B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Tooele, Utah Building Permit Cost Calculator

Estimates permit cost in Tooele from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit Plan Review - Single-Family Residence
IBC rate
see rule
Building Permit Plan Review - Multi-Family Residence
IBC rate
see rule
Building Permit Plan Review - Commercial
IBC rate
see rule
Building Permit Plan Review - Industrial
IBC rate
see rule
Building Permit Plan Review - Single-Family Residence Card File
2 hrs. at IBC rate
see rule
Building Permit Plan Review - Multi-Family Residence Card File
2 hrs. at IBC rate + 1 hr. at IBC rate/dwelling unit
see rule
Work Without a Permit
2 × permit fees
see rule
All Other Plans
Per IBC
see rule
All Other Building Fees
Per IBC
see rule
○Power-To-Panel Agreement
Flat fee $50.00
$50.00
○Inspections - General Purpose
Flat fee $50.00
$50.00
Inspections - After-Hours
$50 + ≥2 hr. callout
see rule
○Re-Inspections Fees (Each After 2)
Flat fee $50.00
$50.00
Development Public Improvements - Inspection Fees
4% engineering & construction estimated cost of all public improvements
see rule
○Development Public Improvements - Bond Administration Fee
Flat fee $250.00
$250.00
○Development Public Improvements - Completion Extension Fee
Flat fee $150.00
$150.00
○Temporary Certificate of Occupancy - Bond Administration Fee
Flat fee $250.00
$250.00
○Inspection Fees for Non-Permanent Foundations - Single-Wide Mobile, Modular, or Manufactured
Flat fee $200.00
$200.00
○Inspection Fees for Non-Permanent Foundations - Double-Wide Mobile, Modular, or Manufactured
Flat fee $260.00
$260.00
○Demolition Permit Application - Residential
Flat fee $160.00
$160.00
○Demolition Permit Application - Non-Residential
Flat fee $250.00
$250.00
○Demolition Permit Bond - Residential
Flat fee $2,500.00
$2,500.00
○Demolition Permit Bond - Non-Residential
Flat fee $5,000.00
$5,000.00
○Stop Work Order - Work with Permit
Flat fee $200.00
$200.00
○Stop Work Order - Work without Permit
Flat fee $300.00
$300.00
Street Excavation Application - Paved Surfaces
$300 + age factor
see rule
Street Excavation age factor - Roads <5 Years Old
$1.50/sq.ft.
see rule
Street Excavation age factor - Roads 5+ Years Old
$0.50/sq. ft.
see rule
○Street Excavation Application - Unpaved Surfaces
Flat fee $100.00
$100.00
○Street Excavation - Single Permit Bond
Flat fee $1,000.00
$1,000.00
○Street Excavation - Master Bond
Flat fee $10,000.00
$10,000.00
How this jurisdiction calculates the fee

The base permit fee and all plan review fees are published only by reference to the IBC rate; no city dollar table exists. The flat dollar amounts below are published in the BUILDING section of the Tooele City Consolidated Fee Schedule dated July 17, 2026. Water rights, reimbursement (latecomer's) fees and impact fees are required in accordance with Tooele City Code prior to issuance of the building permit.

Source: published fee schedule · Verified 11/9/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Open Decks - cost per square foot, average (construction valuation input, not a permit fee)
Flat fee $6.80
$6.80
○Covered Decks - cost per square foot, average (construction valuation input, not a permit fee)
Flat fee $22.10
$22.10
○Covered Porches (Aluminum) - cost per square foot, average (construction valuation input, not a permit fee)
Flat fee $7.50
$7.50
○Sun Rooms - cost per square foot, average (construction valuation input, not a permit fee)
Flat fee $20.05
$20.05
○Pre-Pay Fees: Basement Finishes & Garages
Flat fee $250.00
$250.00
○ONE INSPECTION
Flat fee $50.00
$50.00
○Inspections and Bonds: General Purpose (July 17, 2026 Fee Schedule)
Flat fee $50.00
$50.00
○Inspections and Bonds: Re-Inspections Fees (Each After 2) (July 17, 2026 Fee Schedule)
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Tooele City publishes no flat deck permit fee. The July 17, 2026 Tooele City Fee Schedule contains no deck line item at all; its BUILDING section states building permit plan reviews at 'IBC rate' and 'All Other Building Fees: Per IBC'. The only City document carrying deck numbers is the sheet the City links as 'Permit Fee Rates', which is actually titled 'Building Valuation Data (Taken from Building Standards Valuation Data)', established April 2001, revised September 12, 2012, and signed into effect by the Community Development Director on 9/12/12. The deck amounts below are cost-per-square-foot AVERAGE CONSTRUCTION VALUATION figures under that sheet's 'Garages (per square foot, average)' block - they are inputs to the valuation, NOT permit fees. Two further components are published on the City's Building Permit Fees information sheet (March 2015): a State Surcharge equal to 1% of the permit fee, and a Plan Check Fee generally calculated to be equal to 65% of the Permit Fee; that sheet also states the permit fee covers the needed inspections so there are normally no additional inspection fees. CONFLICT PRESERVED: Tooele City Code 4-3-1.1 incorporates Table 1-A of the 1997 edition of the Uniform Building Code by reference as the building fee schedule for calculating all construction related fees, while the July 17, 2026 Fee Schedule states 'IBC rate' and 'Per IBC'. The two are not reconciled by the City. The code is treated as primary for the fee-calculation basis; the 2012 sheet is the only source for the deck valuation amounts and is 14 years old, so do not present these as current 2026 figures without that qualifier. The 2026 Fee Schedule carries a disclaimer that the absence of a fee on the schedule, or the presence of an incorrect fee, does not relieve any person of the requirement to pay the correct fee. 2026 Fee Schedule: https://files.tooelecity.gov/Documents/FeeSchedules/Fee%20Schedule%20(07-17-26).pdf

Source: published fee schedule · Verified 9/17/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Flat Fees: Electrical (new meter base)
Flat fee $50.00
$50.00
○ONE INSPECTION
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

One narrow flat fee is published, and it is for a new meter base only - there is no published fee for general electrical work. The amount appears on the sheet the City links as 'Permit Fee Rates' (actually titled 'Building Valuation Data', revised September 12, 2012, signed into effect 9/12/12 by the Community Development Director) under its 'Flat Fees' column. A related current-schedule item is 'Power-To-Panel Agreement: $50' in the BUILDING section of the July 17, 2026 Tooele City Fee Schedule at https://files.tooelecity.gov/Documents/FeeSchedules/Fee%20Schedule%20(07-17-26).pdf, which also lists 'Inspections and Bonds: General Purpose: $50' and 'Re-Inspections Fees (Each After 2): $50'. Neither schedule contains a general electrical permit fee. The March 2015 Building Permit Fees information sheet adds a State Surcharge equal to 1% of the permit fee and a Plan Check Fee generally equal to 65% of the Permit Fee. CONFLICT PRESERVED: Tooele City Code 4-3-1.1 incorporates 1997 UBC Table 1-A as the building fee schedule for all construction related fees, while the July 17, 2026 Fee Schedule states 'IBC rate' and 'Per IBC'; the City does not reconcile these, and the code is treated as primary. The 2012 vintage of the $50 meter-base amount is a material caveat. 2026-09-17 (lane B run 1390, pipeline run 94): re-verified. The cited "Permit Fee Rates" sheet is actually titled "Building Valuation Data (Taken from Building Standards Valuation Data)", established April 2001, revised September 12, 2012; it is image-only and was OCR'd at 300 dpi (pdftoppm + tesseract) rather than read from an empty pdftotext output. It prints, in its Flat Fees column, "Re-Roof - Shingles Only $50", "Tear-Off & Replace $100", "Window, Siding Replacement $50", "Electrical (new meter base) $50" and "ONE INSPECTION = $50", and under Roof Conversion (per square foot, average) "Change in Pitch $12.00 ($125 permit & $25 plan check min.)". The $300 / $200 stop-work figures are in the sibling Tooele City Fee Schedule (07-17-26), read in full today, which prints "Stop Work Orders / Work with Permit: $200 / Work without Permit: $300". Both documents are current on files.tooelecity.gov. No change.

Source: published fee schedule · Verified 9/17/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit Plan Review - Single-Family Residence
IBC rate
see rule
Building Permit Plan Review - Commercial
IBC rate
see rule
All Other Building Fees
Per IBC
see rule
Work Without a Permit
2 x permit fees
see rule
○Inspections - General Purpose
Flat fee $50.00
$50.00
○Re-Inspections Fees (Each After 2)
Flat fee $50.00
$50.00
○Stop Work Orders - Work without Permit
Flat fee $300.00
$300.00
How this jurisdiction calculates the fee

Tooele City publishes no flat permit fee for fences, retaining walls or sheds. The City Fee Schedule (current as of 17 July 2026) sets building permit plan review for single-family, multi-family, commercial and industrial work at the IBC rate, and under Other states that All Other Plans and All Other Building Fees are Per IBC - i.e. the permit fee resolves through the adopted International Building Code fee/valuation mechanism rather than any City-published flat amount. Separately payable items in the same section include a $50 general-purpose inspection, $50 re-inspection after the first two, and doubling of permit fees for work started without a permit. Utah's 1% state surcharge under Utah Code 15A-1-209 is statutory statewide but is not itemised in this schedule. | 2026-09-14 (lane B run 1068): examples populated. Tooele publishes no flat fee for this permit type, so the governing published price IS the Tooele City Fee Schedule (current as of July 17, 2026) BUILDING section, read in full this pass with curl + pdftotext -layout. Every amount below is printed there verbatim. No figure was guessed.

Source: published fee schedule · Verified 11/9/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Flat Fees: Re-Roof - Shingles Only
Flat fee $50.00
$50.00
○Flat Fees: Re-Roof, Tear-Off & Replace
Flat fee $100.00
$100.00
○Roof Conversion, Change in Pitch - per square foot, average (with a published $125 permit and $25 plan check minimum)
Flat fee $12.00
$12.00
○Flat Fees: Window, Siding Replacement (adjacent line, for context)
Flat fee $50.00
$50.00
○ONE INSPECTION
Flat fee $50.00
$50.00
○Stop Work Orders: Work without Permit (July 17, 2026 Fee Schedule)
Flat fee $300.00
$300.00
○Stop Work Orders: Work with Permit (July 17, 2026 Fee Schedule)
Flat fee $200.00
$200.00
How this jurisdiction calculates the fee

Two flat re-roof fees and one roof-conversion valuation rate are published, all on the sheet the City links from its live Applications & Forms page as 'Permit Fee Rates' - a document actually titled 'Building Valuation Data (Taken from Building Standards Valuation Data)', established April 2001, revised September 12, 2012, and hand-signed into effect on 9/12/12 by the Community Development Director. 'Re-Roof - Shingles Only' and 'Tear-Off & Replace' sit in the sheet's 'Flat Fees' column and are permit fees. 'Change in Pitch' sits under 'Roof Conversion (per square foot, average)' and is a construction valuation rate, carrying its own parenthetical permit and plan check minimums, which are quoted in the label below. MATERIAL CAVEAT: none of these amounts appear in the July 17, 2026 Tooele City Fee Schedule (https://files.tooelecity.gov/Documents/FeeSchedules/Fee%20Schedule%20(07-17-26).pdf), whose BUILDING section has no roofing line item at all and states only 'IBC rate' / 'Per IBC'; the 2012 sheet is nonetheless live, City-published, and currently linked, so it is treated as primary for these amounts, but they are 14 years old and should not be presented as current 2026 figures without that qualification. Additional published components from the March 2015 Building Permit Fees information sheet: State Surcharge equal to 1% of the permit fee; Plan Check Fee generally calculated to be equal to 65% of the Permit Fee; and the statement that the permit fee covers the needed inspections so there are normally no additional inspection fees. CONFLICT PRESERVED: Tooele City Code 4-3-1.1 incorporates 1997 UBC Table 1-A as the fee schedule for calculating all construction related fees, against the 2026 schedule's 'IBC rate'; unreconciled by the City, code treated as primary for the calculation basis. 2026-09-17 (lane B run 1390, pipeline run 94): re-verified. The cited "Permit Fee Rates" sheet is actually titled "Building Valuation Data (Taken from Building Standards Valuation Data)", established April 2001, revised September 12, 2012; it is image-only and was OCR'd at 300 dpi (pdftoppm + tesseract) rather than read from an empty pdftotext output. It prints, in its Flat Fees column, "Re-Roof - Shingles Only $50", "Tear-Off & Replace $100", "Window, Siding Replacement $50", "Electrical (new meter base) $50" and "ONE INSPECTION = $50", and under Roof Conversion (per square foot, average) "Change in Pitch $12.00 ($125 permit & $25 plan check min.)". The $300 / $200 stop-work figures are in the sibling Tooele City Fee Schedule (07-17-26), read in full today, which prints "Stop Work Orders / Work with Permit: $200 / Work without Permit: $300". Both documents are current on files.tooelecity.gov. No change.

Source: published fee schedule · Verified 9/17/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Building Permit Plan Review - Single-Family Residence
IBC rate
see rule
Building Permit Plan Review - Commercial
IBC rate
see rule
All Other Building Fees
Per IBC
see rule
Work Without a Permit
2 x permit fees
see rule
○Inspections - General Purpose
Flat fee $50.00
$50.00
○Re-Inspections Fees (Each After 2)
Flat fee $50.00
$50.00
○Stop Work Orders - Work without Permit
Flat fee $300.00
$300.00
How this jurisdiction calculates the fee

Tooele City publishes no flat permit fee for fences, retaining walls or sheds. The City Fee Schedule (current as of 17 July 2026) sets building permit plan review for single-family, multi-family, commercial and industrial work at the IBC rate, and under Other states that All Other Plans and All Other Building Fees are Per IBC - i.e. the permit fee resolves through the adopted International Building Code fee/valuation mechanism rather than any City-published flat amount. Separately payable items in the same section include a $50 general-purpose inspection, $50 re-inspection after the first two, and doubling of permit fees for work started without a permit. Utah's 1% state surcharge under Utah Code 15A-1-209 is statutory statewide but is not itemised in this schedule. | 2026-09-14 (lane B run 1068): examples populated. Tooele publishes no flat fee for this permit type, so the governing published price IS the Tooele City Fee Schedule (current as of July 17, 2026) BUILDING section, read in full this pass with curl + pdftotext -layout. Every amount below is printed there verbatim. No figure was guessed.

Source: published fee schedule · Verified 11/10/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Sheds less than 400 s.f. - cost per square foot, average (construction valuation input, not a permit fee)
Flat fee $16.40
$16.40
○Pre-Pay Fees: Carports, Sheds
Flat fee $50.00
$50.00
Building Permit Plan Review - Single-Family Residence
IBC rate
see rule
All Other Building Fees
Per IBC
see rule
Work Without a Permit
2 x permit fees
see rule
○Inspections - General Purpose
Flat fee $50.00
$50.00
○Re-Inspections Fees (Each After 2)
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Tooele City publishes no flat permit fee for fences, retaining walls or sheds. The City Fee Schedule (current as of 17 July 2026) sets building permit plan review for single-family, multi-family, commercial and industrial work at the IBC rate, and under Other states that All Other Plans and All Other Building Fees are Per IBC - i.e. the permit fee resolves through the adopted International Building Code fee/valuation mechanism rather than any City-published flat amount. Separately payable items in the same section include a $50 general-purpose inspection, $50 re-inspection after the first two, and doubling of permit fees for work started without a permit. Utah's 1% state surcharge under Utah Code 15A-1-209 is statutory statewide but is not itemised in this schedule. | 2026-09-14 (lane B run 1068): examples populated. Tooele publishes no flat shed permit fee. Two City documents together are the published price and both were read in full this pass: the Tooele City Fee Schedule (current as of July 17, 2026, curl + pdftotext -layout) for the permit/plan-review basis and inspection amounts, and the sheet the City links as "Permit Fee Rates" - actually titled "Building Valuation Data (Taken from Building Standards Valuation Data)", established April 2001, revised September 12, 2012 - which is an image-only PDF and was read by tesseract OCR at 250dpi. The $16.40 and $50 figures below come from that sheet; the per-square-foot rate is a construction-valuation input, not a permit fee.

Source: published fee schedule · Verified 9/17/2026

See the full write-up: Tooele building permit cost