SECTION 602—TOPSOIL
602.01 Description
This work shall consist of applying topsoil in accordance with these specifications and in conformity with the depths and limits shown on the plans or as established by the Engineer. In the case of Class B topsoil this work shall also involve furnishing topsoil to the project site.
602.02 Materials
602.03 Procedures
602.04 Measurement and Payment
Topsoil will be measured in acres of surface area computed to the nearest 0.1 acre and will be paid for at the contract unit price per acre for the class and depth specified. For smaller areas, and those areas 601.04