General Provisions (00100-00999)

313Pit Run

WI · 2019 Standard SpecificationsBook pages 138138View official source ↗

Effective with the December 2018 Letting 129 2019 Standard Spec ifications Section 313 Pit Run

313.1Description

(1)This section describes providing pit run material used primarily for subgrade correction and

improvement.

313.2Materials

(1)Furnish a homogenous mixture of naturally occurring material that has at least 50 percent by weight

retained on the 1 1/2 sieve, wit h the remaining material composed of sand with a nominal quantity of silt/clay. The maximum size of an individual piece cannot be mo re that 2/3 of the specified individual layer thickness. Obtain material from a department-approved sou rce substantially free of topsoil, organic materials, and other deleterious materials.

(2)A department-approved source i s a pit with acceptable departme nt test results for wear and

soundness on record. The engineer may also approve other sources conforming to the following criteria:

1.The deposit is of suitable te xture and composition to produce crushed and graded aggregates that, in the

engineer’s judgem ent, conform to 313.2(1) .

2.The material in the deposit, in the engin eer’s judgement, i s sound, hard, and durable.
(3)The department will assess pit run acceptability based primarily on the engineer's visual inspection.

The engineer may reject material produced from any pit with exc essive non-durable rock such as sandstone, shale, slate, disintegrated granite, or heavily weathered rock.

(4)The contractor may substitute 3-inch dense-graded base conforming to 305.2 , breaker run conforming

to 311.2 , or select crushed material conforming to 312.2 for pit run material.

313.3Construction

(1)Place pit run where the plans show or as the engineer directs. Ensure that there is adequate moisture

in the aggregate during placing, shaping, and compacting to pre vent segregation and achieve adequate compaction.

(2)Spread and compact pit run in co mpacted layers of 16-inches or less. The engineer may allow thicker

layers to address so ft foundation conditions . Compact pit run u sing standard compaction conforming to 301.3.4.2 .

313.4Measurement

(1)The department will measure the Pi t Run bid items by the ton o r cubic yard acceptably completed.

313.5Payment

(1)The department will pay for measured quantities at the contrac t unit price under the following bid

items: ITEM NUMBER DESCRIPTION UNIT

313.0110 Pit Run TON

15 Pit Run CY

(2)Payment for Pit Run is full comp ensation for providing pit run material. If the contractor substitutes 3-

inch base, breaker run, or select crushed material for pit run as allowed under 313.2 , the department will pay for that material at the Pit Run unit price.

Effective with the December 2018 Letting 130 2019 Standard Spec ifications Section 315 Asphaltic Base

315.1Description

(1)This section describes constru cting a plant mixed asphaltic base for overlaying with new pavement.

315.2Materials

(1)Furnish one-inch nominal size aggregate graded as specified in 460.2.2.3 and conform to the other

material and mixture requirements specified for asphaltic surface in 465.

315.3Construction

315.3.1 General

(1)Conform to the general requirements for asphaltic pavements sp ecified in 450, except as modified

here in 315.3. Place the mixture in 4-inch or thinner compacted layers unless the engineer directs otherwise. 315.3.2 Asphaltic Base Widening

(1)Excavate and widen the existing shoulder to accommodate the ba se widening. After placing the

asphaltic base, reconstruct the shoulder and slope to the grade and cross-section the plans show. Unless the engineer directs other wise, reconstruct using the pr eviously excavated material. Dispose of unused material as specified in 205.3.12 .

(2)Prepare the foundation for the asphaltic base mixture as speci fied in 211. If the width of the base

widening precludes using trench rollers and other conventional equipment, prepare and compact the foundation using engineer- approved hand methods.

(3)Place the mixture to the thic kness of the existing abutting pa vement, including the existing asphaltic

surfacing, unless the contract specifies otherwise. Construct i n successive layers until the top surface is flush with the adjacent pavement surface. Before allowing th e asphaltic mixture to cool; place, spread, strike off, and compact the material.

(4)The engineer may allow other spr eading and compacting methods and equipment if the width of the

base widening precludes using the equipment specified in 450.

315.4Measurement

(1)The department will measure Asphaltic Base and Asphaltic Base Widening by the ton acceptably

completed as specified for asphaltic pavement in 450.4 .

(2)The department will not measure asphaltic materials, required for and incorporated in the mixture,

separately. 315.5 Payment

(1)The department will pay for measured quantities at the contrac t unit price under the following bid

items: ITEM NUMBER DESCRIPTION UNIT

315.0100 Asphaltic Base TON

315.0200 Asphaltic Base Widening TON

(2)Payment is full compensation fo r preparing the foundation; for providing an asphaltic base mixture

design, when required; for providing and placing the mixture, including reclaime d asphalt; and for compacting the mixture.

(3)Payment for Asphaltic Base Widening also includes excavating, reconstructing earth shoulders, and

disposing of surplus or unsuitable excavated material.

Source: Wisconsin Standard Specifications for Highway and Structure Construction, 2019 Edition. Pages 138138 of 601.