Effective with the December 2018 Letting 129 2019 Standard Spec ifications Section 313 Pit Run
313.1Description
improvement.
313.2Materials
retained on the 1 1/2 sieve, wit h the remaining material composed of sand with a nominal quantity of silt/clay. The maximum size of an individual piece cannot be mo re that 2/3 of the specified individual layer thickness. Obtain material from a department-approved sou rce substantially free of topsoil, organic materials, and other deleterious materials.
soundness on record. The engineer may also approve other sources conforming to the following criteria:
engineer’s judgem ent, conform to 313.2(1) .
The engineer may reject material produced from any pit with exc essive non-durable rock such as sandstone, shale, slate, disintegrated granite, or heavily weathered rock.
to 311.2 , or select crushed material conforming to 312.2 for pit run material.
313.3Construction
in the aggregate during placing, shaping, and compacting to pre vent segregation and achieve adequate compaction.
layers to address so ft foundation conditions . Compact pit run u sing standard compaction conforming to 301.3.4.2 .
313.4Measurement
313.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
313.0110 Pit Run TON
15 Pit Run CY
inch base, breaker run, or select crushed material for pit run as allowed under 313.2 , the department will pay for that material at the Pit Run unit price.
Effective with the December 2018 Letting 130 2019 Standard Spec ifications Section 315 Asphaltic Base
315.1Description
315.2Materials
material and mixture requirements specified for asphaltic surface in 465.
315.3Construction
315.3.1 General
here in 315.3. Place the mixture in 4-inch or thinner compacted layers unless the engineer directs otherwise. 315.3.2 Asphaltic Base Widening
asphaltic base, reconstruct the shoulder and slope to the grade and cross-section the plans show. Unless the engineer directs other wise, reconstruct using the pr eviously excavated material. Dispose of unused material as specified in 205.3.12 .
widening precludes using trench rollers and other conventional equipment, prepare and compact the foundation using engineer- approved hand methods.
surfacing, unless the contract specifies otherwise. Construct i n successive layers until the top surface is flush with the adjacent pavement surface. Before allowing th e asphaltic mixture to cool; place, spread, strike off, and compact the material.
base widening precludes using the equipment specified in 450.
315.4Measurement
completed as specified for asphaltic pavement in 450.4 .
separately. 315.5 Payment
items: ITEM NUMBER DESCRIPTION UNIT
315.0100 Asphaltic Base TON
315.0200 Asphaltic Base Widening TON
design, when required; for providing and placing the mixture, including reclaime d asphalt; and for compacting the mixture.
disposing of surplus or unsuitable excavated material.