208.01 Description.
REMOVAL AND REINTERMENT OF GRAVES
208.01 Description.
This Section shall cover the services necessary to remove, disinter, and reinter graves or remains found within the limits of the highway right of way. The removal, disinterment, and reinterment shall be in compliance with all State, County, and/or City ru les and regulations. Reinterment shall be in approved, established cemeteries or burial grounds. The number of graves specified in the contract is approximate only; the actual number may vary and will depend upon a close investigation of the existing buria l site during preliminary grading operations. Only the number of graves actually moved as directed will be paid for at the contract unit price, and no claim will be allowed for extra compensation due to overruns or underruns of the items provided under thi s Section.
208.02 Materials.
All materials furnished for use in connection with work under this item must be acceptable to the Engineer and suitable for the particular work with which it is associated.
208.03 Construction Details.
208.04 Method of Measurement.
The removal, disinterment, and reinterment of grav es, when provided by the plans or proposal, shall be measured in individual grave units, with each grave actually removed and relocated considered as a separate individual unit.
208.05 Basis of Payment.
210.01 Description.
and/or City rules and regulations, and for furnishing all equipment, tools, labor, and incidentals necessary to complete the work.
209.01 Description.
This Section shall cover the work of permanently resetting mailboxes required to be removed from their original position inside the right of way.
209.02 Materials.
All new mailboxes and new support materials furnished shall meet the requirements shown on the plans. The Contractor may re- use existing mailboxes or support materials if approved by the Engineer. Other materials shall be returned to the property owner if requested or disposed of by the Contractor.
209.03 Construction Requirements.
All work shall be done in a workmanlike manner in accordance with the requirements of local codes, ordinances, and U.S. Postal Service Regulations. Any materials lost or rendered unfit for re- use on account of negligence or improper handling by the Contractor shall be replaced by him without additional compensation.
209.04 Method of Measurement.
The number of mailbox reset installations will be the number of each type installation (i.e. single, double, or multiple) permanently reset as directed and accepted. No measurement or direct payment will be made fo r mailboxes removed only and not reset, or for mailboxes removed and temporarily reset.
209.05 Basis of Payment.
210.01 Description.
The work under this Section shall cover the excavation, hauling, disposal, or compaction of all material not being removed under some other item which is encountered within the limits of the work and is necessary for all construction in accordance with these specifications and in reasonably close conformity with the lines, grades, thickness, and typical cross sections shown on the plans or established by the Engineer. All excavation covered in this s ection will be classified as "Unclassified Excavation", "Muck Excavation", "Channel Excavation", or "Borrow Excavation", as described in this Section. Attention is directed to the fact that the roadbed must be treated by one of the methods specified in Sec tion 230, 231 or 232 before the placement of an overlying subbase, base, or paving structure will be permitted.