Home / Calculators / Building Permit Fee Calculator

Ogden, Utah Building Permit Cost Calculator

Estimates permit cost in Ogden from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total valuation $1.00 to $1,200.00
Flat fee $70.50
$70.50
○Commercial or residential plan review submittal fee
Flat fee $70.50
$70.50
○Over the counter plan review
Flat fee $47.00
$47.00
○Additional inspections not included in the technical code base fee schedule, per hour
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions, per hour
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Per Ogden Municipal Code section 4-6-1, permit fees are set by total permit valuation: $1.00 to $1,200.00 is $70.50; $1,201 to $2,000 is $70.50 for the first $1,200 plus $2.78 per $100; $2,001 to $25,000 is $92.75 for the first $2,000 plus $16.00 per $1,000; $25,001 to $50,000 is $460.75 for the first $25,000 plus $11.50 per $1,000; $50,001 to $100,000 is $748.25 for the first $50,000 plus $8.00 per $1,000; $100,001 to $500,000 is $1,148.25 for the first $100,000 plus $6.30 per $1,000; $500,001 to $1,000,000 is $3,668.25 for the first $500,000 plus $5.25 per $1,000; and $1,000,001 and up is $6,293.25 for the first $1,000,000 plus $4.00 per $1,000. Plan review is 65% of the technical code base fee schedule, or the actual cost of performing the review if less.

Source: published fee schedule · Verified 9/18/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total permit valuation $1.00 to $1,200.00 (lowest bracket of the Ogden Municipal Code 4-6-1 building permit fee table)
Flat fee $70.50
$70.50
○Plan review submittal fee, commercial and residential (Building Inspections FAQ)
Flat fee $70.50
$70.50
○Over the counter plan review (Ogden Municipal Code 4-6-1)
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions to plans, per hour (Ogden Municipal Code 4-6-1)
Flat fee $47.00
$47.00
○Additional inspections not included in technical code base fee schedule, per hour (Ogden Municipal Code 4-6-1)
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Ogden has no separate deck fee line. A deck permit is priced off the city's general valuation-based building permit fee table in Ogden Municipal Code 4-6-1 (hosted on American Legal), which runs from the lowest valuation bracket up to a per-thousand rate for large projects. Plan review is charged at 65% of the technical code base fee schedule, or the actual cost of performing the review if that is less. A plan review submittal fee is collected up front per the Building Inspections FAQ.

Source: published fee schedule · Verified 9/18/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total permit valuation $1.00 to $1,200.00 (minimum permit fee)
Flat fee $70.50
$70.50
Total permit valuation $1,201 to $2,000
$70.50 for the first $1,200 plus $2.78 per $100 or fraction thereof
see rule
○Total permit valuation $2,001 to $25,000
$2,000.00 base plus $16.00 x 250 = $6,000.00
$6,000.00
○Total permit valuation $25,001 to $50,000
$25,000.00 base plus $11.50 x 250 = $27,875.00
$27,875.00
○Total permit valuation $50,001 to $100,000
$50,000.00 base plus $8.00 x 250 = $52,000.00
$52,000.00
○Total permit valuation $100,001 to $500,000
$100,000.00 base plus $6.30 x 250 = $101,575.00
$101,575.00
Plan review fee · add-on
65% of the technical code base fee schedule, or the actual cost of the review if less — select the permit fee line above to calculate
see rule
○Over the counter plan review
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions, per hour
Flat fee $47.00
$47.00
○Additional inspections not included in the technical code base fee schedule, per hour
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Ogden does not publish a flat electrical permit fee; fees are calculated from the total permit valuation table in Ogden Municipal Code section 4-6-1, with a minimum of $70.50 for valuations of $1.00 to $1,200.00. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. Ogden Municipal Code 4-6-1 was read in full this pass; it is current through Ord. 2026-6 dated 5-5-2026. Every bracket of the technical code base fee schedule is reproduced below verbatim. Ogden publishes no flat fee for this permit type, so the valuation table IS the published price.

Source: published fee schedule · Verified 9/15/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Fence permit
Flat fee $0.00
$0.00
How this jurisdiction calculates the fee

Ogden states that fence permits are no cost. 2026-09-17 (lane B run 1390, pipeline run 94): VERIFIED VERBATIM, closing the item run 1291 left open as "not reached". ogdencity.gov/192/Permit-Requirements was downloaded and read in full today and prints, under Permit Examples: "Parking Slabs and Fence Installations (Parking Slabs and Fence Permits Are No Cost)". The stored $0 fence permit is exactly what the city publishes. No successor document and no fee change.

Source: published fee schedule · Verified 11/9/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total permit valuation $1.00 to $1,200.00 (minimum permit fee)
Flat fee $70.50
$70.50
Total permit valuation $1,201 to $2,000
$70.50 for the first $1,200 plus $2.78 per $100 or fraction thereof
see rule
○Total permit valuation $2,001 to $25,000
$2,000.00 base plus $16.00 x 250 = $6,000.00
$6,000.00
○Total permit valuation $25,001 to $50,000
$25,000.00 base plus $11.50 x 250 = $27,875.00
$27,875.00
○Total permit valuation $50,001 to $100,000
$50,000.00 base plus $8.00 x 250 = $52,000.00
$52,000.00
○Total permit valuation $100,001 to $500,000
$100,000.00 base plus $6.30 x 250 = $101,575.00
$101,575.00
Plan review fee · add-on
65% of the technical code base fee schedule, or the actual cost of the review if less — select the permit fee line above to calculate
see rule
○Over the counter plan review
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions, per hour
Flat fee $47.00
$47.00
○Additional inspections not included in the technical code base fee schedule, per hour
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Ogden does not publish a flat reroof permit fee; fees are calculated from the total permit valuation table in Ogden Municipal Code section 4-6-1, with a minimum of $70.50 for valuations of $1.00 to $1,200.00. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. Ogden Municipal Code 4-6-1 was read in full this pass; it is current through Ord. 2026-6 dated 5-5-2026. Every bracket of the technical code base fee schedule is reproduced below verbatim. Ogden publishes no flat fee for this permit type, so the valuation table IS the published price.

Source: published fee schedule · Verified 9/15/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total permit valuation $1.00 to $1,200.00 (minimum permit fee)
Flat fee $70.50
$70.50
Total permit valuation $1,201 to $2,000
$70.50 for the first $1,200 plus $2.78 per $100 or fraction thereof
see rule
○Total permit valuation $2,001 to $25,000
$2,000.00 base plus $16.00 x 250 = $6,000.00
$6,000.00
○Total permit valuation $25,001 to $50,000
$25,000.00 base plus $11.50 x 250 = $27,875.00
$27,875.00
○Total permit valuation $50,001 to $100,000
$50,000.00 base plus $8.00 x 250 = $52,000.00
$52,000.00
○Total permit valuation $100,001 to $500,000
$100,000.00 base plus $6.30 x 250 = $101,575.00
$101,575.00
Plan review fee · add-on
65% of the technical code base fee schedule, or the actual cost of the review if less — select the permit fee line above to calculate
see rule
○Over the counter plan review
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions, per hour
Flat fee $47.00
$47.00
○Additional inspections not included in the technical code base fee schedule, per hour
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Ogden does not publish a flat retaining wall permit fee; fees are calculated from the total permit valuation table in Ogden Municipal Code section 4-6-1, with a minimum of $70.50 for valuations of $1.00 to $1,200.00. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. Ogden Municipal Code 4-6-1 was read in full this pass; it is current through Ord. 2026-6 dated 5-5-2026. Every bracket of the technical code base fee schedule is reproduced below verbatim. Ogden publishes no flat fee for this permit type, so the valuation table IS the published price.

Source: published fee schedule · Verified 9/15/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total permit valuation $1.00 to $1,200.00 (minimum permit fee)
Flat fee $70.50
$70.50
Total permit valuation $1,201 to $2,000
$70.50 for the first $1,200 plus $2.78 per $100 or fraction thereof
see rule
○Total permit valuation $2,001 to $25,000
$2,000.00 base plus $16.00 x 250 = $6,000.00
$6,000.00
○Total permit valuation $25,001 to $50,000
$25,000.00 base plus $11.50 x 250 = $27,875.00
$27,875.00
○Total permit valuation $50,001 to $100,000
$50,000.00 base plus $8.00 x 250 = $52,000.00
$52,000.00
○Total permit valuation $100,001 to $500,000
$100,000.00 base plus $6.30 x 250 = $101,575.00
$101,575.00
Plan review fee · add-on
65% of the technical code base fee schedule, or the actual cost of the review if less — select the permit fee line above to calculate
see rule
○Over the counter plan review
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions, per hour
Flat fee $47.00
$47.00
○Additional inspections not included in the technical code base fee schedule, per hour
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Ogden does not publish a flat shed permit fee; fees are calculated from the total permit valuation table in Ogden Municipal Code section 4-6-1, with a minimum of $70.50 for valuations of $1.00 to $1,200.00. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. Ogden Municipal Code 4-6-1 was read in full this pass; it is current through Ord. 2026-6 dated 5-5-2026. Every bracket of the technical code base fee schedule is reproduced below verbatim. Ogden publishes no flat fee for this permit type, so the valuation table IS the published price.

Source: published fee schedule · Verified 9/15/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Total permit valuation $1.00 to $1,200.00 (minimum permit fee)
Flat fee $70.50
$70.50
Total permit valuation $1,201 to $2,000
$70.50 for the first $1,200 plus $2.78 per $100 or fraction thereof
see rule
○Total permit valuation $2,001 to $25,000
$2,000.00 base plus $16.00 x 250 = $6,000.00
$6,000.00
○Total permit valuation $25,001 to $50,000
$25,000.00 base plus $11.50 x 250 = $27,875.00
$27,875.00
○Total permit valuation $50,001 to $100,000
$50,000.00 base plus $8.00 x 250 = $52,000.00
$52,000.00
○Total permit valuation $100,001 to $500,000
$100,000.00 base plus $6.30 x 250 = $101,575.00
$101,575.00
Plan review fee · add-on
65% of the technical code base fee schedule, or the actual cost of the review if less — select the permit fee line above to calculate
see rule
○Over the counter plan review
Flat fee $47.00
$47.00
○Additional plan review required by changes, additions or revisions, per hour
Flat fee $47.00
$47.00
○Additional inspections not included in the technical code base fee schedule, per hour
Flat fee $47.00
$47.00
How this jurisdiction calculates the fee

Ogden does not publish a flat water heater permit fee; fees are calculated from the total permit valuation table in Ogden Municipal Code section 4-6-1, with a minimum of $70.50 for valuations of $1.00 to $1,200.00. POPULATED 2026-09-13 (Lane B second tranche): the row previously carried an empty examples array and was therefore unreachable by target selection. Ogden Municipal Code 4-6-1 was read in full this pass; it is current through Ord. 2026-6 dated 5-5-2026. Every bracket of the technical code base fee schedule is reproduced below verbatim. Ogden publishes no flat fee for this permit type, so the valuation table IS the published price.

Source: published fee schedule · Verified 9/15/2026

See the full write-up: Ogden building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.