, and deviations in the alignment are accomplished with smooth transitions without kinks.
G.Use mandrels as stiffeners in each duct during concrete placement for
precast segments.
1.Extend mandrel throughout the length of the segment being cast
and at least 2 ft into the corresponding duct of the previously cast segment.
2.Provide mandrels of sufficient rigidity to maintain the duct geometry
with the tolerances shown in this Section.
3.3TENDON INSTALLATION
A.Verify that ducts are unobstructed, undamaged, and free of water and
debris after completion of concrete placement and before installing the prestressing steel.
1.Prove that the ducts are clear of obstructions or damage by passing
a suitably sized torpedo through the ducts.
a.Size the torpedo ¼ inch smaller than the clear, inside
dimensions of the duct, with rounded ends.
b.Use a 2 ft long torpedo for straight ducts.
c.Size the torpedo, for sharply curved ducts, such that when
both ends touch the outermost wall, the torpedo is at least ¼ inch clear of the inside wall.
d.The member will be rejected if the torpedo will not easily
travel completely through the duct.
e.Using a torpedo to verify that ducts are clear is not required
for four strand tendons in flat ducts used for transverse PT of segmental box-girders placed before concrete casting. 1) Prove PT ducts are free and clear of obstructions or damage by moving the group of strands back and forth in duct for a minimum distance of 1 ft in each direction. 2) Move strands easily, by hand, without resorting to excessive effort or mechanical assistance.
2.Flush ducts with oil-free and water-free compressed air or water as
required to remove unwanted material from inside of ducts.
a.Ducts subjected to contamination with chlorides, water used
for flushing ducts may contain slack lime (calcium hydroxide) or quicklime (calcium oxide) in the amount of 0.1 lb/gal. 1) Test for presence of chlorides and oils in discharged water before placing tendons. 2) Continue to flush if chloride levels in flush water outflow exceeded 300 ppm until chloride level in flush water outflow is below 250 ppm. Post-Tensioning Concrete
b.Blow all water out of the duct with oil-free compressed air
and swab dry after flushing.
B.Conduct duct pressure field tests before installing the internal or external
prestressing steel.
1.Install grout caps, inlet and outlet port caps, and other components
necessary to seal ducts.
2.Pressurize duct to 50 psi using oil-free and water-free compressed
air.
a.Only one duct per web or girder may be tested at a time.
3.Lock off the outside air source.
4.Record pressure loss for 1 minute.
a.Locate the leak, repair, and retest if the pressure loss
exceeds 15.0 psi for tendons greater than 150 ft long, or 25.0 psi for tendons less than or equal to 150 ft long.
5.Include location and method of repair in duct air test records if
repairs are required.
6.Do not load strand until all pressure tests are successful.
C.Strands in an individual tendon may be pushed or pulled through the duct
individually, or may be pulled through the duct as a unit.
1.Protect the strand which is being advanced into the duct from
contact with abrasive materials such as steel or concrete and contaminants such as grease, oil, and dirt at all times.
a.Round off ends of strands and wires that are pushed, or fit
advancing end with smooth protective cap.
b.Use pulling lines with a capacity of at least 2.5 times the
dead weight of the tendons when used for essentially horizontal tendon installation.
c.Do not use pushing wheels made from metal.
d.Do not intentionally rotate strands or wires during
installation.
e.Use a special steel wire sock or other device attached to
advancing end if a tendon is pulled through the duct.
f.Do not install permanent tendons before completion of
testing as required by this Section.
3.4STRESSING TENDONS
A.General
1.Do not apply PT forces until the concrete has attained the required
compressive strength as shown.
a.Do not apply PT forces to cast-in-place concrete structures
other than segmentally constructed bridges until 10 days after the last concrete has been placed in the member.
Post-Tensioning Concrete
b.Make test cylinders for determining strength of the same
concrete and cured under the same conditions as the member.
2.Stress all strands in each tendon simultaneously with a multi-strand
jack except for those in flat ducts with not more than four strands.
3.Furnish equipment for tensioning the tendons from the
manufacturer of the PT system.
4.Sequence the stressing of post-tension cast-in-place bridge such
that no more than one tendon is stressed per web before stressing a tendon in another web.
a.Do not apply an eccentric force about the centerline of the
structure that exceeds 1/6 of the total post-tensioning force at any time during the prestressing.
5.Keep stressing operation records that include the following for each
tendon installed:
a.Project Pin, Name, and number
b.Contractor and subcontractor
c.Tendon location, size and type
d.Date tendon was first installed in ducts
e.Coil and reel number for strands or wires and heat number
for bars and wire
f.Assumed and actual cross-sectional area
g.Assumed and actual modulus of elasticity
h.Date stressed
i.Jack and gauge numbers per end of tendon
j.Required jacking force
k.Gauge pressures
l.Elongations (theoretical and actual)
m.Anchor sets (theoretical and actual)
n.Stressing sequence (for example tendons before and after
this tendon)
o.Stressing mode (one end or two ends or simultaneous)
p.Witnesses to stressing operation (Contractor, manufacturer’s
representative, and Inspector)
q.Date grouted, days from stressing to grouting, grouting
pressure applied, and injection end
r.Other relevant information
B.Stressing Jacks
1.Use hydraulic jacks to stress tendons that are capable of providing
and sustaining the necessary forces. Equip each jack with either:
a.A pressure gauge with an accurately reading dial at least
6 inches in diameter.
Post-Tensioning Concrete
b.A load cell with indicator by means of which the prestressing
force in the tendon may be determined. 1) Do not use the lower 10 percent of the Manufacturer’s rated capacity when determining the jacking stress.
2.Use a jacking system that provides an independent means of
measuring the tendon elongation.
C.Tensioning Operations
1.Tension prestressing steel so that the force of the prestressing
steel will not be less than the value shown on the authorized shop drawings.
a.Do not exceed 80 percent of the guaranteed ultimate tensile
strength of the prestressing steel during the stressing of the tendons. 1) Replace tendons stressed past 80 percent of the guaranteed ultimate tensile strength.
b.Anchor the prestressing steel at initial stresses that will result
in the long term retention of permanent forces of not less than those shown on the approved shop drawings.
c.Do not allow the initial stress at the anchorage to exceed 70
percent of guaranteed ultimate tensile strength after anchor set.
2.Remove and replace strand due to wire failure or slipping during
stressing if any of the following conditions are met:
a.Member cross section has a final effective PT force less than
98 percent of the design total PT force based on the recorded jacking force or liftoff force, whichever is smaller.
b.PT force across a mating joint is less than 98 percent of PT
force required by the contract drawings for that mating joint for that stage of construction. 1) This requirement applies to segmental construction, or similar construction that has members post- tensioned together across a common joint face at any stage of construction.
c.Any single tendon has more than a 5 percent reduction in
cross-sectional area or post-tensioning steel due to wire failure.
3.Follow stressing sequence shown in authorized shop drawings.
D.Elongations
1.Conduct the tensioning process such that tension being applied
and the elongation of the post-tensioning steel can be measured at all times.
2.Keep a permanent record of gauge pressures and tendon
elongations for each tendon.
3.Measure elongations to the nearest 1/16 inch.
Post-Tensioning Concrete
4.Preload tendons to 20 percent of their final jacking force before
beginning elongation readings to eliminate take-up in the tensioning system.
5.Mark each strand before final stressing to permit measurement of
elongation and to verify that all anchor wedges set properly.
6.The measured elongation must agree within 7 percent of the
theoretical elongation for the post-tensioned elements to verify the required tendon force, or the entire operation must be checked and the source of the error determined and remedied to the satisfaction of the Department before proceeding with the work.
a.Do not overstress the tendon to achieve the theoretical
elongation.
b.Acceptance may be achieved by force verification lift-off
tests demonstrating that the measured force is within minus 1 percent and plus 5 percent of the required force as shown if the measured elongations fall outside of the acceptable tolerance.
7.Do not cut off the stressing tails of the tendons until the elongations
have been approved by the PT system manufacturer’s representative. Within 4 hours of approval:
a.Cut prestressing steel using an abrasive saw or plasma
torch to within ¾ inch to 1½ inch from anchorage. 1) Flame cutting of PT steel is not permitted.
b.Clean rust and other debris from metal surfaces which will
be covered by the grout cap
c.Place grout cap, including a seal, over the wedge place until
the tendon is grouted.
E.Protection of Steel After Installation
1.Minor rust which may form on the surface of the prestressing steel
within 10 calendar days after protective packaging has been opened will not be cause for rejection.
2.Prestressing steel installed, tensioned, and grouted within 10
calendar days will not require the use of corrosion inhibitor in the duct following installation of the prestressing steel.
a.Blow a vapor phase corrosion inhibitor powder conforming to
MIL-PRF-3420 into ducts containing prestressing steel if prestressing steel is anticipated to be removed from protective packaging for 10 days or more before grouting.
3.Do not exceed 15 calendar days between removal of prestressing
steel from protective packaging and grouting operations.
a.Failure to begin grouting operations will result in stoppage of
work.
Post-Tensioning Concrete
3.5GROUTING
A.General
1.Begin grouting operations to fill the void space between the duct
and the tendons as soon as possible after all the prestressing steel has been tensioned, anchored and approved by the PT system manufacturer’s representative.
2.Flush the inside of the duct with water under pressure to remove all
traces of the corrosion inhibitor used to protect the prestressing steel if a vapor phase corrosion inhibitor has been blown into ducts before grouting.
a.Continue flushing operations until the discharge water is free
of traces of the corrosion inhibitor.
b.Blow all water out of the duct with oil-free compressed air
and swab dry after flushing.
3.Eliminate vibration from all sources under the contractor’s control
within 300 ft of the member being grouted for the duration of the grouting procedure and 4 hours after completion.
4.Conduct a joint meeting of the Contractor, grouting crew and the
Engineer before grouting operations begin.
a.Discuss the grouting operation plan, required testing,
corrective procedures, and other relevant issues at the meeting.
B.Temperature
1.Keep PT grout below 90 degrees F during mixing or pumping.
a.Cool the mixing water if necessary.
2.Keep ducts free of water to avoid damage due to freezing in
temperatures below 32 degrees F.
3.Keep accurate temperature records covering maximum and
minimum air temperatures, and temperatures of the concrete adjacent to the ducts to be grouted when ambient temperature may be expected to fall below 40 degrees F.
4.Do not use any material in which frost or ice is present, and keep
the ducts and equipment free of frost and ice.
5.Postpone grouting operations if frost is expected within 48 hours of
start.
6.Maintain a temperature of at least 35 degrees in the grout in the
ducts for the duration of the grouting and the longer of 72 hours after completion or until job-cured 2 inch cubes of PT grout reach a minimum compressive strength of 800 psi when low temperatures are expected and grouting cannot be postponed.
Post-Tensioning Concrete
C.Equipment
1.Use equipment which meets the requirements in Section 10.11.3 of
the AASHTO LRFD Bridge Construction Specifications.
2.Provide flushing equipment with an independent power source on
site, capable of developing a pressure of 250 psi and of sufficient capacity to flush out partially grouted ducts as required due to blockage or breakdown of equipment.
a.Do not exceed the allowable grouting pressures when
flushing. Refer to this Section, article 3.5 E7.
D.Mixing
1.Mix PT grout according to the manufacturer’s recommendations.
a.Continue mixing grout until a uniform, thoroughly blended
grout is obtained, without excessive temperature increase.
2.Agitate the grout continuously until it is pumped.
3.Do not begin grouting operations until the field trial tests specified in
PTI M55.1, Section 4.7.1 have been satisfactorily performed.
a.Do not add water to increase grout flowability that has been
decreased by delayed use of the grout.
4.Perform field mockup test specified in PTI M55.1, Section 4.7.2,
when required by the Engineer.
5.Do not exceed a water-cement ratio of 0.45.
E.Grouting Operations
1.Blow oil-free and water-free compressed air through the ducts
checking all inlet and outlet pipes to verify they are capable of accepting injection of the PT grout immediately before grouting.
2.Open all inlet and outlet ports before grouting starts.
3.Obtain target flow rates as a function of mixer type used and
ambient temperatures from the PT grout manufacturer.
a.Verify the grouting rate is slow enough to avoid air
entrapment and segregation of the grout and verify complete filling of the duct.
4.Maintain a continuous, one-way flow of PT grout in a generally
uphill direction.
a.Inject PT grout from near the lowest end of tendons.
b.Grout each tendon in one operation.
c.Flush the grout out of the duct with water immediately when
one-way flow of grout cannot be maintained or grouting is interrupted.
5.Refer to PTI M55.1, Section 4.7.3 for production test requirements
of production grout.
6.Perform normal operations at approximately 75 psi.
7.Do not exceed a pumping pressure at the tendon inlet of:
a.145 psi for internal polyethylene ducts
b.245 psi for internal circular steel ducts
Post-Tensioning Concrete
c.145 psi for external HDPE pipe
d.Close the inlet and inject the PT grout at the next outlet
(which now becomes an inlet) which has just been, or is ready to be closed, as long as a one-way flow is maintained if the actual grouting pressure exceeds the maximum allowed. 1) Fit the outlet that is to be used for injection with a positive shutoff. 2) Do not inject grout into a succeeding outlet from which grout has not yet flowed.
8.Waste grout through the first outlet after the inlet pipe until residual
water or entrapped air has been removed,
a.Cap or otherwise close outlet when the consistency of the
ejected grout is the same as the injected grout.
b.Close following remaining outlets in the same manner,
except at high points where the outlets a short distance downstream to the high point are closed before the high point outlet.
c.Discharge at least 2 gallons of grout through the final outlet
pipe before sealing.
9.Provide a standpipe at the upper end of the duct for vertical or
nearly vertical tendons.
a.Design the standpipe to collect and store bleed water and
allow it to be removed from the grout.
b.Locate the standpipe so that the level of the grout can be
brought to an elevation so that bleeding will not cause the level of the grout to drop below the highest point of the upper anchorage device.
c.Remove the standpipe after the grout has hardened.
10.Do not remove or open plugs, caps, or valves until the PT grout has
set.
a.Remove ends of inlet/outlet pipes at least 2 inches below the
concrete surface after the grout has set.
b.Fill the void with epoxy grout within 4 hours of inlet and outlet
removal.
c.Remove all miscellaneous material used for sealing grout
caps before carrying our further work to protect anchorages.
d.Permanently seal all outlet and inlet openings for external
tendons.
11.Keep grouting operation records that include the following for each
duct:
a.Names of personnel performing the grouting activity
b.Identification of tendon
c.Date grouted
d.Number of days from tendon installation to grouting
e.Quantities and types of material used
Post-Tensioning Concrete
f.The maximum pumping pressure at the inlet
g.Temperature measurements of air, water, prepackaged
material, mixture grout, and concrete member in the duct 1) Note if temperatures are within acceptable limits.
h.Summary of tests performed and the results, including
post-grouting inspection
i.Volume of grout pumped and capacity of duct accounting for
reduction for area of prestressing steel 1) Include ratio of actual grout used to anticipated quantity of grout used.
j.Time from beginning grouting operation to sealing all inlet
and outlet pipes
k.Discussions of problems encountered during grouting and
steps taken to resolve them
F.Post-Grouting Inspection
1.Randomly inspect 10 percent of the inlet and outlet pipes at
anchorage and at high points for voids by drilling and inspecting with a borescope.
a.Inspect ducts between 24 and 72 hours after grouting.
b.Use drilling equipment that will automatically shut off when
steel is encountered to prevent damaging the prestressing steel and anchorages.
c.All anchorages and high points will be inspected if a void
exposing prestressing steel is found by random drilling.
d.Fill drilled holes not indicating voids with epoxy compound
within 4 hours of completion of inspections. 1) Use an injection tube to fill drilled hole from the base.
e.Use vacuum grouting to fill voids that expose prestressing
steel. 1) Perform vacuum grouting operations under the direct supervision of a crew foreman who has been trained and has experience in the use of vacuum grouting equipment and procedures.
3.6PROTECTION OF END ANCHORAGE
A.Protect PT strand, wire, and bar anchorages as soon as practical, but not
to exceed 10 days after grouting is completed.
B.Cap inlets and outlets with plastic or stainless steel threaded plugs.
Post-Tensioning Concrete
C.Construct anchorage pour-backs with epoxy grout according to
manufacturer’s recommendations.
1.Mechanically clean and abrasive blast clean the surface of concrete
in anchorage recesses until clean aggregate is exposed.
a.Flush surface with water and blow dry.
2.Do not damage reinforcing steel coatings.
3.Test substrate at pour-back locations using ASTM C 1583 and
develop a minimum of 175 psi tension.
D.Construct pour-backs using tight fitting forms that can be installed and
held in place securely against the previously placed concrete.
1.Fill recess with epoxy grout and finish flush.
END OF SECTION
Post-Tensioning Concrete
Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.
Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 945–968 of 1,331.
View official source ↗