B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Millcreek, Utah Building Permit Cost Calculator

Estimates permit cost in Millcreek from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Valuation less than $2,000
Flat fee $76.50
$76.50
○Valuation $2,001 to $25,000: first $2,000
Flat fee $76.50
$76.50
○Each additional $1,000 from $2,001 to $25,000
Flat fee $16.50
$16.50
○Valuation $25,001 to $50,000: first $25,000
Flat fee $456.00
$456.00
○Each additional $1,000 from $25,001 to $50,000
Flat fee $12.00
$12.00
○Valuation $50,001 to $100,000: first $50,000
Flat fee $765.00
$765.00
○Each additional $1,000 from $50,001 to $100,000
Flat fee $8.50
$8.50
○Valuation $100,001 to $500,000: first $100,000
Flat fee $1,181.00
$1,181.00
○Each additional $1,000 from $100,001 to $500,000
Flat fee $6.50
$6.50
○Valuation $500,001 to $1,000,000: first $500,000
Flat fee $3,781.00
$3,781.00
○Each additional $1,000 from $500,001 to $1,000,000
Flat fee $5.50
$5.50
○Valuation over $1,000,001: first $1,000,000
Flat fee $6,531.00
$6,531.00
○Each additional $1,000 over $1,000,000
Flat fee $4.50
$4.50
○Plan review, hourly
Flat fee $120.00
$120.00
○Re-inspection
Flat fee $75.00
$75.00
○Overtime, after hour or same day inspection
Flat fee $120.00
$120.00
Building without a permit penalty · add-on
100% of the building permit fee — select the permit fee line above to calculate
see rule
Canceled building permit fee
25%
see rule
○Board of appeals hearing
Flat fee $300.00
$300.00
How this jurisdiction calculates the fee

Stepped valuation table based on the current ICC valuation table. Plan review is 40% of the building permit fee for residential and 65% for commercial, and a 1% state surcharge applies to building fees.

Source: published fee schedule · Verified 9/15/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Value of project less than $2,000
Flat fee $76.50
$76.50
Value of project $2,001 to $25,000
$76.50 for the first $2,000 + $16.50 for each additional $1,000 or fraction thereof
see rule
Value of project $25,001 to $50,000
$456 for the first $25,000 + $12 for each additional $1,000 or fraction thereof
see rule
Value of project $50,001 to $100,000
$765 for the first $50,000 + $8.50 for each additional $1,000 or fraction thereof
see rule
Value of project $100,001 to $500,000
$1,181 for the first $100,000 + $6.50 for each additional $1,000 or fraction thereof
see rule
Plan Review Fee (Residential) · add-on
40% of Building Permit Fee — select the permit fee line above to calculate
see rule
Plan Review Fee (Commercial) · add-on
65% of Building Permit Fee — select the permit fee line above to calculate
see rule
Plan Review Fee (Hourly)
$120.00/hour
see rule
Applicable State Surcharge on all permits · add-on
1% of Building Fees — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

Charged as a building permit from the stepped valuation table based on the current ICC valuation table; the city publishes no flat deck fee. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. The Millcreek FY26 Consolidated Fee Schedule (DocumentCenter/View/5286, 8 pages, footer dated 11/12/2025) was downloaded and read in full this pass. It publishes no flat deck or patio line; item 1 Building Permit and item 6 Retaining Wall Permit are both priced "*Based on current ICC Valuation Table", and the schedule then prints its own BUILDING PERMIT AND INSPECTION FEES VALUATION TABLE, reproduced below verbatim. LAYOUT NOTE for future passes: in this PDF each bracket's base amount is printed on the line ABOVE its bracket label, so a same-line read pairs every base with the wrong bracket; the pairing below follows the printed base-then-label order.

Source: published fee schedule · Verified 9/15/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Mechanical, electrical or plumbing permit
Flat fee $70.00
$70.00
○Each additional appliance or fixture
Flat fee $20.00
$20.00
○Base solar permit
Flat fee $70.00
$70.00
○Solar plan review
Flat fee $100.00
$100.00
How this jurisdiction calculates the fee

Flat fee charged under the combined mechanical, electrical and plumbing permit category, which includes circuits, electrical service charge, power to panel and temporary panel, with an additional charge per extra appliance or fixture.

Source: published fee schedule · Verified 9/15/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Site plan approval for signs, fences and accessory buildings, excluding ADUs
Flat fee $100.00
$100.00
How this jurisdiction calculates the fee

Charged as a building permit from the stepped valuation table; a separate site plan approval fee applies to signs, fences and accessory buildings excluding ADUs. | 2026-09-14 (lane B run 1068): SUCCESSOR DOCUMENT LOCATED AND CHECKED, NO CHANGE. DocumentCenter/View/5286 still serves the FY26 Consolidated Fee Schedule (byte-identical to View/5836, "FY26 Amended Fee Schedule 11.12.25"), so the permalink is one fiscal year behind its label. Millcreek publishes no stand-alone FY27 fee schedule; the FY27 schedule is an appendix inside the FY27 Adopted Budget at millcreekut.gov/DocumentCenter/View/6497 (pages 64-73, image-only, read by OCR at 400dpi). Item 138 "Site Plan Approval for Signs, Fences, and Accessory Buildings, Excluding Accessory Dwelling Units" is $100.00 in the FY27 appendix, identical to FY26, and the building valuation table is unchanged. Row numbering shifts after item 138 in FY27 because a "Sensitive Lands - Level 2" row was inserted, so match Millcreek lines by description, never by item number across years. FOR FUTURE PASSES: check View/6497 (or its successor budget), not only View/5286. 2026-09-17 (lane B run 1390, pipeline run 94): FISCAL-YEAR SUCCESSOR HUNT DRIVEN TO AN ANSWER, NEGATIVE. The cited document is headed "MILLCREEK FY26 CONSOLIDATED FEE SCHEDULE" and footed 11/12/2025, i.e. a fiscal year that ended 2026-06-30, so a FY27 edition was hunted specifically. Millcreek's own document search returns only FY25 (View/4398, View/5308, View/5495) and FY26 (View/5286, and an identical byte-size copy at View/5836) - no FY27 schedule is published anywhere on millcreekut.gov. The cited URL still returns the FY26 PDF (851,427 bytes; note that a HEAD request to this CivicPlus DocumentCenter path returns 404 while GET returns 200, so a HEAD-only reachability check would falsely report it gone). FY26 is therefore the latest edition the city publishes and the stored figures stand. RE-CHECK: a Millcreek FY27 schedule is overdue and is a live supersession candidate for the next pass.

Source: published fee schedule · Verified 11/9/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Re-roof, residential
Flat fee $70.00
$70.00
○Re-roof, commercial, $1 to $9,999
Flat fee $150.00
$150.00
○Re-roof, commercial, $10,000 to $49,999
Flat fee $300.00
$300.00
○Re-roof, commercial, $50,000 and up
Flat fee $500.00
$500.00
How this jurisdiction calculates the fee

Flat fee for residential re-roofs; commercial re-roofs are banded by valuation.

Source: published fee schedule · Verified 9/15/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Value of project less than $2,000
Flat fee $76.50
$76.50
Value of project $2,001 to $25,000
$76.50 for the first $2,000 + $16.50 for each additional $1,000 or fraction thereof
see rule
Value of project $25,001 to $50,000
$456 for the first $25,000 + $12 for each additional $1,000 or fraction thereof
see rule
Value of project $50,001 to $100,000
$765 for the first $50,000 + $8.50 for each additional $1,000 or fraction thereof
see rule
Value of project $100,001 to $500,000
$1,181 for the first $100,000 + $6.50 for each additional $1,000 or fraction thereof
see rule
Plan Review Fee (Residential) · add-on
40% of Building Permit Fee — select the permit fee line above to calculate
see rule
Plan Review Fee (Commercial) · add-on
65% of Building Permit Fee — select the permit fee line above to calculate
see rule
Plan Review Fee (Hourly)
$120.00/hour
see rule
Applicable State Surcharge on all permits · add-on
1% of Building Fees — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

Retaining wall permits are charged from the stepped valuation table based on the current ICC valuation table; the city publishes no flat retaining wall fee. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. The Millcreek FY26 Consolidated Fee Schedule (DocumentCenter/View/5286, 8 pages, footer dated 11/12/2025) was downloaded and read in full this pass. It publishes no flat deck or patio line; item 1 Building Permit and item 6 Retaining Wall Permit are both priced "*Based on current ICC Valuation Table", and the schedule then prints its own BUILDING PERMIT AND INSPECTION FEES VALUATION TABLE, reproduced below verbatim. LAYOUT NOTE for future passes: in this PDF each bracket's base amount is printed on the line ABOVE its bracket label, so a same-line read pairs every base with the wrong bracket; the pairing below follows the printed base-then-label order.

Source: published fee schedule · Verified 9/15/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Site plan approval for signs, fences and accessory buildings, excluding ADUs
Flat fee $100.00
$100.00
How this jurisdiction calculates the fee

Charged as a building permit from the stepped valuation table; a separate site plan approval fee applies to signs, fences and accessory buildings excluding ADUs. | 2026-09-14 (lane B run 1068): SUCCESSOR DOCUMENT LOCATED AND CHECKED, NO CHANGE. DocumentCenter/View/5286 still serves the FY26 Consolidated Fee Schedule (byte-identical to View/5836, "FY26 Amended Fee Schedule 11.12.25"), so the permalink is one fiscal year behind its label. Millcreek publishes no stand-alone FY27 fee schedule; the FY27 schedule is an appendix inside the FY27 Adopted Budget at millcreekut.gov/DocumentCenter/View/6497 (pages 64-73, image-only, read by OCR at 400dpi). Item 138 "Site Plan Approval for Signs, Fences, and Accessory Buildings, Excluding Accessory Dwelling Units" is $100.00 in the FY27 appendix, identical to FY26, and the building valuation table is unchanged. Row numbering shifts after item 138 in FY27 because a "Sensitive Lands - Level 2" row was inserted, so match Millcreek lines by description, never by item number across years. FOR FUTURE PASSES: check View/6497 (or its successor budget), not only View/5286. 2026-09-17 (lane B run 1390, pipeline run 94): FISCAL-YEAR SUCCESSOR HUNT DRIVEN TO AN ANSWER, NEGATIVE. The cited document is headed "MILLCREEK FY26 CONSOLIDATED FEE SCHEDULE" and footed 11/12/2025, i.e. a fiscal year that ended 2026-06-30, so a FY27 edition was hunted specifically. Millcreek's own document search returns only FY25 (View/4398, View/5308, View/5495) and FY26 (View/5286, and an identical byte-size copy at View/5836) - no FY27 schedule is published anywhere on millcreekut.gov. The cited URL still returns the FY26 PDF (851,427 bytes; note that a HEAD request to this CivicPlus DocumentCenter path returns 404 while GET returns 200, so a HEAD-only reachability check would falsely report it gone). FY26 is therefore the latest edition the city publishes and the stored figures stand. RE-CHECK: a Millcreek FY27 schedule is overdue and is a live supersession candidate for the next pass.

Source: published fee schedule · Verified 11/9/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Mechanical, electrical or plumbing permit including water heater
Flat fee $70.00
$70.00
○Each additional appliance or fixture
Flat fee $20.00
$20.00
How this jurisdiction calculates the fee

Flat fee charged under the combined mechanical, electrical and plumbing permit category, which expressly includes water heaters, with an additional charge per extra appliance or fixture.

Source: published fee schedule · Verified 9/15/2026

See the full write-up: Millcreek building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.