THIN BONDED POLYMER OVERLAY

PART 1 GENERAL

1.1SECTION INCLUDES

A.Thin bonded polymer overlay system applied to concrete bridge decks and

approach slabs

B.Removal of existing polymer overlay from concrete bridge decks and

approach slabs

C.Repair of damaged areas of a polymer overlay system

1.2RELATED SECTIONS Not Used

1.3REFERENCES

A.ASTM C 88: Soundness of Aggregates by Use of Sodium Sulfate or

Magnesium Sulfate

B.ASTM C 131: Resistance to Degradation of Small-Size Coarse Aggregate

by Abrasion and Impact in the Los Angeles Machine

C.ASTM C 566: Total Evaporable Moisture Content of Aggregate by Drying
D.ASTM C 579: Compressive Strength of Chemical-Resistant Mortars,

Grouts, Monolithic Surfacings, and Polymer Concretes

E.ASTM C 881: Epoxy-Resin-Base Bonding Systems for Concrete
F.ASTM C 1583: Tensile Strength of Concrete Surfaces and the Bond

Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-off Method)

G.ASTM D 570: Water Absorption of Plastics
H.ASTM D 638: Tensile Properties of Plastics
I.ASTM D 790: Flexural Properties of Unreinforced and Reinforced Plastics

and Electrical Insulating Materials

Thin Bonded Polymer Overlay

J.ASTM D 2240: Rubber Property – Durometer Hardness
K.ASTM D 4285: Indicating Oil or Water in Compressed Air
L.ASTM D 5821: Determining the Percentage of Fractured Particles in

Coarse Aggregate

M.ASTM D 7428: Resistance of Fine Aggregate to Degradation by Abrasion

in the Micro-Deval Apparatus

N.ASTM E 274: Skid Resistance of Paved Surfaces Using a Full-Scale Tire
O.ASTM E 1621: Elemental Analysis by Wavelength Dispersive X-Ray

Fluorescence Spectrometry

P.International Concrete Repair Institute (ICRI)

1.4DEFINITIONS

A.Polymer Overlay System – A thin bonded polymer overlay applied as a

wearing surface consisting of a two-part polymer resin broadcasted with aggregate to refusal before it cures and includes a healer/sealer primer where applicable.

B.Thin Bonded Polymer Overlay, Type I – Consists of a polymer overlay

system without healer/sealer primer.

C.Thin Bonded Polymer Overlay, Type III – Consists of a polymer overlay

system with a healer/sealer primer.

D.Installer – The entity preparing the surface and installing and finishing the

polymer overlay system

E.Provider – The manufacturer furnishing the polymer overlay system

1.5SUBMITTALS

A.Provider Qualifications for review
1.Include at least the following:
a.Company name
b.Name, phone number and experience of the Provider’s

Technical Support Representative

Thin Bonded Polymer Overlay

c.List of projects using the submitted products with at least

four years of satisfactory performance under similar environmental conditions as the project in which it is to be applied. List the following for each project: 1) Project name 2) Bridge locations (state routes, structures numbers and mile posts) 3) Scope of work 4) Products used 5) Approximate date of the system opening to traffic

B.Materials for review
1.Include at least the following:
a.Manufacturer’s Product Data Sheets and recommended

installation instructions

b.Material Safety Data Sheets
c.The Provider's certification stating that the provider is the

sole provider of the components of the polymer overlay system and that the components: 1) Comply with this Section 2) Are fully compatible with one another

d.The Installer’s certification with the Provider’s written

concurrence that the polymer overlay system is fully compatible with all deck repair materials 1) Include cure duration recommended for the deck repair material before application of the polymer resin.

2.Certified test report for information from an independent nationally

recognized laboratory stating that the polymer resins in the polymer overlay system components meet the requirements in this Section

a.Test results must be from within a three year period of the

submittal.

3.Certified Test Report for information from an AASHTO accredited

testing laboratory confirming the compliance of the aggregate material with the test requirements of this Section

a.Test results must be from within a one year period of the

submittal.

4.Manufacturer’s product data sheets for steel shot media, for

information

C.Method for existing polymer overlay removal for information
1.Include equipment information and details
D.Safety plan for polymer overlay removal and thin bonded polymer overlay

installation activities for information.

Thin Bonded Polymer Overlay

E.Method for mixing the polymer resins for information
1.The Provider’s written concurrence that the selected mixing method

is acceptable and compatible with the polymer overlay system.

a.Include description of provider proposed equipment.
2.Mixing ratio of the polymer resins.
F.A warranty letter stating that the Installer guarantees the polymer overlay

system against material and installation defects incurred under traffic for a period of 5 years.

1.The guarantee period starts on the date of Physical Completion or

written documentation of the partial acceptance of the thin bonded polymer overlay.

2.Include in the letter:
a.State Project Pin Number
b.State Project Name
c.State Structure Numbers
d.Contractor, Provider, and Installer Name
3.Defects (performance failures) include:
a.Spalling: Broken or missing pieces of polymer overlay

system

b.Scaling: Visible, exposed, rough surface texture resulting

from a loss of aggregate or resin

c.Delamination: Visible or audible debonding of the polymer

overlay system at the bond line (interface) with the existing bridge receiving surface

d.Cracking: Visible cracks not reflected from a crack in the

existing deck

e.Loss of skid resistance: Skid resistance less than 40 as

measured according to ASTM E 274

4.The guarantee covers 100 percent of the polymer overlay system

materials and installation costs including removal and replacement of the polymer overlay system for failed sections.

5.The Department will notify the Installer of defects to be repaired

during the guarantee period.

a.Submit detailed plans and procedures of corrective work

according to Provider’s recommendations and obtain the Department’s authorization before commencing work.

b.Perform corrective work within 60 days of notification unless

stated otherwise.

Thin Bonded Polymer Overlay

1.6QUALITY CONTROL

A.Technical Support Representative
1.Provide a Technical Support Representative from the Provider

onsite during surface preparation and application of the polymer overlay system on the first day the polymer overlay system is installed on a structure.

a.The Technical Support Representative must have a

minimum of 3 years of experience with the system and with guiding and assisting installers in the polymer overlay system installation.

b.The Technical Support Representative will instruct the

workers in proper mixing, application technique, safety precautions, traffic opening time, and environmental requirements.

c.The Technical Support Representative must be available for

consultation but not necessarily present at the job site for the remaining work.

d.The Department reserves the right to require the Technical

Support Representative to be onsite if at any time the Engineer is concerned with the product installation quality.

1.7DELIVERY, STORAGE, AND HANDLING

A.Polymer Resin
1.Identify the containers as Part A and Part B and plainly mark with:
a.Manufacturer’s name
b.Manufacturer’s address
c.Name of the product
d.Mixing proportions and instructions
e.Lot and batch numbers
f.Date of manufacture
g.Quantity
2.Transport to and store on the job site in a dry, weather protected

environment away from moisture, and within the maintained temperature range of 60 to 100 degrees F and according to Provider’s recommended installation instructions.

B.Broadcast Aggregate
1.Store aggregate in a clean, dry location, protected from rain and

other moisture sources.

2.Protect the aggregate from contaminants on the job site.

Thin Bonded Polymer Overlay

C.Handling Liquid Materials
1.Use protective gloves, clothing, boots, and goggles when directly

exposed to the material.

2.Provide manufacturer’s safety data sheets to workers and

inspectors.

PART 2 PRODUCTS

2.1POLYMER OVERLAY SYSTEM

A.Use a thin bonded polymer overlay system that chemically cures to

provide an impervious wearing surface consisting of the following:

1.Healer/Sealer primer for Thin Bonded Polymer Overlay, Type III
2.Polymer Resin
3.Broadcast Aggregate
B.Healer/Sealer primer, when applicable
1.Compatible with the repair materials and the polymer resin.
C.Polymer Resin
1.Two-part Epoxy-Urethane Co-Polymer that meets the requirements

of Table 1.

2.Free of fillers, volatile solvents, and external/conventional

flexibilizers.

Table 1 PHYSICAL PROPERTIES OF THE CURED POLYMER RESIN Property Value Method Compressive Strength, min. psi 5,000 ASTM C 579 (Method B) Tensile Strength, min. psi 2,000 ASTM D 638 Tensile Elongation, min. percent 30 ASTM D 638 Water Absorption, max. percent by wt. 1.0 ASTM D 570 Shore D Hardness, min. 77°F 60-75 ASTM D 2240 Gel Time @ 73°F +/- 3°F, minutes 15-45 ASTM C 881 Adhesion to Concrete 100% failure in ASTM C 1583 concrete Flexural Yield Strength, min. psi 3,000 ASTM D 790 Percent Solids 100

Thin Bonded Polymer Overlay

D.Broadcast Aggregate
1.Thoroughly washed and kiln dried to maximum moisture content of

0.2 percent by weight according to ASTM C 566.

a.Do not use recycled or reused aggregate for the first layer of

application. 1) Refer to this Section, Paragraph 3.3 E2.

2.Use basalt aggregate meeting the properties in Table 2 and the

gradation in Table 3, or use calcined bauxite aggregate meeting the properties in Table 4 and the gradation in Table 5.

Table 2 BASALT AGGREGATE PROPERTIES Magnesium Sulfate Soundness, 15% max. ASTM C 88 (5 cycles) LA Abrasion, Grade D, 20.0% max. ASTM C 131 Micro Deval Abrasion, 7.0% max. ASTM D 7428 Mohs Scale Hardness 7.0 min.

Table 3 BASALT AGGREGATE GRADATION Sieve Size Percent Passing 0.187 inch; No.4 100 0.078 inch; No.10* 10 – 35 0.033 inch; No.20 0 – 10 0.024 inch; No.30 0 – 0.2 * 100 percent of the aggregate retained on the #10 sieve has at least one mechanically fractured face according to ASTM D 5821.

Table 4 CALCINED BAUXITE AGGREGATE PROPERTIES Magnesium Sulfate Soundness, 15% max. ASTM C 88 (5 cycles) LA Abrasion, Grade D, 20.0% max. ASTM C 131 Micro Deval Abrasion, 3.0% max. ASTM D 7428 Mohs Scale Hardness 8.0 min. Aluminum Oxide, ASTM E 1621 85.0% min.

Thin Bonded Polymer Overlay

Table 5 CALCINED BAUXITE AGGREGATE GRADATION Sieve Size Percent Passing 0.187 inch; No.4 100 0.046 inch; No.16* 0-5 0.024 inch; No.30 0 – 0.2 * 100 percent of the aggregate has at least one mechanically fractured face for materials being retained on the #16 sieve according to ASTM D 5821.

2.2EQUIPMENT

A.Polymer Overlay Removal
1.Diamond grinding
a.Provide equipment utilizing diamond blades mounted on a

self-propelled machine designed for grinding and texturing pavement.

b.Hand held and small walk behind diamond grinders may be

used in areas not accessible by larger equipment.

2.Heating and scraping
a.Provide equipment capable of heating and scraping off the

existing polymer overlay system

B.Metered Mixing
1.Use equipment capable of metering, mixing, and distributing the

polymer resin.

a.Use equipment that features positive displacement

volumetric metering pumps controlled by a hydraulic power unit.

b.Use motionless, in-line mixing.
2.Use equipment that is approved by the Provider.
C.Hand Mixing
1.Use equipment that is approved by the Provider.
D.Polymer Resin Application
1.Use new 3/16 inch notched squeegee blades for the first layer on

each structure.

a.Replace notched squeegee if coverage rate does not meet

Provider’s recommendations.

Thin Bonded Polymer Overlay

E.Broadcasting Aggregate
1.Use mechanical equipment capable of dispensing the aggregate

onto the deck in a uniform manner as required by the Provider and as specified.

F.Sandblaster/Air Compressor
1.Verify air is free of water and oil according to ASTM D 4285.

2.3SHOT BLASTING

A.Use S-390 or larger steel shot media.

PART 3 EXECUTION

3.1POLYMER OVERLAY REMOVAL

A.Diamond grinding
1.Create a surface in a parallel, corduroy-type texture consisting of

grooves with the following dimensions:

a.Width: 1/16 to ¼ inch
b.Depth: 1/16 inch
c.Spacing: 1/16 to ¼ inch
2.Limit deviations to an ⅛ inch from the lower edge of a 10 ft

straightedge after grinding.

3.The textured pattern is not required in locations where hand held

and walk behind diamond grinders are used.

B.Heating and scraping
1.Do not damage the concrete substrate.
2.Polymer overlay residue remaining after the heating and scraping

operation must be thin enough to be fully removed during surface preparation.

3.Difficult to remove resin within tining may remain.

3.2SURFACE PREPARATION

A.Remove paint markings, visible grease, oils, and other surface

contaminants prior to shot-blasting.

1.Follow manufacturer recommendations when using solvents to

remove contaminants.

2.Complete deck repairs before shot-blasting.

Thin Bonded Polymer Overlay

B.Shot-blast concrete surface to produce a surface relief that meets the ICRI

Surface Preparation CSP 5-7.

1.Use sandblasting equipment or mechanical grinders only in areas

that cannot be reached with steel shot-blasting.

2.Refer to http://www.udot.utah.gov/go/standardsreferences for a

CSP Examples document.

C.Remove dust or debris just before application of the resin with

compressed air.

D.Protect expansion joints, cold joints, grates, drains and other elements

which may not perform adequately if in contact with hardened resin.

E.Do not allow traffic on the deck that has been shot-blasted.
1.Only allow the polymer overlay system equipment on cleaned

surfaces.

3.3APPLICATION

A.Limitations
1.Do not apply the polymer overlay system when it has rained within

24 hours or is expected to rain within 8 hours of application.

2.Verify the concrete substrate is dry before applying the polymer

overlay system.

a.Measure moisture content with an electronic concrete

moisture meter at three locations on the bridge deck to be covered by the polymer overlay system. 1) Take measurements at the beginning, middle, and end of the coverage area.

b.Measure moisture content with a concrete moisture meter at

each structural pothole patch location to be covered by the polymer overlay system.

c.Do not apply the polymer overlay system if one or more

measurements exceed 4.0 percent.

3.Apply when the outside air temperature is above 50 degrees F and

will remain above 50 degrees F per the manufacturer's recommended cure time.

4.Application over new surfaces
a.Allow newly placed concrete to cure for at least 28 calendar

days before beginning installation of polymer overlay system.

b.Allow newly placed rapid setting mortar materials to cure for

at least eight hours, or as recommended by the rapid setting mortar manufacturer, before beginning installation of polymer overlay system. Thin Bonded Polymer Overlay

5.Application to bridges constructed offline and moved into their final

location by self propelled modular transporters (SPMT)

a.Apply the polymer overlay system no sooner than 30

calendar days after setting the bridge in its final location.

B.Mixing Polymer Resin
1.Condition resin material to the proper temperature according to the

Provider’s recommendations.

2.Use metered mixing equipment to measure and mix the polymer

resin components as recommended by the Provider.

a.Maintain mix ratios according to the Provider's

recommendations.

b.Hand mixing polymer resin may be performed in repair areas

and areas with limited access.

3.Mix polymer resin immediately before dispensing.
4.Verify the mix ratio by volumetric sampling immediately before

beginning the application.

a.Use containers with graduated markings with not less than 5

gallon capacity.

b.Remove the static mixer and dispense each component into

separate containers. 1) Dispense at least five gallons of the primary component for ratio comparison. 2) Uncontaminated samples may be returned to the reservoirs they were originally dispensed from.

c.The Engineer or Technical Support Representative may

request additional sampling.

C.Application of Polymer Resin
1.Apply healer/sealer primer according to the Provider’s

recommended installation instructions when placing a Thin Bonded Polymer Overlay, Type III.

a.Apply polymer resin while the healer/sealer primer is still

wet.

2.Evenly distribute the polymer resin at the rate recommended by the

Provider.

D.Broadcasting Aggregate
1.Broadcast the aggregate before the polymer begins to gel.
a.Do not exceed the maximum time limits in Table 6 between

the application of polymer resin and broadcasting the aggregate, unless otherwise directed by the provider’s technical representative.

Thin Bonded Polymer Overlay

Table 6 Time Limits Temperature Maximum Time Above 90°F 10 minutes 80°F to 90°F 15 minutes 70°F to 80°F 20 minutes 60°F to 70°F 25 minutes 50°F to 60°F 35 minutes

2.Cover the surface until no wet spots remain.
a.Continue to broadcast aggregate over individual wet spots.
b.Do not place piles of aggregate.
3.Drop the aggregate vertically.
a.Do not project aggregate toward live traffic.
E.Remove Excess Aggregate
1.Completely remove excess and loose aggregate by vacuum or with

compressed air after the overlay has hardened and before applying subsequent layers.

a.Remove dust and debris with compressed air.
2.Do not reuse removed excess aggregate for subsequent layers

unless the following criteria is met:

a.Aggregate is removed directly into containers
b.Aggregate is screened to required gradation specified in

Table 3 and Table 5

c.Aggregate is stored free of contaminants
F.Apply Successive Layer of Overlay
1.Provide at least two layers.
2.Longitudinal Joints in the Overlay
a.Stagger and overlap joints between successive layers 6 to

12 inches so that no ridges appear between two adjacent lanes.

b.Maintain straight construction joints between adjacent

placements and layers.

3.Provide a total overlay thickness of at least 3/8 inch when using

Basalt aggregate.

G.Traffic
1.Do not allow vehicles on the polymer overlay while it is curing.
2.Traffic may be allowed on the final layer or on non-final layers after

the resin has cured, as determined by the Provider

a.Remove excess and loose aggregate before allowing traffic

on the thin bonded polymer overlay system.

Thin Bonded Polymer Overlay

b.Brush blast the surface with shot blast according to the

Provider’s recommendations before applying additional layers when traffic has been allowed on the cured surface between layers.

H.Final Cleanup
1.Remove excess and loose aggregate by vacuum or sweeper truck

two weeks after traffic has been on the polymer overlay.

2.Completely remove aggregate from joints.

3.4POLYMER OVERLAY REPAIR

A.Locate and mark polymer overlay repair areas as shown and in the

presence of the Engineer.

1.Delaminated areas
a.Sound the polymer overlay around repair area for

delamination of the polymer overlay to determine repair limits.

2.Polished areas
a.Polished areas are identified as areas where minimal

aggregate remains.

b.Treat gouges which reduce the overall thickness of the

polymer overlay to less than 1/8 inch as polished areas.

3.Square off and mark the edges of polymer overlay system repair

area six inches beyond the determined limits and parallel to the travel lane.

B.Saw cut ½ inch deep saw cut along the marked edges of repair areas.
C.Remove existing polymer overlay within the repair area according to this

Section, Article 3.1.

D.Prepare the deck surface within the repair area according to this Section,

Article 3.2.

E.Apply the polymer overlay system within the repair area according to this

Section, Article 3.3 and Article 3.4.

3.5PROTECTION

A.Prevent sandblasting material and debris from falling into waterways,

pedestrian areas, traffic areas, or onto railroad tracks.

END OF SECTION

Thin Bonded Polymer Overlay

Get an email when 03372 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 1028–1040 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 03372 — Thin Bonded Polymer Overlay. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.