B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Concrete (03000-03999)

03932Concrete Slope Protection Repair

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. February 16, 2023Book pages 1097–1100 Save this section

Ask about Section 03932

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

CONCRETE SLOPE PROTECTION REPAIR

PART 1 GENERAL

1.1SECTION INCLUDES

A.Repair of concrete slope protection and cutoff wall

1.2RELATED SECTIONS

A.Section 02056: Embankment, Borrow, and Backfill
B.Section 03055: Portland Cement Concrete
C.Section 03152: Concrete Joint Control
D.Section 03211: Reinforcing Steel and Welded Wire
E.Section 03310: Structural Concrete
F.Section 03390: Concrete Curing

1.3REFERENCES

A.ASTM C 578: Rigid, Cellular Polystyrene Thermal Insulation
B.ASTM D 4285: Indicating Oil or Water in Compressed Air
C.ASTM D 5249: Backer Material for Use with Cold- and Hot-Applied Joint

Sealants in Portland-Cement Concrete and Asphalt Joints

1.4DEFINITIONS Not Used

1.5SUBMITTALS

A.Manufacturer’s product data sheets and recommended installation

instructions for review.

Concrete Slope Protection Repair

PART 2 PRODUCTS

2.1MATERIALS

A.Concrete – Class A(AE). Refer to Section 03055.
B.Reinforcing Steel
1.Coated reinforcing steel or coated welded wire according to Section

03211.

C.Backer Rod
1.Size the diameter of the backer rod to be 25% to 50% larger than

opening at time of installation. For example:

a.0.5 inch backer rod for 3/8 inch opening
b.0.625 inch backer rod for ½ inch opening
c.1 inch backer rod for ¾ inch opening
d.1.25 inch backer rod for 1 inch opening
2.Use a closed cell, polyethylene-foam rod joint filler.
a.Meet the requirements of ASTM D 5249 Type 1 or Type 3.
D.Rigid Plastic Foam
1.Refer to ASTM C 578.
2.Type 9, Density of 2 lb/ft3.
E.Joint Sealer (Structures)
1.Refer to Section 03152.
F.Embankment Material
1.Refer to Section 02056.

2.2EQUIPMENT

A.Sandblaster/Air Compressor
1.Verify air is free of water and oil according to ASTM D 4285.
B.Jackhammer
1.30 lb class or smaller

PART 3 EXECUTION

3.1CONCRETE REMOVAL

A.Make 1/2 inch deep saw cuts to define the work area unless shown

otherwise.

Concrete Slope Protection Repair

B.Remove the concrete in work areas.
1.Use 30 lb class jackhammer or smaller.
2.Protect reinforcing steel to remain.
C.Sandblast clean exposed reinforcing steel and concrete surfaces before

placing new concrete.

3.2EMBANKMENT PREPARATION

A.Prepare the area to be repaired.
1.Smooth and shape the berms and slopes.
2.Fill depressions with embankment material, grade, and compact.
3.Firmly compact the embankment material.

3.3PLACE RIGID PLASTIC FOAM

A.Place rigid plastic foam material 1 inch thick against the surface of all

structural members before placing the concrete slope protection.

B.Anchor the rigid plastic foam in place with a compatible adhesive.
C.Recess the rigid plastic foam in the joints against structural members so a

groove is formed above the rigid plastic foam filler as shown.

3.4PLACE REINFORCING STEEL

A.Place reinforcing steel or welded wire when shown according to Section

03211.

B.Install doweled anchors when shown according to Section 03211.

3.5PLACE CONCRETE

A.Thoroughly wet the surface with water before placing the concrete.
1.Remove standing water before placing concrete.
B.Keep the repair area clean until concrete has been placed.
C.Place concrete a maximum of 7 days after removing the existing concrete

slope protection unless otherwise determined by the Engineer. Refer to

D.Make concrete of a consistency so it can be placed on the slopes without

deformation.

Concrete Slope Protection Repair

E.Re-establish the original joint and scoring design unless shown otherwise.
F.Place entire slope protection during one placement.
1.Use a construction joint located in a scoring or at the junction of the

slope and the abutment if it is not feasible to complete in a single placement.

3.6FINISH AND CURE CONCRETE

A.Use a Floated Surface Finish.
1.Refer to Section 03310.
B.Cure Concrete.
1.Refer to Section 03390.

3.7SEAL JOINTS AND CLOSURES

A.Completely remove curing compounds, oil, grease, dirt, and any other

foreign materials from concrete surfaces in the joints by sandblasting.

1.Provide concrete surfaces in the joints that are clean and dry when

backer and sealant are placed.

B.Place the backer rod and Joint Sealer (Structures) when the concrete has

properly cured.

C.Place the joint sealer (structures) with caulking guns in joints after placing

the backer rod and in the recess above the rigid plastic foam as shown.

1.Apply the sealant when the substrate is at least 50 degrees F and

ambient air temperature is not forecast to fall below 50 degrees F for at least 8 hours after application of sealant.

2.Seal joints and grooves in one continuous direction.
3.Tool the sealant using a concave pointing tool with soap solution

until the joints and recess are sealed over completely.

4.Finish sealant in a neat and clean fashion.
a.Verify there are no irregular surfaces including peaks and

valleys.

b.Remove sealant outside of the joint.

3.8PROTECTION

A.Prevent sandblasting material and debris from falling into waterways,

pedestrian areas, traffic areas, or onto railroad tracks.

END OF SECTION Concrete Slope Protection Repair

Get an email when 03932 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 1097–1100 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 03932 — Concrete Slope Protection Repair. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.