B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Spanish Fork, Utah Building Permit Cost Calculator

Estimates permit cost in Spanish Fork from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit
As set by 2021 IRC
see rule
Partial Building Permit - Residential/Commercial
$90/$360
see rule
○Plan Check Residential per plan
Flat fee $499.00
$499.00
○Plan Check Residential per hour over 3 hours
Flat fee $129.00
$129.00
○Duplicate Plan Check Residential per plan
Flat fee $238.00
$238.00
○Plan Check Non-residential per plan
Flat fee $1,634.00
$1,634.00
○Plan Check Non-residential Hourly per hour over 3 hours
Flat fee $306.00
$306.00
Building Re-inspection
$132 Flat Fee Per Trip
see rule
○Building re-inspection as stated on the Inspections page (conflicts with the fees table)
Flat fee $93.00
$93.00
○Temporary Certificate
Flat fee $120.00
$120.00
Construction Deposit (single-family)
$1,500/Building Permit
see rule
Construction Deposit (multi-family)
$500/Building Permit Unit
see rule
How this jurisdiction calculates the fee

The building permit fee itself is published only as being set by the adopted code; the City's own published dollar amounts cover plan check, partial permits, re-inspection, temporary certificates and refundable construction deposits. Municipal Code 14.04.020 sets the plan check review fee at the City's actual costs incurred, adjusted annually, with the annual amount established by resolution or in the annual budget. A partial building permit fee is charged in addition to the building permit fee and allows limited commencement of construction while the full plans are still under review, at the applicant's risk. ADOPTION STATUS NOW RESOLVED (2026-09-10): the FY2026 adoption question flagged on 2026-08-31 is closed. spanishfork.gov migrated the Building department off the old .php paths (both /departments/community_development/building/fees.php and /permits.php now return HTTP 404) to /living-in-our-community/building/. Its Building Fees page is captioned "Building Fees for July 1, 2026 to June 30, 2027" and every amount below is reprinted there verbatim, so the figures carried forward on 2026-08-31 are confirmed as the adopted FY2027 schedule. CONFLICT PRESERVED: the Building Fees page prints "Building Re-inspection $132 per trip" while the Building Permits & Inspections page (/living-in-our-community/building/building-permits-inspections/) prints "a $93 re-inspection fee may apply"; the City does not reconcile these and neither was picked. 2026-09-17 (lane B run 1390, pipeline run 94): DEAD SOURCE LINK REPAIRED - a real 404, not a 403. spanishfork.gov/departments/community_development/building/index.php and .../permits.php both return HTTP 404 (the city moved its content under /living-in-our-community/). source_url repointed to the live pages: the Building landing page and the Building Permits & Inspections page. Every stored figure re-verified verbatim on the Building Fees page, which is headed "Building Fees for July 1, 2026 to June 30, 2027" - the current fiscal-year edition: Building Permit "As set by 2021 IRC"; Partial Building Permit Residential $90 / Commercial $360; Residential Plan Check $499 per plan; Residential Plan Check Additional Time $129 per hour over 3 hours; Duplicate Residential Plan Check $238 per plan; Non-Residential Plan Check $1,634 per plan; Non-Residential Additional Time $306 per hour over 3 hours; Building Re-inspection $132 per trip; Temporary Certificate $120; Construction Deposit Single-Family $1,500 per building permit, Multi-Family $500 per building permit unit. THE STANDING TWO-SOURCE CONFLICT IS RE-CONFIRMED AND STILL NOT RESOLVED: the new Building Permits & Inspections page states "If the work is not ready, a $93 re-inspection fee may apply", while the Building Fees table prices Building Re-inspection at $132 per trip. Both are official City of Spanish Fork publications; the row carries both, each labelled with its source, and neither was picked.

Source: published fee schedule · Verified 11/10/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit
As set by 2021 IRC
see rule
○Plan Check Residential per plan
Flat fee $499.00
$499.00
How this jurisdiction calculates the fee

There is no deck-specific line in the fee table; a deck falls under the building permit fee, which the City publishes only as being set by the adopted code, plus the applicable plan check fee. ADOPTION STATUS NOW RESOLVED (2026-09-10): the FY2026 adoption question flagged on 2026-08-31 is closed. spanishfork.gov migrated the Building department off the old .php paths (both /departments/community_development/building/fees.php and /permits.php now return HTTP 404) to /living-in-our-community/building/. Its Building Fees page is captioned "Building Fees for July 1, 2026 to June 30, 2027" and reprints Building Permit "As set by 2021 IRC" and Residential Plan Check "$499 per plan" verbatim, so both figures are confirmed as the adopted FY2027 schedule. 2026-09-17 (lane B run 1390, pipeline run 94): DEAD SOURCE LINK REPAIRED - a real 404, not a 403. spanishfork.gov/departments/community_development/building/index.php and .../permits.php both return HTTP 404 (the city moved its content under /living-in-our-community/). source_url repointed to the live pages: the Building landing page and the Building Permits & Inspections page. Every stored figure re-verified verbatim on the Building Fees page, which is headed "Building Fees for July 1, 2026 to June 30, 2027" - the current fiscal-year edition: Building Permit "As set by 2021 IRC"; Partial Building Permit Residential $90 / Commercial $360; Residential Plan Check $499 per plan; Residential Plan Check Additional Time $129 per hour over 3 hours; Duplicate Residential Plan Check $238 per plan; Non-Residential Plan Check $1,634 per plan; Non-Residential Additional Time $306 per hour over 3 hours; Building Re-inspection $132 per trip; Temporary Certificate $120; Construction Deposit Single-Family $1,500 per building permit, Multi-Family $500 per building permit unit. THE STANDING TWO-SOURCE CONFLICT IS RE-CONFIRMED AND STILL NOT RESOLVED: the new Building Permits & Inspections page states "If the work is not ready, a $93 re-inspection fee may apply", while the Building Fees table prices Building Re-inspection at $132 per trip. Both are official City of Spanish Fork publications; the row carries both, each labelled with its source, and neither was picked.

Source: published fee schedule · Verified 11/10/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit
As set by 2021 IRC
see rule
How this jurisdiction calculates the fee

Spanish Fork publishes no separate electrical trade permit fee. Electrical work is permitted under the building permit fee structure with the applicable plan check fee. SITE MIGRATION AND CONFLICT RECORDED 2026-09-10: the previously cited pages /departments/community_development/building/fees.php and /permits.php now return HTTP 404. Spanish Fork has moved the Building Department to /living-in-our-community/building/, whose Building Fees page is captioned "Building Fees for July 1, 2026 to June 30, 2027" and still prints Building Permit = As set by 2021 IRC, unchanged. Also newly published there: Partial Building Permit residential $90 / commercial $360, Residential Plan Check $499 per plan ($129/hour over 3 hours), Duplicate Residential Plan Check $238, Non-Residential Plan Check $1,634 per plan ($306/hour over 3 hours), Temporary Certificate $120, Construction Deposit $1,500 single-family / $500 per multi-family unit. TWO OFFICIAL CITY PAGES DISAGREE ON THE RE-INSPECTION FEE AND NEITHER WAS PICKED: the Building Fees page prints "Building Re-inspection $132 per trip" while the Building Permits & Inspections page prints "a $93 re-inspection fee may apply". 2026-09-17 (lane B run 1390, pipeline run 94): DEAD SOURCE LINK REPAIRED - a real 404, not a 403. spanishfork.gov/departments/community_development/building/index.php and .../permits.php both return HTTP 404 (the city moved its content under /living-in-our-community/). source_url repointed to the live pages: the Building landing page and the Building Permits & Inspections page. Every stored figure re-verified verbatim on the Building Fees page, which is headed "Building Fees for July 1, 2026 to June 30, 2027" - the current fiscal-year edition: Building Permit "As set by 2021 IRC"; Partial Building Permit Residential $90 / Commercial $360; Residential Plan Check $499 per plan; Residential Plan Check Additional Time $129 per hour over 3 hours; Duplicate Residential Plan Check $238 per plan; Non-Residential Plan Check $1,634 per plan; Non-Residential Additional Time $306 per hour over 3 hours; Building Re-inspection $132 per trip; Temporary Certificate $120; Construction Deposit Single-Family $1,500 per building permit, Multi-Family $500 per building permit unit. THE STANDING TWO-SOURCE CONFLICT IS RE-CONFIRMED AND STILL NOT RESOLVED: the new Building Permits & Inspections page states "If the work is not ready, a $93 re-inspection fee may apply", while the Building Fees table prices Building Re-inspection at $132 per trip. Both are official City of Spanish Fork publications; the row carries both, each labelled with its source, and neither was picked.

Source: published fee schedule · Verified 11/10/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Fence permit not required by the adopted Building Code
No fee is charged
see rule
How this jurisdiction calculates the fee

Fence permits are issued without charge unless the adopted Building Code is what triggers the permit, in which case the standard building permit fee applies. SITE MIGRATION AND CONFLICT RECORDED 2026-09-10: the previously cited pages /departments/community_development/building/fees.php and /permits.php now return HTTP 404. Spanish Fork has moved the Building Department to /living-in-our-community/building/, whose Building Fees page is captioned "Building Fees for July 1, 2026 to June 30, 2027" and still prints Building Permit = As set by 2021 IRC, unchanged. Also newly published there: Partial Building Permit residential $90 / commercial $360, Residential Plan Check $499 per plan ($129/hour over 3 hours), Duplicate Residential Plan Check $238, Non-Residential Plan Check $1,634 per plan ($306/hour over 3 hours), Temporary Certificate $120, Construction Deposit $1,500 single-family / $500 per multi-family unit. TWO OFFICIAL CITY PAGES DISAGREE ON THE RE-INSPECTION FEE AND NEITHER WAS PICKED: the Building Fees page prints "Building Re-inspection $132 per trip" while the Building Permits & Inspections page prints "a $93 re-inspection fee may apply".

Source: published fee schedule · Verified 9/17/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Accessory structure permit, structure less than 200 square feet or otherwise exempt from the adopted Building Code
free of charge
see rule
Building Permit (accessory structures over 200 square feet)
As set by 2021 IRC
see rule
How this jurisdiction calculates the fee

Accessory structure permits are free of charge where the structure is less than 200 square feet or is otherwise exempt from the adopted Building Code under Municipal Code 14.04.010. Larger accessory structures fall under the standard building permit fee and plan check. SITE MIGRATION AND CONFLICT RECORDED 2026-09-10: the previously cited pages /departments/community_development/building/fees.php and /permits.php now return HTTP 404. Spanish Fork has moved the Building Department to /living-in-our-community/building/, whose Building Fees page is captioned "Building Fees for July 1, 2026 to June 30, 2027" and still prints Building Permit = As set by 2021 IRC, unchanged. Also newly published there: Partial Building Permit residential $90 / commercial $360, Residential Plan Check $499 per plan ($129/hour over 3 hours), Duplicate Residential Plan Check $238, Non-Residential Plan Check $1,634 per plan ($306/hour over 3 hours), Temporary Certificate $120, Construction Deposit $1,500 single-family / $500 per multi-family unit. TWO OFFICIAL CITY PAGES DISAGREE ON THE RE-INSPECTION FEE AND NEITHER WAS PICKED: the Building Fees page prints "Building Re-inspection $132 per trip" while the Building Permits & Inspections page prints "a $93 re-inspection fee may apply". 2026-09-17 (lane B run 1390, pipeline run 94): DEAD SOURCE LINK REPAIRED - a real 404, not a 403. spanishfork.gov/departments/community_development/building/index.php and .../permits.php both return HTTP 404 (the city moved its content under /living-in-our-community/). source_url repointed to the live pages: the Building landing page and the Building Permits & Inspections page. Every stored figure re-verified verbatim on the Building Fees page, which is headed "Building Fees for July 1, 2026 to June 30, 2027" - the current fiscal-year edition: Building Permit "As set by 2021 IRC"; Partial Building Permit Residential $90 / Commercial $360; Residential Plan Check $499 per plan; Residential Plan Check Additional Time $129 per hour over 3 hours; Duplicate Residential Plan Check $238 per plan; Non-Residential Plan Check $1,634 per plan; Non-Residential Additional Time $306 per hour over 3 hours; Building Re-inspection $132 per trip; Temporary Certificate $120; Construction Deposit Single-Family $1,500 per building permit, Multi-Family $500 per building permit unit. THE STANDING TWO-SOURCE CONFLICT IS RE-CONFIRMED AND STILL NOT RESOLVED: the new Building Permits & Inspections page states "If the work is not ready, a $93 re-inspection fee may apply", while the Building Fees table prices Building Re-inspection at $132 per trip. Both are official City of Spanish Fork publications; the row carries both, each labelled with its source, and neither was picked.

Source: published fee schedule · Verified 11/10/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit
As set by 2021 IRC
see rule
How this jurisdiction calculates the fee

Spanish Fork publishes no separate water heater or mechanical trade permit fee. The work is permitted under the building permit fee structure. SITE MIGRATION AND CONFLICT RECORDED 2026-09-10: the previously cited pages /departments/community_development/building/fees.php and /permits.php now return HTTP 404. Spanish Fork has moved the Building Department to /living-in-our-community/building/, whose Building Fees page is captioned "Building Fees for July 1, 2026 to June 30, 2027" and still prints Building Permit = As set by 2021 IRC, unchanged. Also newly published there: Partial Building Permit residential $90 / commercial $360, Residential Plan Check $499 per plan ($129/hour over 3 hours), Duplicate Residential Plan Check $238, Non-Residential Plan Check $1,634 per plan ($306/hour over 3 hours), Temporary Certificate $120, Construction Deposit $1,500 single-family / $500 per multi-family unit. TWO OFFICIAL CITY PAGES DISAGREE ON THE RE-INSPECTION FEE AND NEITHER WAS PICKED: the Building Fees page prints "Building Re-inspection $132 per trip" while the Building Permits & Inspections page prints "a $93 re-inspection fee may apply".

Source: published fee schedule · Verified 11/9/2026

See the full write-up: Spanish Fork building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.