B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
General Provisions (00100-00999)

729INTELLIGENT TRANSPORTATION SYSTEMS

AL · 2022 Standard SpecificationsBook pages 625663View official source ↗

728.02 Materials.

The Contractor shall retain ownership of the truck and impact attenuator unit, including all hardware and attachments, after their use on the project is complete.

728.02 Materials.

All truck mounted impact attenuator units furnished for use under this Sectio n shall be new or acceptable used units which include all of the latest modifications to manufacturer's current production models. The Contractor shall furnish the Engineer a copy of the certification by the testing agency that the attenuator meets the performance standards given in NCHRP Report 350, TL -2 for a work zone speed limit of 45 miles per hour and TL -3 for a work zone speed limit of 50 mph or greater. Truck mounted attenuators shall be used in accordance with the manufacturer's recommendations including the support truck weight and roll ahead distance. The impact attenuator shall have a standard trailer lighting system, including brake lights, tail lights, and turn signals.

728.03 Construction Requirements.

a.General . The truck mounted atten uator unit furnished under this Section shall be used when work is performed under traffic.
b.Maintenance . All truck mounted impact attenuator units shall be maintained in such a manner as to provide continuous service during their use on the project. Un its which become non -operational during use will require the Contractor to suspend work until the units can be repaired or replaced. The truck mounted impact attenuator units shall be stored in an approved secure storage area when not in use.

728.04 Method of Measurement.

Measurement of Truck Mounted Impact Attenuator Units will be made in complete functional units.

728.05 Basis of Payment.

a.Unit Price Coverage . The ordered and accepted truck mounted impact attenuator units under this item, measured as noted above, will be paid for at the contract unit price bid which shall be full compensation for the furnishing of the unit, complete with truck, and its exclusive use on the project, for providing all equipment, supplies, services, labor and incidentals necessary to operate and to maintain the units in good serviceable condition during the life of the contract.
b.Payment will be made under Item No .: 728-A Truck Mounted Impact Attenuator Unit - per each INTELLIGENT TRANSPORTATION SYSTEMS

729.01 Description.

This Section shall cover the work of furnishing, installing and testing Intelligent Transportation Systems (ITS). Descriptions and definitions of the equipment, words and terminology used in the furn ishing and installing of Intelligent Transportation Systems (ITS) equipment are given in the Manual of Uniform Traffic Control Devices (MUTCD) and the publications of the Institute of Transportation Engineers (ITE), the National Electrical Manufactures Ass ociation (NEMA), the National Fire Protection Association (NFPA), and the International Municipal Signal Association (IMSA).

729.02 Materials.

All materials furnished for use shall conform to the requirements given in Section 893 and the requirements shown on the Plans, and/or listed on the Alabama Department of Transportation (ALDOT) “Materials, Sources, and Devices with Special Acceptance Requirements Manual” (MSDSAR). All

729.03 Construction Requirements.

furnished materials and equipment shall be new and free from defects. Existing equipment shall only be used if shown on the Plans to be re- used.

729.03 Construction Requirements.

a.General. ITS devices/equipment (i.e., cabinets, cameras, Dynamic Message Signs, Vehicle Detection Systems, etc.) shall NOT be mounted on structural members until erection or final placement of the structure (i.e., Overhead Sign Bridge, ITS Pole, etc.).
1.Drawings and Specifications. Installations shall comply with the regulations of the latest edition of the National Electrical Code (NEC) (a.k.a. NFPA 70), the latest edition of the National Electrical Safety Code (NESC) (a.k.a. ANSI/IEEE C2), and local Utility regulations.
2.Material and Equipment Lists, Shop Drawing Approval. Material and equipment listings shall be submitted to the Des ign Bureau’s Traffic Engineering Division for approval within thirty (30) calendar days after the issuance of the “ Notice to Proceed ”. Material and equipment lists shall include catalog cutouts or published data sheets and shall be completed on the Depart ment’s Material Submittal Form D- 40. Material Submittal package(s) and Form D -40 shall be electronically completed and submitted in accordance with Traffic Engineering Division’s procedures as outlined in the Form D -40 quick help guide and instruction doc uments. All components required for a complete system, sub -system and/or pay item shall be listed on the Form D-40 as defined in the form’s instruction documents. Partial listings or incomplete shop drawings for any individual pay item, system, or sub -system will not be accepted for consideration and shall be returned for correction without review. Any changes to the approved material and equipment lists must be requested in writing through proper channels. If requested by the Engineer, the Contractor s hall submit for inspection and approval samples of both the specified and proposed substitute items at no cost to the Department. The Department will not be liable for any equipment purchased or work done , or any delay incurred before such approval. Failure of the Engineer to note unsatisfactory equipment as received will not relieve the Contractor from responsibility. Manufacturers’ warranties and guaranties furnished on equipment used in the work shall be delivered to the Engineer; likewise, instructi on sheets and parts lists shall be delivered to the Engineer upon receipt of the equipment. Throughout the entire project, the same manufacturer shall make all units of any one item.
3.Supporting Structures and ITS Poles. Supporting Structures and ITS Poles used for mounting the equipment shall conform to the requirements given in Section 718 and Section 891 . Concrete ITS Pole with metal tenon extension shall be installed per the manufacturer’s recommendations and as shown on the Plans.
4.As-Built Drawings. The Contractor shall submit as- built documentation of work provided in accordance with this Specification upon completion of the Burn -In Period as required in Sub -Article 729.03(s), “ Burn-In”. As-built submittal packag es are to be neat, legible, and orderly. All electronic/digital copies shall be submitted via Department approved media. Except for standard bound materials, bind all letter -size (8.5 inch x 11 inch) documentation, including ledger -size (11 inch x 17 inc h) drawings folded to letter- size (8.5 inch x 11 inch), in logical groupings in loose -leaf binders of 3 -ring, plastic comb, or plastic coil/spiral type. All binders and media shall have typed labels affixed identifying its contents. The following document s, at a minimum and as they are applicable, shall be included: [Contractor shall furnish at least two (2) sets of bound documentation.]
a.User/Operation Manual. The Contractor shall furnish a manual containing detailed operating instructions for each different type or model of equipment. The Contractor shall deliver two (2) hard copies and one (1) electronic searchable copy of each User/Operation Manual to the Engineer upon completion of the Project. The User/Operation Manuals shall be for the ITS elect ronic equipment and any software provided on the Project. The

729.03 Construction Requirements.

User/Operation Manuals should be grouped into the following ITS component areas: camera, VDS, network devices and other equipment.

b.Maintenance Procedures Manuals. The Contractor shall furnish a manufacturer’s manual containing detailed preventative and corrective maintenance procedures for each different type or model of equipment.
c.System Connection Diagrams. The Contractor shall furnish diagrams showing the ITS site detailing the wirin g between devices.
d.Drawings. The Contractor shall furnish a corrected set of plans showing in detail all changes made during construction from the original plans. These corrected drawings shall also include: (a) schematic wiring/circuit diagrams; (b) cabinet wiring diagrams; (c) actual route location and depth of conduits, encasements and CommBoxes; and, (d) aerial cable route locations including poles and pole attachment heights (at a minimum). Cable and conduit route locations shall be collected in Department approved GPS format with a horizontal tolerance of ±6 inches {15 cm} and a vertical tolerance of ±12 inches {30 cm}. These readings for cable and conduit are to be taken every 50 feet {15 m} and at changes in direction unless otherwise directed by the Engineer. GPS readings shall also be taken at the top center of installed CommBoxes. Resulting field survey data shall be provided in an ESRI ArcGIS shapefile format and include any necessary descriptive fields. These corrected drawings and field survey shall be furnished as an electronic copy. These corrected drawings should not be finalized for submittal until after all equipment and materials have been installed at their final location and a successful Acceptance Test has been completed. Along with these corrected drawings, all testing documentation and test results as required within the Specification shall be included in the as -built submittal package.
e.ALDOT OSP Database Forms. The Contractor shall provide the Department with completed Out side Plant (OSP) Database Forms which document fiber optic cable and ITS device installation information. These ALDOT forms should be supplied in PDF file format to the Contractor by the Engineer at the Pre -Construction meeting. These forms are to be pri nted and hand -completed by the appropriate technician (i.e. Fiber Optic Technician for fiber optic cables; and ITS Technician for ITS device/equipment) in the field at each site as corresponding form installation occurs, unless otherwise directed by the Engineer. The Engineer shall field verify submitted forms for accuracy; and then transmit acceptable forms to the Area Traffic Management Center Supervisor for OSP database entry. Copies of these forms should also be sent to Design Bureau’s Traffic Design ITS Group for their records. If any data is missing or any questions regarding form entries are noted at data entry, the forms in question will be returned to the Contractor for corrective action. The Contractor must complete these forms and submit them in a timely manner for review and entry. Otherwise, the Acceptance Test and Burn -In will be subject to being held up.
5.Approved Intelligent Transportation System Devices and Materials. Some materials and equipment required to be furnished under this Section will be standard production type products. Acceptance will be made by the Engineer based on selected confirmation tests, the manufacturer’s certification of the materials and equipment, and visual inspection at the job site. Approved devices are sh own on the Department’s List VI “Approved Intelligent Transportation System Devices and Materials” . Information concerning this list is given in Sub-

Article 106 — 01(f), “Use of Materials with Special Acceptance Requirements ” and ALDOT -355,

“General Informa tion Concerning Materials, Sources, and Devices with Special Acceptance Requirements ”.

6.Coordination of Work . Coordination with roadway work and with bridgework shall be of prime importance to prevent undue damage to completed items of work and to exist ing facilities. Any damage to existing facilities caused by the installation of the material or equipment required under this Specification shall be repaired by the Contractor at no additional cost to the Department. The Contractor shall field verify equi pment locations with the Engineer prior to installation.

729.03 Construction Requirements.

7.Restoration of Site. During the installation of the underground systems, removal of brush, trees, fencing, and other obstructions within the right -of-way shall comply with Section 201 and shall b e paid for separately under that Section. Landscaping shall be restored to original or better condition if disturbed.
8.Excavating and Backfilling. Excavation required for the installation and placement of conduits, foundations, CommBoxes, ITS poles and other appliance shall be performed in such manner as to cause the least possible injury to pavement, curbs or other improvements. Trenches shall not b e excavated wider than necessary for the proper installation of the required conduits, wires and/or fiber optic cables. Excavating shall not be performed until immediately before installation of conduit and other appliances. The material from the excavat ion shall be placed in a position where the least interference with the surface drainage will occur. Any trenches required for construction shall be backfilled the same day. Surplus excavated material shall be removed from the site the same day and disposed of by the Contractor , or as directed by the Engineer. Compaction shall be accomplished to the extent necessary to prevent future settlement of the backfill. The Contractor shall be required to restore any areas disturbed by his work to their original condition without additional cost to the Department.
9.License and Certifications. The Contractor responsible for the performance of the work shall be licensed as a General Contractor authorized to perform electrical work by the Alabama State Licensing Board for General Contractors and in good standing. At least one out of every three persons in each work crew shall be a Journeyman licensed by the Alabama Electrical Contractors Board and in good standing. J ourneymen shall be present and shall have direct involvement with all work required for the installation and operational testing of electrical materials and equipment. The Contractor shall submit copies of the General Contractor license, Journeyman licenses and certifications to the Engineer as a part of the submittal of the list of materials proposed for installation. Work shall not begin on the installation of electrical materials or equipment until copies of the licenses and certifications have been approved by the Engineer. Fiber Optic related work shall be completed by qualified Fiber Optic Technicians as defined in Item 729.03(b)1 “Fiber Optic Technician Qualifications” .
b.Fiber Optic Cable. The Contractor shall assembl e and install all necessary material and equipment and furnish a working fiber optic cable as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operati onal system shall be supplied by the Contractor. All optical fibers within each and every cable shall be usable and shall be 100% attenuation -tested by the manufacturer. The minimum information required within these attenuation testing results are define d in the materials section of this Specification (see Item 893.02(a)6, “Quality Assurance and Packing” for details on the “ cable reel data sheet ”). The cable reel data sheet shall be provided with each reel and affixed within the reel wrapping. When the cable reel is received from the manufacturer, a copy of the cable reel data sheet (a.k.a. “ manufacturer’s certified test report ”) along with any other shipping documentation shall be submitted to the Engineer. The cable reel tag is to be delivered to the Engineer upon its removal during cable installation. Once the documentation is no longer needed for their use, the Engineer should forward these items (or a copy) to the ALDOT Region TSM&O Engineer for their permanent records and for fiber optic database storage. The Contractor shall insure fiber optic cable is stored in temperatures that meet the manufacturer’s recommendations.
1.Fiber Optic Technician Qualifications. The Fiber Optic Technician qualifications shall be submitted with the Material Submitt al package for approval. The Contractor shall have the Engineer’s approval of the Fiber Optic Technician’s qualifications prior to commencing work. These technicians shall be in possession of their certification at all times and show this certification a s often as asked by the Engineer. The Department reserves the right to revoke the approval of any technician not demonstrating the skill and knowledge to perform at accepted industry standards. Failure to provide proof to the Engineer will result in a st op work being placed upon fiber optic work until such a time that proof of meeting

729.03 Construction Requirements.

these Fiber Optic Technician Qualification requirements are met. Contract time will not be stopped if the Contractor is unable to provide adequate proof or qualified staff. Only technicians that meet all these requirements shall perform fiber work including splicing, terminating fiber, and testing of fiber. Technician performing fiber terminations, splicing, and testing shall have:

a.Education: Attended and successfully c ompleted at least one four (4) day class on installation of fiber optic products conducted by major manufacturer of fiber products or an accredited/approved firm or organization. The entity conducting the training, along with the class and materials, shal l be current and accredited for certification by one of the following United States based certification organizations: Electronics Technicians Association (ETA), The Fiber Optic Association (FOA), or International Municipal Signal Association (IMSA). Fib er Optic Technicians shall maintain their certification and be in good standing with the applicable certification organization while performing such work on ALDOT projects. Technicians with expired or suspended certification shall not be allowed to conduc t work .
b.Work History: Technicians shall have a minimum of two (2) years of work experience with one year continuous for splicing, terminating and testing fiber optic cable. Work experience shall be within the last 5 years. The applicant shall submit a resume providing a summary of qualifications and a general description of professional experience, education and training in the fiber optic installation techniques (termination, splicing and testing). The applicant shall also provide a work record for the previous two years detailing specific project, types of installations, testing and a customer reference for each project. The applicant should include as much additional detail as reasonable to facilitate approval.
2.Fiber Optics Material Installat ion. It shall be the Contractor’s responsibility to protect reeled fiber optic cable from vandals or other sources of possible damage while unattended. The sections of cable intended for duct installation are produced to meet specific length requirements. Any damage to the cable sections may require replacement of the entire section, at the discretion of the Engineer. The Contractor shall be responsible for damage to the cable during handling and placing, and responsible for all cost to replace damaged fiber optic cable. The cable manufacturer's specifications regarding tensile strength, pulling capacity, and bending radius, etc. shall not be violated. Whenever unreeled cable is placed on the pavement or surface above a manhole, the Contractor shall provide barricades or other means of preventing vehicular or pedestrian traffic through the area. The “ figure -eight ” configuration shall be used when installing fiber optic cables. Fiber optic cable should not be coiled in a continuous direction exce pt for lengths of 100 feet {30.5 m} or less. The preferred size for the “ figure -eight ” is about 25 feet {7.6 m} in length, with each loop 9 feet {2.7 m} to 14 feet {4.3 m} in diameter. Traffic cones spaced 10 feet {3.0 m} apart are useful guides during “figure -eighting ”. When “ figure -eighting ” long lengths of cable, care should be taken to relieve pressure on the cable at the crossover of the eight. On projects where a fiber optic cable is to be mechanically or hand pulled, a “ Pull Tape” as specified in Sub-Article 893.10(d) shall be factory or field installed within conduit for the purpose of attaching to, and the pulling of said cable. PULL ROPES NOT SPECIFICALLY DESIGNED FOR FIBER OPTIC AND ELECTRICAL CABLE INSTALLATION SHALL NOT BE USED ON ANY ALDOT PROJECT. If a mechanical pulling machine is used, it shall be equipped with a monitored or recording tension meter. At no time shall the cable manufacturer’s recommended maximum pulling tension be exceeded. The fiber optic cable’s central strength member and aramid yard shall be attached directly to the pulling eye/pulling grip in accordance with the cable manufacturer’s Standard Operation and Installation Procedures (SOP). Contractor shall use cable manufacturer approved pulling grips to ensure th at the cable’s optical and mechanical characteristics are not degraded during installation.
a.Installation and Standard Operation Plan.
i.Manufacturer’s Operation and Installation Procedures. The Contractor shall install in accordance with the cable ma nufacturer’s Standard Operation and Installation Procedures (SOP). These procedures shall be provided upon the request of the Engineer.

729.03 Construction Requirements.

ii. Contractor’s Installation Plan. The Contractor shall submit to the Engineer for approval a detailed installation plan for all fiber optic cable installed as part of this project. The Contractor shall have the Engineer’s written approval prior to commencing any fiber optic cable installation. This installation plan shall include all proposed end -to-end cable splice po ints which shall be in a CommBox that was already designated as a splice point. The Contractor will be required to limit the amount of splice points within the network and maximize the length of each cable run. Reel lengths and end -to-end cable splice po ints shall be submitted by the Contractor and approved by the Engineer prior to the ordering of the fiber optic cable.

b.Designated Cable Slack (Maintenance Coil). Throughout the fiber optic cable installation, the Contractor shall be required to pull an d store excess cable slack at designated intervals. The following lengths of slack cable shall be minimums used unless otherwise shown on the Plans: CommBox with Splice Closure 75 ft. {23 m} per cable end CommBox without Splice Closure 150 ft. {46 m} per cable Pull Box 100 ft. {30 m} ITS Cabinet/Controller Cabinet 10 ft. {3 m} Hub Building 100 ft. {30 m} TMC/Transportation Control Center (TCC) (OSP Entrance) 100 ft. {30 m}
c.Slack Storage. The Contractor shall not leave slack cable lying free on the ground, bottom of a CommBox, bottom of a pull box, or floor of a Hub/TMC/TCC. Only during the actual pulling process will this be allowed. If channeling rack is not available on existing, the C ontractor may leave slack upon approval of the Engineer.
d.Aerial Lashing. Aerial cable shall be lashed to a separate stranded steel messenger wire within a Medium Density Polyethylene (MDPE) jacket. The fiber optic trunk cable shall not be lashed to messenger wire also used for signal heads or other similar items.
e.Riser Duct. Riser duct shall be in accordance with RISER ASSEMBLY requirements within this Specification and as shown on the Plans.
3.Fiber Optic Cable Tag and Labeling.
a.General. The Contractor shall label all fiber optic cabling with a unique identification in a permanent and consistent manner that is approved by the Engineer prior to installing fiber cable. The Engineer shall provide the Contractor with the identifications to be u sed. Fiber optic cable tag labels shall meet the material requirements within this Specification and as shown on the Plans. The Contractor shall provide these unique cable tag identifications on all test results or fiber related documents provided to the Engineer. Metal or non -metal fiber optic cable tags are to be primarily used within CommBoxes, ITS Cabinets, and Hub Buildings. Special non -metal aerial fiber optic cable tag labels are to be used for aerial installations. Cable tag labels shall be affi xed to the cable per the manufacturer’s recommendations; and shall be affixed in a manner which will not cause damage to the fiber. Handwritten labels shall not be allowed. The Contractor shall install cable tags within 1 foot {0.3 m} of each splice and /or termination point. Each tag label shall identify the cable type, fiber count, and each fiber optic cable origination and termination points (or next ITS site that the cable is connecting).
b.Aerial Fiber Cable Labeling. Aerial fiber optic cable tags shall meet the material requirements within this Specification and as shown on the Plans. Aerially -mounted fiber optic cable tags shall be placed at 500 ft. {152 m} increments linearly along the fiber optic cable path and shall be identifiable as ALDOT fiber when viewed from ground level.

729.03 Construction Requirements.

A “proof check ” sample, of quantity one, shall be produced and provided to the Engineer prior to procurement of the remaining units. The Contractor is required to obtain the Engineer’s approval of the “ proof check ” sample prior to subsequent procurements by the Contractor. If the Contractor does not obtain approval prior to subsequent procurements, the Contractor assumes the risk of the aerial fiber optic cable tags being rejected even after installation. No paymen t shall be made to the Contractor if the aerial fiber optic tag is rejected.

4.Fiber Optic Testing. The Contractor shall supply all equipment, materials and software necessary to perform the test as specified within the Specifications. Fiber optic testi ng shall be performed by certified Fiber Optic Technicians approved as specified within the Specifications. Test for attenuation, decibel loss, shall be measured in dB/km. The Contractor required fiber tests shall be done by a certified Fiber Optic Techn ician in the presence of the Engineer or his/her designee.
a.Fiber Optic Test Methods.
i.Power/Light Meter Test. A typical Power/Light Meter Test consists of the following steps/conditions: • Connect the light source to the terminated fiber at the location identified by the Engineer. Connect a power meter to the other end of the fiber at the location identified by the Engineer. Record the results in accordance with standard industry practice and submit the test report to the Engineer. • Use the light frequencies of 1310 nm and 1550 nm for single -mode unless otherwise directed by the Engineer. • Perform the test bi -directionally. A Project Inspector shall witness and approve the results before f inal acceptance by the Engineer. ii. Optical Time Domain Reflectometer (OTDR) Test. OTDR shall be used for fiber testing as a means of determining the integrity of the fiber strands. A launch cable of a length exceeding the “dead zone” of the OTDR or a f actory “ fiber box” of 246 feet {75 m} minimum with no splices within the box shall be used for testing with the OTDR. If a patch cable is utilized, the length of patch cable shall be stored on a fiber storage bobbin with a 5 inch {127 mm} minimum diameter . Termination of the fiber for testing shall be the factory fiber via “ lab splice”, mechanical splice, or fusion splice, bare fiber adapter, or mechanical termination. Supplemental patch cables and barrel connectors to transition between connector types shall not be allowed. The traces shall demonstrate dB/km loss not to exceed +3% of the factory test documentation that came with that reel of fiber or 1% of the cable’s published production dB loss per km as specified within the Specifications plus the ma ximum OTDR error level as noted by the manufacturer of the OTDR (typically +2%). The OTDR should be calibrated to show anomalies of 0.1 dB minimum. When a “gainer” appears in an OTDR trace, that strand shall be bi -directionally tested. Each trace shall include the following data: • The trace itself with a launch transition not to exceed 6 dB; • Measurement results - cursor, marker, distance between cursor and marker, total loss between launch point and end of fiber, attenuation calculation in dB/km; • Cable information - fiber identification (if not the filename), cable identification (reel number and manufacturer’s identification reel number), OTDR location, end of fiber location, operator identification, date shot, time shot; and, • Set up parameters - wavele ngth, pulse width, refractory index, range, and horizontal scale.
b.Fiber Optic Test Times (Milestones). The following fiber optic testing times/milestones should be observed and/or documented to the satisfaction of the Engineer.
i.Manufacturer’s On -Site Testing. The cable manufacturer shall provide necessary documents to validate test equipment along with test results delivered and provide to the Engineer upon cable delivery.

729.03 Construction Requirements.

ii. General Receiving Test. The Contractor shall provide the ALDOT Region TS M&O Engineer the fiber cable manufacturer’s OTDR test results and Power/Light Meter readings for each strand of outdoor fiber (i.e., trunk, drop, aerial, and armored) prior to performing the fiber optic cable receiving test. Prior to any work, the Contra ctor shall certify to the Engineer that any and all fiber optic cable that is to be used on said project has been delivered to the work site and/or the Contractor’s storage facility and meets the requirements as specified within the Specifications and was undamaged during shipping. Compliance with this requirement shall be accomplished in the following manner. The Contractor is recommended to OTDR test each fiber strand per loose tube on each reel of cable 14 days prior to installation. The Contractor a nd Engineer shall jointly inspect and test all reels of cable for damage prior to installation. The fiber optic cable shall meet the following factory attenuation criteria: • Fiber cable attenuation specified herein for 1310 nm and 1550 nm, • Strand lengths a re consistent in the OTDR reports, • Launch Transition < 0.6 dB, and • No event shown in the OTDR trace > 0.10 dB. Upon completion of these test procedures, the Contractor shall issue to the Engineer all test data as specified and a “ Letter of Quality Assurance” from said Contractor stating that the fiber cable has been delivered to the construction site and/or the Contractor’s storage facility and meets the requirements as specified within the Specifications. Upon the Engineer’s acknowledgment of the receipt and acceptance of the Letter of Quality Assurance, the Contractor may commence installation of said cable at the Contractor’s risk. No fiber optic cable shall be installed prior to the receiving test and the acceptance of the Engineer. iii. Existing Fiber Testing. The Contractor shall test any existing fiber cable to be used on the project before beginning any fiber work on those fibers. Existing dark fibers, whether to be used on the project or remain dark, shall be OTDR tested. Testing of any existing fiber strands that are currently lit shall be coordinated with the Engineer for scheduling when the lit fiber may be taken offline for testing. A minimum of seven (7) calendar day notice shall be given to the Engineer before testing lit existing fibers. These fiber test reports shall be submitted to the Engineer for review and acceptance. iv. Installation and Post Fiber Testing. As the cable is pulled off the reel, it shall be carefully inspected for jacket defects. If defects are noticed, the pulling operation shall be stopped immediately. The Contractor shall submit to the Engineer the proposed corrective action to be taken for review and acceptance. Armored fiber optic cable shall be properly grounded upon cable installation. This groundin g system shall be tested in accordance with the Specifications. Post installation testing ensures the integrity of the fiber strands have not been damaged during the installation process. Once the fiber cable has been installed, the Contractor shall OTDR test each fiber strand before proceeding to splicing and/or terminations. These OTDR test results shall be compared to the receiving OTDR test results for determining if any fibers were damaged by the Contractor’s work during construction. In such case t hat there is damage done during construction the Contractor shall be responsible for all equipment, materials and labor to repair the damage to the satisfaction of the Engineer at no additional cost to the Department. The Engineer has the final determinat ion of what constitutes damage during construction. At minimum, no event shall exceed 0.10 dB post installation. The process for repair and/or replacement of cable shall be submitted to the Engineer for review and acceptance prior to conducting the work. Repaired and/or replaced cable shall be retested to ensure compliance with standards. Test reports shall be submitted to the Engineer for review and acceptance.

v.Termination/Splicing Complete Testing. Upon completion of the installation of fiber cab les, drop cables, splices, and termination of cable ends; dependent on the project requirements as shown on the Plans, each fiber terminated and spliced shall be OTDR and Power/Light Meter tested. The Contractor shall review the OTDR and Power/Light Meter results to ensure the fiber attenuation, splice loss, and connector pairs meet the requirements as specified within the Specifications. The reviewer (also a certified Fiber Optic Technician) shall be different from the certified Fiber Optic Technician wh o performed the installation and tests. The Contractor shall

729.03 Construction Requirements.

clean, polish, re -terminate, and/or re- splice in order to bring the results within specified tolerances. vi. Fiber Optic Test Reporting. Upon completion the Contractor shall issue to the Engine er all traces and loss/length print outs. These are to be submitted in a suitable binder organized by cable and strand number. A cover sheet is required for each binder indicating which cable(s) were tested, the OTDR user’s name, the certified reviewer’s name, the type of test performed, and the date(s) of the test. Cover sheets for final test results bearing the reviewer’s signature, the date signed, and a statement indicating that the installation complies with the Specification’s requirements are required. The Contractor’s employee who has reviewed the traces is required to sign or initial them. A check mark is required on all traces that satisfy the Specification’s requirements. For intermediate test results, the Contractor shall flag any discrepan cies that may exist with a short description of the proposed corrective action (e.g. re- splice). Where test results do not satisfy the requirements as specified within the Specifications, the Contractor shall provide justification as to why the testing an d/or material are not able to prove meeting the requirements as specified within the Specifications. This binder/package is to be submitted to the Engineer for fiber work acceptance and distribution. Also with this binder/package, the Contractor shall su bmit to the Engineer on a data compact disk or other approved electronic media the raw OTDR fiber trace files along with the OTDR documentation (manufacturer/model/serial number). The Contractor may alternately submit this binder/package as an electronic submittal (preferably in PDF format or as approved by the Engineer). No payment for splices or terminations shall be made unless fiber optic test reports and ALDOT’s OSP Database Forms have been accurately completed by the Contractor and submitted to the E ngineer.

c.Fiber Distribution Units (FDU), Connectors, and Fan -Out Kit. The Contractor shall assemble and install all necessary material and equipment and furnish a working Fiber Distribution Unit as shown on the Plans and as specified within the Specifi cations. All items that are required to complete the installation and ensure a fully functional and operational system shall be supplied by the Contractor.
1.Distribution Hardware. The following distribution equipment specifications cover installations of Fiber Distribution Units from the headend and hub, primary fiber distribution unit (PFDU) to secondary fiber distribution unit (SFDU) which are utilized within the individual cabinets and communication closets within buildings or within hub buildings. When splicing in the field within a CommBox or aerial installation, a splice closure shall be provided as indicated on the Plans and in accordance with Article 729.03(q)2, “ Installation of Splice Closure (Underground and Aerial) ”.
2.Fan-Out Kit. Fan-out kits shall be installed per fan -out kit and/or fiber optic cable manufacturer procedures and standard fiber connector installation training. Fan-out kit shall be compatible with the fiber optic cable being terminated and shall be color- coded to ma tch the optical fiber scheme or as specified within this Specification.
3.Fiber Connectors. Installer of fiber connectors shall have been trained to perform the installation of the type of connector being installed. Manufacturer guidelines shall be fo llowed. Prior to testing connector, installer shall visually verify connector end is clean of foreign materials using a fiber scope. Heat cure epoxy connectors are the preferred method and shall be used unless otherwise indicated on the Plans.
4.Cable Management. The Contractor shall ensure that fiber cables are installed in the manner in which they were designed for the FDU. Cables shall be secured in the locations designed by the FDU manufacturer using zip ties while ensuring the fiber cable is not o verly bound causing attenuation loss in the fiber cable. The excess end of zip ties shall be cleanly cut flush. Fiber cable shall not be stretched, kinked, or bound when run within the cable management system.

729.03 Construction Requirements.

5.Splice and Termination Procedure. The procedure for fusion splicing shall be submitted to the Engineer for approval. This submittal shall consist of:
a.OSP Database Form(s);
b.manufacturer/model of fusion splicer and date of last calibration;
c.form of splice protection; and
d.means of accessibility for splice protection and traffic control. The Contractor shall only splice fibers at locations as shown on the Plans unless otherwise approved by the Engineer. All splices shall be protected and stored in fiber optic splice units or integra ted fiber optic splice and termination units that are housed in field cabinets, pull boxes, CommBoxes, hubs, and other buildings. The Contractor shall document all splice and terminations on forms provided by the Engineer. No payment for splices or termin ations shall be made unless forms have been accurately completed by the Contractor and accepted by the Engineer. Fiber optic cables shall terminate in a fiber optic splice closure or fiber distribution unit where ends are protected. During installation, f iber optic cable ends must be protected per manufacturer recommended methods and as approved by the Engineer.
6.Pre-terminated Connector Assemblies. Pre-terminated Connector Assemblies (i.e., Factory Connector Build -Outs, or pigtails) may be spliced onto a cable as an alternative to installing heat cure epoxy or mechanical connectors. Pre - terminated Connector Assemblies shall be installed per manufacturer’s standard operating procedures of the fiber optic cable and fiber distribution unit; and, as approv ed by the Engineer. Pre-terminated Connector Assemblies (PTCA) cables shall be labeled where the buffer tube being spliced is permanently indicated on the PTCA cable jacket. This labeling is to be done prior to splicing.
7.Fiber Optic Patch Cable. Fiber optic patch cables (a.k.a. patchcords or jumpers) shall be appropriately sized for the length of run. Excess patch cable is to be limited to no more than one slack coil of 6 inch diameter. Fiber optic patch cables and connectors shall be compatible with the fiber optic cable and equipment to which it will connect.
d.Network Devices. The Contractor shall assemble and install all necessary material and equipment and furnish a working Network Device as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operational system shall be supplied by the Contractor. Wiring connections in poles shall be environmentally sealed using a m inimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. Final network device locations shall be accepted by the Engineer prior to installation.
1.Managed Ethernet Switch.
a.Installation. Managed Ethernet Switch (MES) shall be installed as shown on the Plans and mounted using manufacturer recommended parts. Ensure that the switch is resistant to all Electromagnetic Interference (EMI). Verify that the switch is mounted securely and is full y accessible by field technicians. Wiring shall be run within wire raceways and secured using zip ties.
2.Wireless Network Device.
a.Wireless Equipment Selection and Installation. The Contractor shall be responsible for determining field conditions of licensed and unlicensed wireless radio site including interference (noise). The Contractor shall perform wireless path loss analysis to determine appropriate radio equipment and antennas and mounting heights necessary for each site. This analysis shall be provided to the Engineer for review and acceptance. The Contractor shall be responsible for selecting equipment which meets the minimum performance requirements shown within the Specifications with the required annual availability at the most constrain ed modulation (i.e., smallest dB range in modulation to obtain for that radio unit).

729.03 Construction Requirem ents.

Prior to deploying and operating a licensed frequency, the Contractor is responsible for performing a frequency coordination, filing a public notice, and submitting an application (Form 601) with the FCC to ensure that no one else is already operating on the same frequency or a frequency that will inject interference on existing systems. If licensed radios encounter interference, it is typically resolved with the assistanc e of the regulatory body.

b.Antenna Installation. Technicians performing installation work shall have a hardware certification by the microwave manufacturer on the product being installed. Prior approval from the Engineer shall be obtained for the instal lation and sealing process when field drilling is required to mount an antenna on an existing cabinet and/or support structure. Antenna mounts shall be secured to prevent movement of antennas in high wind conditions. Once the antennas are aligned, the pos ition shall be marked with torque marking paint that shows any movement about the azimuth and elevation axis. Pictures of these marks shall be submitted as part of the as -built plan set submittal. These marks shall be made such that they do not deteriora te in the weather or sun.
c.Cable Installation. Cable shall be routed as shown on the Plans. When the Plans do not denote a specified route, prior approval from the Engineer shall be obtained for the proposed route. Cables mounted internal to structure supports shall use a hoisting grip to properly secure each cable type at the top of the support structure. Lightning arrestors shall be installed as shown on the Plans and grounded on the support structure. Wiring connections in supports shall be enviro nmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. A drip loop shall be provided where cable enters a support structure; the bottom of the loop shall be lower than the cable entry point. Structure entries shall be through a weatherhead, grommet or sealed using butyl rubber.
e.Camera.
1.General. The Contractor shall assemble and install all necessary material and equipment and furnish a working Closed -Circuit Television (CCTV) camera as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operational system shall be supplied and installed by the Contra ctor. Wiring connections in poles shall be environmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. The Contractor shall provide a camera installation complete with associat ed detection equipment, control equipment, power supplies, and any other camera -related field electronic equipment and transient voltage surge suppression as shown on the Plans and as specified within the Specifications. The Contractor shall provide an in stallation kit with mounting brackets, data cables, power cables, hardware and any incidentals required by the manufacturer. The Contractor shall maintain full responsibility for the camera housing mounting to the support structure and confirm that the cam era can be properly mounted on the support structure prior to installation. The Contractor shall securely mount the camera on the support structure. The camera shall be constructed and shall be adjusted to obtain optimum function of the camera. The camer a, cabinet, and other components shall be mounted at locations as shown on the Plans. The Contractor is responsible to ensure that the camera does not interfere with the operation of any other ITS electronic equipment when installed. The Contractor shall be responsible for camera configuration and initial settings (i.e., date/time stamp, compass orientation, time server IP address, alert settings, camera ID label, SNMP settings, and initial user account login defaults). These camera settings shall be coor dinated with the ALDOT Region TSM&O Engineer prior to placing camera and associated equipment in service.
a.Cabinet Equipment.
i.Controller Cabinet Installation. The Contractor shall install the camera controller in the designated space of the ITS Cabi net. The Contractor shall install any associated camera equipment per the manufacturer’s requirements and as shown on the Plans.

729.03 Construction Requirements.

ii. Wiring and Connections. Upon completion of wiring and connections, bundle all incoming cables and hold in place with nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point only. Install cables and connectors so that the manufacturer's rated minimum bending radius and pulling tension are not exceeded. Take proper care to prev ent abrasions to the cable jacket during installation.

b.Cables and Electrical Power Service. The Contractor shall install the conduit for electrical cable between the service pole and the ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article 729.03(m) and Article 893.13, “Electrical Power Service and Transformer” . All camera data shielded cables shall be routed separate from any 120 Vac or greater power wiring or surge suppressor ground wiring. “Power -Over-Ethernet” (POE) communications cables shall be permitted where installation and cable is in accordance with NEC Chapter 8. Cable, shield or conductor used for camera control, power supply, or grounding shall not be spliced.
c.Interface Protocol. The Contractor shall provide the Engineer with the manufacturer’s open software interface/protocols for the Camera so that it can be fully integrated into the Department’s current ALGo ATMS software.
d.Manufacturer’s Software. The Contractor shall provide the manufacturer’s configuration and diagnostic software along with all licenses, software installation media and documentation/manuals to the Engineer at the completion of the Burn -In. Any special camera configurations or firmware updates shall also be delivered to the Engineer with this package.
f.Vehicle Detection Systems (VDS) .
1.General. The Contractor shall assemble and install all necessary material and equipment and furnish a working VDS as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operational system shall be supplied by the Contractor. Wiring connections in poles shall be environmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. The Contractor shall provide a VDS installation complete with associated detection equipment, control equipment, power, and communications equipme nt as shown on the Plans and as specified within the Specifications. The Contractor shall provide an installation kit with mounting brackets, data cables, power cables, hardware and any incidentals required by the manufacturer. The Contractor shall mainta in full responsibility for the VDS housing mounting to the support structure and confirm that the VDS can be properly mounted on the support structure prior to installation. The Contractor shall securely mount the VDS on the support structure. The VDS shall be constructed and shall be adjusted to obtain optimum function of the VDS. The VDS, cabinet, and other components shall be mounted at locations as shown on the Plans. The Contractor is responsible to ensure that the VDS does not interfere with the op eration of any other ITS electronic equipment when installed. The Contractor shall be responsible for VDS configuration and setting up initial pre -sets using the manufacturer’s software.
a.Cabinet Equipment.
i.VDS Controller Cabinet Installation. The ITS Cabinet for remote control of the VDS from ground level shall conform to the requirements in Sub-Article 729.03(l) and Article 893.12, “ITS Cabinet” . The ITS Cabinet shall be installed at locations as shown on the Plans unless otherwise designated and approved by the Engineer. The Contractor shall install the VDS controller in the designated space of the ITS Cabinet. The Contractor shall install any associated VDS equipment per the manufacturer’s requirements and as shown on the Plans.

729.03 Construction Requirements.

ii. Wiring an d Connections. Upon completion of wiring and connections, bundle all incoming cables and hold in place with nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point only. Install cables and connectors so that the manufacturer's rated minimum bending radius and pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during installation.

b.Cables and Electrical Power Service. The Contractor shall install the conduit for elec trical cable between the service pole and the ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article 729.03(m) and Article 893.13, “Electrical Power Service and Transformer” . All VDS data cables shall be routed separate from any 120 Vac or greater power wiring or surge suppressor ground wiring. Cable, shield or conductor used for VDS control, power supply, or grounding shall not be spliced.
c.Interface Protocol. The Contractor shall provide the Engineer with the manufacturer’s open software interface/protocols for the environmental sensor.
d.Manufacturer’s Software. The Contractor shall provide the manufacturer’s configuration and diagnostic software along with all licenses to the Engineer at the completion of the Burn- In.
2.Radar Vehicle Detection System (RVDS). Structure mounted equipment shall be installed per the manufacturer’s recommendations for elevation and orientation. After installation, the RVDS shall be tested for accuracy by comparing data collected by the RVDS to manual count data under the conditions as specified within the Specifications or as approved by the Engineer to verify the RVDS is operating within the accuracy requirements as specified within the Specifications.
3.Magnetometer Vehicle Detection System (MVDS). In ground magnetometer units shall be installed per the manufacturer’s recommendations for depth, orientation, and sealant. Structure mounted equipment shall be installed per the manufacturer’s recommendations for elevati on and orientation. After installation, the MVDS shall be tested for accuracy by comparing data collected by the MVDS to manual count data under the conditions as specified within the Specifications or as approved by the Engineer to verify the MVDS is oper ating within the accuracy requirements as specified within the Specifications.
4.Bluetooth Data Collection System (BDCS). Structure mounted equipment shall be installed per the manufacturer’s recommendations for elevation and orientation. After installat ion, the BDCS shall be verified as operational by confirmed matches of discoverable and/or non -discoverable Bluetooth devices between two BDCS locations for travel time purposes.
g.Dynamic Message Sign (DMS).
1.General. The Contractor shall assemble and install all necessary material and equipment and furnish a working DMS as shown on the Plans and as specified within the Specifications. All items that are required to complete t he installation and ensure a fully functional and operational system shall be supplied by the Contractor. Wiring connections in poles shall be environmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. The Contractor shall provide a DMS installation complete with associated control equipment, 120 Vac power, and communications equipment as shown on the Plans and as specified within the Specifications. The Contractor shall provi de an installation kit with mounting brackets, data cables, power cables, hardware and any incidentals required by the manufacturer. The Contractor shall maintain full responsibility for the sign housing mounting to the support structure and confirm that t he sign can be properly mounted on the sign support structure prior to installation. The Contractor shall securely mount the sign on the sign support structure. Initially, the Contractor is to set the housing at a 3 degree tilt forward toward traffic and adjust the housing

729.03 Construction Requirements.

under both day and night conditions to optimize the view of the sign from the roadway by a motorist and eliminate random reflections as directed by the Engineer. Alternatively, the housing may be constructed at a 3 -degree tilt toward traffic, if approved by the Engineer, but shall be adjusted to obtain the same optimization of the viewing of the sign from the roadway. The Contractor shall attach and secure all mechanical hardware for initial attachment prior to the reopening of lanes t o traffic. The Contractor shall complete attachment of hardware prior to the release of crane cables. The Contractor shall also install and connect the DMS wiring and communications cables to the ground cabinet and disconnect switch in the controller cabinet only after attaching and securing the sign to the sign structure. During the Acceptance Testing, the Engineer will evaluate the initial setting of the sign and direct the Contractor to adjust the sign tilt if necessary. The Contractor shall use nylon stop washers with mounting attachments. For all structural aspects, stainless lock washers and nuts are unacceptable; use stainless steel nuts with nylon inserts for locking. The Contractor will lift and install the DMS housing and display in place on the overhead structure only with prior approval of, and in the presence of the Engineer. Do not lift and install the DMS housing and display until all equipment, materials, and labor are available such that the DMS can be operated with messages from th e local DMS controller within 72 hours of installation on the overhead structure. The Contractor shall only program message displays on the DMS at the direction of the Engineer. Make sight alignment adjustments to the DMS housing and display as directed by the Engineer. Securely install mounting hardware to the torque recommended by the overhead sign support manufacturer. The DMS shall be mounted at locations shown on the Plans. The DMS shall be mounted using the manufacturer supplied mounting brackets. The Contractor is responsible to ensure that the DMS does not interfere with the operation of any other ITS electronic equipment when installed. The Contractor shall be responsible for DMS configuration and setting up initial pre- sets using the manufacture r’s software.

a.Photosensor System. The Contractor shall aim one sensor in the northerly direction (away from nearby lights) and scale it for a reading of up to 100 lux (horizon type). The other two sensors shall be aimed in opposite directions and perpendicular to the sign face. These two sensors shall be scaled for a reading of up to 100,000 lux. The sensors are to be mounted on the top of the housing near the right side for ease of maintenance. The aiming angle of the sensors shall be adjustable. The Contractor shall aim the photosensors and calibrate the dimming system consistent with field conditions found for each sign as a part of the installation process. This work is to be completed prior to any Acceptance Testing.
b.Cabinet Equipment.
i.Controller Cabinet Installation. The ITS Cabinet for remote control of the DMS from ground level shall conform to the requirements in Sub-Article 729.03(l) and Article 893.12, “ITS Cabinet” . The ITS Cabinet shall be installed at locations as indicated on the Plans unless otherwise designated and approved by the Engineer. The ITS Cabinet shall be mounted to the support pole(s) at a height of 42 inches {107 cm} from ground level to the bottom of the cabinet housing and shall be easily accessed by maintenance personnel. The Contractor shall install the DMS controller unit in the designated space of the ITS Cabinet. The Contractor shall install any associated DMS equipment per the manufacturer’s requirements and as shown on the Plans. ii. Wiring and Connections. Make all connections to terminal boards or screw -type equipment terminals with insulated fork-tongue compression connectors only when using stranded cable. Make all wiring to bulkhead connectors on equipment housings with MS bayonet -type connectors. Solder connector joints for use with extra -low voltage systems, with the joint metals preheated to the flow temperature of the solder or crimped using ratchet -type positive crimp tools and a double crimp (conductor and jacket) connector. Remo ve the outer jacket of data and communications cables to expose approximately 6 in. {150 mm} of the shielding or drain wire. Twist together and solder the shielding or drain wire for

729.03 Construction Requirements.

all cables serving a similar function with a 10 AWG minimum insulated (g reen jacketed) ground lead securely connected to the cabinet ground bus. Make the ground lead routing as short as possible. Cut the shield off and leave it isolated at the other end. Upon completion of wiring and connections, bundle all incoming cables a nd hold in place with nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point only. The controller will be powered from the power distribution assembly provided in the ITS Cabinet. Bond the shields of all extra -low voltage cables to the ground bus inside the cabinet. The shield inside the sign enclosure shall be unconnected and insulated. Route low voltage cables and extra -low voltage cables installed in the cabinet on opposite sides of the cabinet. Group similar extra - low voltage cables in the controller cabinets, between common locations, together with cable ties. Install cables and connectors so that the manufacturer ’s rated minimum bending radius and pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during installation.

c.Cables and Electrical Power Service. The Contractor shall install the conduit for electrical cable between the service pole and the ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article 729.03(m) and Article 893.13, “Electrical Power Service and Transformer” . All DMS data cables shall be routed separate from any 120 Vac or greater power wiring or surge suppressor ground wiring. Cable, shield or conductor used for DMS control, power supply, or grounding shall not be spliced. The shield of low voltage instrumentation cables shall be grounded at one end only.
d.Use and Operations of DMS Prior to Final Acceptance. The Department will approve or control any and all DMS displays at all times that a display is in potential public view to ensure compliance with current MUTCD . When potential public view exists, no message or graphical display of any kind or activation of any DMS display component is permitted witho ut prior approval of the Engineer. At such time as the Engineer determines that any given DMS is ready for Department control, the Department will exercise complete and total control of that DMS display and all central and local communications with that l ocal DMS controller. Prior to any action, coordinate with the Engineer any remaining work or any testing or maintenance that may affect that DMS display. Do not interpret such DMS display control as acceptance of the project in whole or in part. Do not construe such action as a waiver by the Engineer of any provision of this Specification. Do not consider such use part of the Burn -In Period.
e.Interface Protocol. The Contractor shall provide the Engineer with the manufacturer’s open software interface/protocols for the DMS.
f.Manufacturer’s Software. The Contractor shall provide the manufacturer’s configuration and diagnostic software along with all licenses to the Engineer at the completion of the Burn -In.
2.DMS Supporting Structure. Supporting Structure used for mounting the DMS and equipment shall conform to the requirements given in Sections 715, 717, and 718 . For each DMS, the Contractor shall provide a complete Supporting Structure design which shall include all structural dimensions for the supporting structure and associated foundations.
a.DMS Housing Structural Design. Professional Engineer calculations and a complete set of sealed DMS housing drawings shall be included within the DMS manufacturer’s submittal to the Engineer. [ See Item 893.07(a)3, “Material and Process Standards” and Item 893.07(a)4, “Sign Housing” for special material submittal requirements regarding: (a) Professional Engineer Certification of DMS Housing Structural Design and (b) welding inspection certification.] A lifting mechanism shall be provided for transporting and installing the DMS and shall be a permanent, integral part of the DMS housing structural frame. Professional Engineer analysis of the DMS housing design shall include a certification of the D MS lifting mechanism.

729.03 Construction Requirements.

3.Concrete Foundation. The Contractor shall submit Concrete Foundation design for each DMS Supporting Structure in accordance with Section 718. The foundation design shall include all dimensions and reinforcing steel configuration. The Contractor shall contact the Utility Companies to determine the location of underground utilities in the area where the foundations are to be located. The Contractor shall be responsible for repairing, to the satisfaction of the Utility Company, any utilities damaged by the Contractor.
4.DMS Acceptance Test. The Contractor shall perform Acceptance Test on the DMS and ITS electronic equipment installed under this Project and have materials specified within this Specification. The Acceptance Test sha ll be in accordance with Sub -Article 729.03(r), “Testing” . The Visibility Inspection of the Field Test shall include the continuous display of a test message on each sign for a period of twenty 24 -hour days. If any sign fails unacceptably (traveling motor ist cannot recognize the test message) to complete the 20 day Burn -In due to component failure, the component shall be replaced and the 20 day Burn -In Period shall be started again from day one. Acceptable failures are those that do not inhibit the motorin g public from message recognition. Any component failures that occur within the acceptable failure shall be replaced prior to final acceptance. The Field Test of the Acceptance Test procedure shall prove that Central and Field Controller software comply w ith the Specifications, and it shall demonstrate that all DMS system equipment is fully integrated and operational. The Field Test procedure shall include the successful exercising of all diagnostic features provided with the DMS. Testing of the DMS Centr al Software and Computer shall include demonstrating proper data transfer to and from each remote site.
h.Environmental Sensor .
1.General. The Contractor shall assemble and install all necessary material and equipment and furnish a working environmenta l sensor as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operational system shall be supplied by the Contractor. Wiring connections in poles shal l be environmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. The Contractor shall provide an Environmental Sensor installation complete with associated control equipment, 120 Vac power, and communications equipment as shown on the Plans and as specified within the Specifications. The Contractor shall provide an installation kit with mounting brackets, data cables, power cables, hardware and any incidentals required by the ma nufacturer. The Contractor shall maintain full responsibility for the sensor housing mounting to the support structure and confirm that the sensor can be properly mounted on the support structure prior to installation. The Contractor shall securely mount the sensor on the support structure. The sensor shall be constructed and shall be adjusted to obtain optimum function of the sensor. The sensor, cabinet, and other components shall be mounted at locations as shown on the Plans. The Contractor is responsible to ensure that the sensor does not interfere with the operation of any other ITS electronic equipment when installed. The Contractor shall be responsible for environmental sensor configuration and setting up initial pre-sets using the manufactu rer’s software.
a.Cabinet Equipment.
i.Controller Cabinet Installation. The ITS Cabinet for remote control of the environmental sensor from ground level shall conform to the requirements in Sub -Article 729.03(l) and Article 893.12, “ITS Cabinet” . The ITS Cabinet shall be installed at locations as shown on the Plans unless oth erwise designated and approved by the Engineer. The Contractor shall install the environmental sensor data processing unit in the designated space of the ITS Cabinet. The Contractor shall install any associated environmental sensor equipment per the manu facturer’s requirements and as shown on the Plans.

729.03 Construction Requirements.

ii. Wiring and Connections. Upon completion of wiring and connections, bundle all incoming cables and hold in place with nylon cable ties. Connect the front panel and chassis to the cabinet ground bus fr om a single point only. Install cables and connectors so that the manufacturer's rated minimum bending radius and pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during installation.

b.Cables and Electrical Po wer Service. The Contractor shall install the conduit for electrical cable between the service pole and the ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article 729.03(m) and Article 893.13, “Electrical Power Service and Transformer” . All environmental sensor data cables shall be routed separate from any 120 Vac or greater power wiring or surge suppressor ground wiring. Cable, shield or conductor used for environmental sensor control, power supply, or grounding shall not be spliced.
c.Interface Protocol. The Contractor shall provide the Engineer with the manufacturer’s open software interface/protocols for the environmental sensor.
d.Manufacturer’s Software. The Contractor shall provide the manufacturer’s co nfiguration and diagnostic software along with all licenses to the Engineer at the completion of the Burn -In.
i.Highway Advisory Radio (HAR).
1.General. The Contractor shall assemble and install all necessary material and equipment and furnish a working HAR as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operational s ystem shall be supplied by the Contractor. Wiring connections in poles shall be environmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. The Contractor shall provide a HAR i nstallation complete with associated control equipment, power, and communications equipment as shown on the Plans and as specified within the Specifications. The Contractor shall provide an installation kit with mounting brackets, data cables, power cables, hardware and any incidentals required by the manufacturer. The Contractor shall maintain full responsibility for the HAR housing and antenna mounting to the support structure and confirm that the HAR can be properly mounted on the support structure prior to installation. The Contractor shall securely mount the HAR on the support structure. The HAR shall be constructed and shall be adjusted to obtain optimum function of the HAR. The HAR, cabinet, and other components shall be mounted at lo cations as shown on the Plans. The Contractor is responsible to ensure that the HAR does not interfere with the operation of any other ITS electronic equipment when installed. The Contractor shall be responsible for HAR configuration and setting up initi al pre -sets using the manufacturer’s software.
a.Cabinet Equipment.
i.Controller Cabinet Installation. The ITS Cabinet for remote control of the HAR from ground level shall conform to the requirements in Sub-Article 729.03(l) and Article 893.12, “ITS C abinet” . The ITS Cabinet shall be installed at locations as shown on the Plans unless otherwise designated and approved by the Engineer. The Contractor shall install the HAR controller in the designated space of the ITS Cabinet. The Contractor shall ins tall any associated HAR equipment per the manufacturer’s requirements and as shown on the Plans. ii. Wiring and Connections. Upon completion of wiring and connections, bundle all incoming cables and hold in place with nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point only.

729.03 Construction Requirements.

Install cables and connectors so that the manufacturer ’s rated minimum bending radius and pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jack et during installation.

b.Cables and Electrical Power Service. The Contractor shall install the conduit for electrical cable between the service pole and the ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article 729.03(m) and Article 893.13, “Electrical Power Service and Transformer” . All HAR data cables shall be routed separate from any 120 Vac or greater power wiring or surge suppressor ground wiring. Cable, shield or conductor used for HAR control, power su pply, or grounding shall not be spliced.
c.HAR Antenna Grounding. The HAR antenna grounding design and design submittal shall be either conducted by or signed off by the HAR equipment manufacturer. The Contractor’s HAR submittal package shall include antenna and grounding details showing design configuration and proposed equipment and materials, supporting design calculations, recommended installation methods/procedures to be utilized, and equipment and proposed material specifications/cut -sheets.
d.Interface Protocol. The Contractor shall provide the Engineer with the manufacturer’s open software interface/protocols for the environmental sensor so that it can be fully integrated.
e.Manufacturer’s Software. The Contractor shall provide the manufacturer’s configuration and diagnostic software along with all licenses to the Engineer at the completion of the Burn -In.
j.Conduit, Conductor , Locate Tone Wire, Warning Tape, and Messenger . Work shall be performed in accordance with the highest industry standards, meeting the requirements of the latest editions of the NEC, NESC, and NEMA.
1.Installation of Buried Duct and Conduit. Conduit shall be installed by means of open trenching, plowing, or precision directional boring. Spare conduit shall have Pull T ape installed in the duct. Maximum spacing between supports and spacing between expansion fittings shall be as shown on the Plans or, if not shown, according to the manufacturer’s recommendations. If rocky soil conditions are encountered during precision directional bore installations, SDR -9 HDPE conduit may be required as approved by the Engineer. Coiled non -metallic conduit shall be treated by a line tamer prior to underground (or below grade) installation. If more than one run of underground c onduit is required, install in one trench unless in conflict with NEC requirements. Extend conduit ends 2 inches {51 mm} above concrete surfaces and 4 inches {100 mm} above crushed stones bases; and install with bushings. For metallic conduit, install m etallic bushings. For non-metallic conduit, install non -metallic bushings. Where conduit connects to a panel, box, or other enclosure, use a locknut in addition to the bushing. Where non -metallic conduits join metal conduits, connection shall be made using appropriate couplings to form a watertight raceway. All conduits entering concrete foundations shall be provided with appropriate bushings at the ends. Conduits shall be stubbed approximately 2 inches {51 mm} above concrete and shall be provided grounding type bushings on conduit ends in the base of poles with copper bonding jumpers. Bends and offsets shall be avoided where possible, but where necessary, shall be made with a proper pipe bender or conduit bending machine. Conduit that has been crush ed or deformed due to improper bending or handling shall not be installed. Surface damage to RMC conduit shall be repaired in accordance with the Specifications. Exposed threads shall be regalvanized. After installation, conduits shall be tested for clearance with a 2 -inch long mandrel (a.k.a., pig) having a diameter 1/4 inch smaller than the inside diameter of the conduit. Conduits not allowing passage of the mandrel shall be rejected. After placement of conduit, all conduits shall be capped to prevent m oisture or foreign matter from entering until the fiber optic cable or conductor installation is started. Upon installation of fiber

729.03 Construction Requirements.

optic cable and/or conductor, conduit ends shall be sealed with duct sealer. Duct sealer shall be a water -blocking, close d-cell, easily removable/re -enterable, polyurethane foam material as recommended by the cable manufacturer and approved by the Engineer. Duct sealer shall be identified for use with the fiber optic cable and conductor insulation; and should not cause deterioration of the insulation over time. For underground conduit adjacent to gasoline service stations or other installations of underground gasoline or diesel storage, piping or pumps, and which lead to a cabinet, circuit breaker panel, service or any encl osure where an arc may occur during normal operation, the Contractor shall refer to the NEC for Class 1, Hazardous Locations.

2.Installation of Hanging Duct and Conduit. Maximum spacing between supports and spacing between expansion fittings shall be as shown on the Plans or, if not shown, according to the manufacturer’s recommendations. The conduit system shall include mechanisms such as expansion fittings or joints to ensure that the expansion and contraction stresses are normalized. Spacing or expansi on fitting shall be based upon manufacturer standards for the location conditions/environment of the installation. After placement of conduit, all conduits shall be capped to prevent moisture or foreign matter from entering until the fiber optic cable or conductor installation is started. Upon installation of fiber optic cable and/or conductor, conduit ends shall be sealed as permitted by the current NEC. If duct sealer is allowed and used, then the duct sealer shall be a water -blocking, closed -cell, eas ily removable/re -enterable, polyurethane foam material as recommended by the cable manufacturer and approved by the Engineer. Duct sealer shall be identified for use with the fiber optic cable and conductor insulation; and should not cause deterioration o f the insulation over time. The Contractor shall be fully responsible in the event defective conduit is installed and shall be held fully responsible for replacement (material and labor) of any conduit found to be defective due to manufacture error, improper construction, or improper installation for one year after the State’s acceptance of the project.
a.Installation of RTRC. The conduit shall be packaged for shipment at the factory. The conduit shall be assembled into manageable bundles. Each sectio n of conduit shall be shipped with protective caps over each end of the section. Conduit that arrives at the job site without the protective cover in place over both ends will be rejected by the Engineer. Conduit connections for RTRC shall be sealed with epoxy adhesive. Joints for RTRC shall be joined until the conduit ends are together. Once connected the joint pullout rating shall be equal to the tensile strength of the conduit. No reducing couplings shall be permitted in a conduit run.
b.Installat ion of RMC. The conduit shall be packaged for shipment at the factory. The conduit shall be assembled into manageable bundles. Each section of conduit shall be shipped with protective caps over each end of the section. Conduit that arrives at the job si te without the protective cover in place over both ends will be rejected by the Engineer.
3.Installation of Conductor. On projects where a conductor(s) and/or electrical cables are to be mechanically or hand pulled, a “Pull Tape” as specified in Sub -Article 893.10(d) shall be factory or field installed within conduit for the purpose of attaching to, and the pulling of said conductor/cable. PULL ROPES NOT SPECIFICALLY DESIGNED FOR FIBER OPTIC AND ELECTRICAL CABLE INSTALLATION SHALL NOT BE USED ON ANY ALDOT PROJECT. Conductors shall have the appropriate identification on the outer jacket. Conductors not meeting this requirement or with illegible identification are not allowed. Wiring within pull boxes and CommBoxes shall be neatly arranged and labeled/ tagged. All ends of hardwire shall be taped to exclude moisture and shall be so kept until splices are made and terminal appliances attached. The ends of spare conductors shall be protected as permitted by the current NEC (capped method is preferred) . End of fiber optic cables shall be protected from moisture by methods as shown on the Plans or as approved by the Engineer. Splices and taps in electrical conductors shall only be made in pull boxes, CommBoxes and pole bases. They shall be made with solder less split bolt connectors. Splices and taps shall be protected and sealed in silicone gel filled enclosures to provide a waterproof connection and to ensure the required electrical insulation. Silicone gel filled enclosures shall be re -enterable; shall be ultra -violet

729.03 Construction Requirements.

(UV) resistant, listed for temperatures from -40°F to 194°F { -40°C to 90°C}; and shall be impact and abrasion resistant. The enclosure shall be sized as shown in the following table: CONDUCTOR SIZE GEL ENCLOSURE SIZE 4 AWG and smaller #2 2 AWG #2.5 Larger than 2 AWG #3 Installation of conductors shall be in accordance with the NEC. Conductors shall not be pulled into a conduit until the installation of the conduit is complete. Prior to the installation of conductors, the Contractor shall ensure the conduit is free of w ater and debris by blowing air and pulling a foam ball, mandrel, or brush through the conduit. The ends of conduit shall be cleaned of bures and capped with a bushing to protect cables during installation. Conductors in conduits shall be carefully pulled into place using approved methods so that the conductors will not be damaged. Powdered soapstone, talc, or other inert lubricant specifically designed for the purpose shall be used when pulling conductors through the conduit. All conductors within a single conduit shall be pulled at the same time; and, shall be handled and installed in such a manner as to prevent kinks, bends or other distortion which could damage the conductor and outer covering. When conductors are pulled through hand holes, pole shaf ts, etc., a pad of firm rubber or other suitable materials shall be placed between the conductors and the edges of the opening to prevent damage to the conductors. The pulling tension on conductors shall not be exceeded. Friction reduction multiduct pulli ng sleeves may be used as an alternate to lubricant. The Contractor shall not exceed the NEC conduit fill capacity requirements. Fiber optic cables shall not be installed in conduits containing current carrying conductors.

4.Installation of Locate Tone Wire. Locate Tone Wire shall be installed along the entire underground conduit run for non- conductive fiber optic cables in accordance with this Specification and as shown on the Plans. Ensure that the Locate Tone Wire enters all CommBoxes and Pull Boxes as the fiber optic cable ; and, that a minimum of 10 feet {3 meters} of slack is coiled and neatly stored in each box. Locate Tone Wire shall be suited for direct burial and shall be continuous. Locate Tone Wire system does not require to be grounded sinc e it is a non -current carrying conductor used for locating fiber optic cable only. Locate Tone Wire shall not be installed inside ITS Cabinets. Where fiber optic conduit is installed via trenching operation, the Locate Tone Wire is to be installed no more than 3 inches {7.62 cm} above the conduit. Where fiber optic conduit is installed via boring operation, the Locate Tone Wire is to be installed in an encasement so that the Locate Tone Wire is external to the conduit with no separation between conduit an d wire. Locate Tone Wire may also be placed in the void between the inner wall of encasement and inner conduits contained within the encasement as long as no other cables are present within the void. Locate Tone Wire may be installed inside conduit only w hen non- armored fiber optic cable is the only other cable within the conduit for ease of utility locating. The Contractor shall perform the Circuit Continuity Test and Insulation Test, as defined within this Specification, on all Locate Tone Wires. The Contractor shall document and provide the test results to the Engineer upon completion of these tests. The Contractor shall replace or repair defective Locate Tone Wire at no additional cost to the Department.
5.Installation of Messenger Wire. The Contractor shall furnish and install messenger wire, aerial lashing, down guy, mounting hardware and fittings, insulators, and all other materials necessary to provide a support for fiber optic and electrical service cables. Messenger wire shall be attached to poles at the locations as shown on the Plans. Installations shall conform with all applicable NEC, NEMA and NESC requirements, along with any special Utility Company pole attachment requirements for the pole being attached. The suspension strand shall b e placed on the roadside of the pole line unless otherwise directed by the Engineer. The installation of messenger wire shall meet all requirements of the National Electrical Safety Code (NESC) regarding clearance from electrical lines and adjacent utility lines.

729.03 Construction Requirements.

The Contractor shall be responsible for locating and drilling all holes required for the attachment of the messenger wire to the poles. The Contractor shall not use any existing holes on utility poles without prior authorization of the Engineer. Re -use of existing cable attachment hardware shall not be permitted. The Contractor shall install messenger wire in continuous segments from pole to pole except where reel splice is required. Where splices are necessary, the Contractor sha ll maintain absolute minimum number of splices for total length of run. Prior approval for these messenger wire splices is required from the Engineer. The Contractor shall tension the unloaded messenger wire in accordance with the recommendations of the messenger wire and fiber optic cable manufacturers, to minimize the possibility of strand fatigue failure. The length of the messenger wire shall be adjusted to ensure the vertical sag is not greater than a two percent of the length between the support pol es once loaded with fiber optic cable. Each messenger wire shall be attached to the supporting structure with separate span wire clamps. The messenger wire shall be grounded at all pole locations where attached in accordance with NESC and the pole owner’s requirements. The Contractor shall not use existing Utility Company grounds. The messenger wire shall be bonded with bonding conductors and clamps to the pole’s ground conductor. For poles without an existing grounding system, the Contractor shall inst all grounding electrodes. The messenger wire shall be bonded at maximum intervals of 1300 feet {396 m}.

6.Installation of Guy Wire. Guy wire (a.k.a. down guy) shall be installed where there is room on the pole to install a Teo bolt attachment in complia nce with the National Electrical Safety Code (NESC). Attach the guy assembly and the guy cable to two separate bolts with one bolt for the span and one bolt for the guy cable. Provide 8 to 12 inch {200 to 300 mm} separation between bolts or as required by the owner. The back guy (down guy) shall be installed, wherever possible, to provide a minimum rise of 2 and run of 1. Anchor holes should be dug to such depths that no more than approximately 6 inches {153 mm} of anchor rods should be above ground after the strain is applied by the guys. Anchors should be in line with the guys. Install guy wire prior to installation of messenger wire and lashed fiber optic or electrical service cable. The Contractor shall determine the guy locations and shall show each location to the Engineer prior to installation of guy. Not more than 6 inches {153 mm} of rod shall remain out of the ground after the load is applied. Down guy shall have a guy marker (a.k.a. guy guard) installed in accordance with applicable NESC, NEMA and local Utility standards. The Contractor shall be wholly responsible for the direct interface with the Utility Company whose pole is to be shared. The Contractor shall submit the drawing representing the aerial cable installation to the said utility f or that Utility Company’s determination and approval of the down guys which may be required on each project. All guys and guying plans shall also adhere to the NESC. Final guying plans shall be submitted for approval to the Engineer prior to the commence ment of installation.
7.Installation of Warning Tape. For Type 1 “Open Trench” Conduit Installations, the Contractor shall place the warning tape within the same ground cut (ditch) as the conduit and locate tone wire as shown on the Plans. Once the conduit and locate tone wire are placed, the cut/ditch shall then be backfilled up to a point no more than 12 inches {305 mm} below grade and at a maximum of 6 inches {152 mm} below grade where the Contractor shall then apply on continuous, unbroken length of the warning tape between the CommBoxes. The cut/ditch s hall be completely filled in and prepared to its original state or as specified by the Engineer. For Type 5 “Directional Bore” Conduit Installations, the warning tape shall not be required unless otherwise indicated on the Plans.
k.Grounding, Lightning P rotection, Insulation , and Circuit Continuity .
1.General. Ground ing electrodes (rods) shall be installed at all service equipment, cabinets, CommBoxes, Pull Boxes, and pole foundations as shown on the Plans or as required by the Engineer and in accordanc e with the NEC and NESC. CommBoxes and Pull Boxes require grounding electodes only when armored fiber optic cables or electrical service conductors are being installed in said box [see

729.03 Construction Requirements.

Item 729.03(q)4, “Installation of CommBox and Pull Box” ]. Hub Building and Generator equipment shall be grounded in accordance with their respective manufacturer requirements and in accordance with the NEC and NESC. The ground resistance value shall meet the values as defined within this Specification. All metal enclosures , metallic conduits, raceways, armored fiber optic cable, and METALLIC junction boxes containing electric wires and equipment shall be bonded together and grounded to earth through the grounding electrode system. The ITS Cabinet grounding system shall be i solated from any other grounding system, including a support pole grounding system. The locate tone wire system shall be isolated from any other grounding system and shall not be extended into a cabinet or building [see Item 729.03(j)4, “Installation of Locate Tone Wire” ]. Ground busbars shall be provided in equipment racks, enclosures, buildings , and structures as necessary. Single grounding electrodes (rods) shall be driven vertically until the top of the electrode (rod) is at least 12 inches {305 mm} b elow the finished grade. Where a grounding conductor passes through a metal conduit, a suitable grounding bushing shall be placed on each end of the conduit and connected to a ground wire. A grounding conductor, either bare or having a green colored insu lation, shall be extended from the service ground to all equipment and shall be used for grounding purposes only. The grounding conductor must be installed in one continuous length. Exposed grounding electrode conductors shall be protected against physica l damage. Unless otherwise indicated on the Plans or in these Specifications, the grounding electrode conductor shall be connected to the grounding electrode by exothermic welding, listed lugs, pressure connectors or clamps. The ground conductor shall be isolated and insulated from any utility grounding equipment.

2.Grounding for Electrical Power Service. For Electrical Power Service and in addition to the above general grounding requirements, the Contractor shall install grounding ele ctrode conductor (ground wire) up the wood pole to a point adjacent to the uppermost span. This grounding electrode conductor shall be secured to the wood pole with hot -dipped galvanized wire staples on 12 inch {300 mm} centers from ground level to 8 feet {2.4 m}. Above 8 feet {2.4 m}, wire staples are to be installed on 24 inch {600 mm} centers. Grounding electrode(s) (ground rod) shall be installed at the base of the pole and exothermically weld the grounding electrode conductor (wire) to the groundin g electrode (rod). The messenger wire shall be bonded to the grounding electrode conductor using a clamp.
3.Lightning Protection. Lightning Protection shall be installed as shown on the Plans at all poles greater than or equal to 75 feet {22.8 m} in he ight and at Overhead Sign Structures.
4.Insulation Testing. The Insulation Testing (a.k.a. Isolation Test) shall be performed for each conductor in the cable to determine insulation resistance. These tests shall be performed using the NEC as a guide. Any connected ITS devices/equipment are to be removed prior to testing to prevent damage. Any reading of less than 250,000 ohms to ground is unacceptable and shall be corrected. The Contractor shall remove the defective cable, install new cable, and the test be repeated. These insulation resistance tests shall be conducted in the presence of the Engineer.
5.Circuit Continuity Test. The Contractor shall perform Circuit Continuity Tests. Each branch circuit shall be temporarily jumpered at its t ermination and the temporarily loop circuit measured for continuity to assure that no open circuits exist, that the branch circuit is according to Plan, that no high resistance connections exist and that each circuit is properly identified. Each circuit s hall be marked with typed labels.
6.Ground Resistance Test. At each grounding electrode (rod) location, a resistance to ground test shall be conducted by the Contractor in the presence of the Engineer. This test shall be conducted using a null balance earth tester with two auxiliary ground rods placed 50 ft and 100 ft {15 m and 30 m}, respectively, from the tested grounding electrode (rod). A reading of 5 ohms (Ω) or less is satisfactory. Any reading greater than 5 ohms (Ω) will require the installatio n of additional grounding electrodes (rods) to be placed in a pattern as shown on the Plans and in accordance with the NEC. After adjustments in the ground ing

729.03 Construction Requirements.

electrode (rod) configuration, the test shall be repeated (and grounding electrode configuration adjusted) until a reading of 5 ohms (Ω) or less is obtained or to the satisfaction of the Engineer. If a ground resistance measurement of 5 ohms or less cannot be achieved with the addition of ground ing electrodes totaling 80 feet in length, the Engineer may accept this 80 feet of grounding electrodes where soil conditions prevent the grounding system from achieving the 5 ohms value so long as the test results meet NEC requirement of no more than 25 ohms. Commbox with conductive optical fiber cables or electrical service conductors shall be grounded in accordance with the NEC. A reading of 25 ohms (Ω) or less is satisfactory. Any reading greater than 25 ohms (Ω) will require the installation of additional grounding electrodes (rods) as detailed above. Th ese cables shall be bonded together and grounded to earth through the grounding electrode in accordance with these specifications and the NEC. Commbox with non -conductive optical fiber cables and locate tone wire installed will not require a grounding sy stem installed. For aerial installations requiring a messenger wiring system, a grounding electrode shall be installed in accordance with these grounding requirements and Item 729.03(j)5, “Installation of Messenger Wire” . For this messenger wire system, a reading of 25 ohms (Ω) or less is satisfactory unless otherwise directed by the pole owner and approved by the Engineer. Any reading greater than the specified ohms (Ω) resistance value will require the installation of additional grounding electrodes (rods) as detailed above. Ground resistance test should not be performed after the earth surrounding the grounding electrodes (rods) has become wet due to weather or other means. Normal soil conditions and moisture content should be observed and noted on the ground resistance test results. Ground enhancement materials (e.g. salts or other chemical treatments) are not to be allowed as an alternative in reaching the designated soil resistivity level. The Engineer may require additional ground resistance testing to be performed after the completion of the Acceptance Test.

l.Intelligent Transportation System (ITS) Cabinet.
1.General. The Contractor shall assemble and install all necessary material and equipment and furnish a working ITS Cab inet as shown on the Plans and as specified within these Specifications. ITS Cabinets shall be installed on poles, Overhead Sign Bridge (OHSB) Structures, mounting pads, or other methods as shown on the Plans and in accordance with these Specifications. Typically, ITS Cabinets are mounted on ITS poles except for DMS installations which are mounted on the OHSB structure supporting the DMS. ITS Cabinets being utilized as Hub Cabinets (i.e. fiber distribution hub application) are to be pad mounted. All ITS Cabinets shall be furnished with mounting plates and other necessary hardware to mount the ITS Cabinet on a pole or foundation. The ITS Cabinet should be mounted as shown on the Plans or as directed by the Engineer. All items that are required to comp lete the ITS Cabinet installation shall be supplied by the Contractor. ITS Cabinet installations shall include: power and communications run to and properly terminated within the cabinet; any required work and hardware to mount and/or anchor the cabinet ; any fans, thermostat, or other electronic devices as shown on the Plans; any required patch cables for equipment housed within; any DIN rails, racks, or panels required for mounting or grounding equipment whether shown on the Plans or not; and any other equipment, materials, or labor needed to provide fully operational equipment within the cabinet housing. ITS Cabinets being utilized as fiber optic hub cabinets shall also house the following: the trunk fiber optic cable storage and major routing points o f the fiber optic network; the primary fiber distribution units; any required network switch gear; electrical power equipment; and various other devices. All hub cabinets shall be furnished with mounting plates and other necessary hardware to mount the IT S Cabinet on a foundation .
2.Wiring, Conductors and Terminal Blocks. The Contractor shall enclose all cabling and wiring entering the cabinet housing in conduit. The Contractor shall securely and neatly dress all cabling and wiring inside the cabinet, including field wiring. The Contractor shall provide sufficient slack, minimum 2 feet {600 mm}, for cabinet equipment maintenance and re -termination of the field wiring. The Contractor shall route fiber drop cables into the cabinet to provide as much physical protection as possible; secure these drop cables through- out the cabinet; and strain -relieve these drop cables within the fiber termination unit.

729.03 Construction Requirements.

The Contractor shall use stranded copper for all conductors, including those in jacketed cables , except for earth ground conductors, which may be solid copper. Neatly arrange all wiring, firmly lace or bundle it, and mechanically secure the wiring without the use of adhesive fasteners. All wiring and cabling shall be routed and secured to avoid sh arp edges and to avoid conflicts with other equipment or cabling. Terminate all wiring on a terminal block, strip, busbar, or device clamp or lug; do not splice any wiring. Use a minimu m 12 AWG for all conductors of 120 Volts AC circuits, unless otherwise shown on the Plans.

3.Surge Protection. Surge -Protective Devices (SPDs) are required as defined in this Specification and shown on the Plans. Surge -Protective Devices (a.k.a. surge suppression) shall be installed to protect all copper wiring and cabling entering the cabinet housing, except for the earth ground conductor. Terminate all wiring between cabinet devices and the transient surge suppressors, except for the video signal coaxial feed, on terminal strips. Use a minimu m 16 AWG grounding of each surge -protective device, or larger if recommended by the surge -protective device manufacturer. Insulated green wire and connected the ground wire directly to the ground busbar. Do not “ daisy chain ” with the grounding wires of other devices including other surge suppressors. Dress and route grounding wires separately from all other cabinet wiring. Install grounding wires with the absolute minimum length possible between the surge - protective device and the ground busbar. Label all surge -protectiv e devices with silk -screened lettering on the mounting panel. Use minimu m 18 AWG insulated black wiring between the surge -protective device sockets and the terminal blocks for the protected circuits , or larger if recommended by the surge- protective device manufacturer .
4.Component Installation. All components/devices of the ITS Cabinet assembly shall be rack mounted with Phillips -head machine screws. Install screws into tapped and threaded holes in the panels. These components/devices include but are no t limited to terminal blocks, busbars, panel and socket mounted surge -protective devices, circuit breakers, accessory and equipment outlets, VDS interface, video encoders, fiber distribution units and field network switches. Fasten all other cabinet compo nents with hex -head or Phillips -head machine screws installed with nuts (with locking washer or insert) or into tapped and threaded holes. These other components include, but are not limited to: door switches, fans, lights, thermostats, thermal blocks, a nd door lock mechanisms. Fasten stud - mounted components to a mounting bracket providing complete access to the studs and mounting nuts. All fastener heads and nuts (when used) shall be fully accessible with a complete ITS Cabinet assembly, and any compon ent/device shall be removable without requiring removal of other components, panels, or mounting rails. Do not use self -tapping or self -threading fasteners.
5.Electrical Power Service. The Contractor shall provide electrical power service in accordance with these Specifications and as shown on the Plans.
6.Grounding. The Contractor shall provide the ITS Cabinet assembly with grounding and shall be connected upon ITS Cabinet installation in accordance with these Specifications and as shown on the Plans. The Contractor shall measure the resistance to ground at each ITS Cabinet location in the presence of the Engineer. Do not splice the ground conductor between the cabinet grounding terminal and the ground rod.
7.Mounting Brackets. Where the ITS Cabi net is pole or structure mounted, the ITS Cabinet shall be installed utilizing mounting brackets and all appurtenances necessary in accordance with the Specifications and as shown on the Plans. ITS Cabinet shall not move or flex on the structure/pole once installed and with all equipment populated. Cabinet wall reinforcement by the cabinet manufacturer may be necessary.
8.Foundation (Mounting Pad). Where the ITS Cabinet is pad mounted, a concrete mounting pad foundation shall be installed in accordance with the Specifications and as shown on the Plans.

729.03 Construction Requirements.

9.Concrete Pad (Service Platform). Where the ITS Cabinet is pole or structure mounted, a poured in place concrete pad shall be installed below the ITS Cabinet where the Plans show it as required. This c oncrete service platform pad shall be installed in accordance with the Specifications and as shown on the Plans.
m.Electrical Power Service and Transformer. The entity (City, County, State, etc.) that will be responsible for the eventua l operation and maintenance of the fiber optic and/or ITS equipment will make application for electrical service upon notification that power service will be required. The Contractor shall inform the Engineer when power service is required at least 30 cal endar days prior to the need of the electrical power service. This same entity will be responsible for the cost of the service connection and the monthly service billings thereafter. The location of the utility service point and power source shown on the Plans is approximate. The Contractor shall determine the exact location, voltage, procedure, and materials required by the Utility Company. The Contractor shall obtain the Engineer’s approval of this exact power/service location prior to installation. When the service equipment is to be installed on a utility -owned pole, the Contractor shall furnish and install riser, conduit, conductors, and other necessary material to complete the installation of the service. The position of the riser and equipment wil l be determined by the Utility Company. When the Contractor is to provide a lateral drop from the power source to the service pole, the Contractor shall arrange with the serving Utility Company to complete the service connections. The Contractor shall ins tall the riser, conduit, conductors, enclosure and accessories, disconnect switch(es), meter base and service pole. No cable used for power supply shall be spliced.
1.Service Pole (Wood Pole). Service Pole (Wood Pole) shall be installed below grade a min imum depth equal to one -sixth the total pole height. Refer to AASHTO “ Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals”, current edition. All final pole locations shall be marked. The Engineer shall appro ve each location prior to the commencement of drilling of each hole. When service pole is installed on a slope of 2:1 or greater, the installation depth shall be increase by 1 times the diameter of the pole (depth is to be measured from the down slope side of the pole.) The backfill shall be native material in 1 foot {300 mm} lifts to match surrounding grade. Tamp each lift to 90 percent compaction. Existing wood poles and required wood poles used to support messenger wire or to serve as the source of power shall be grounded.
2.Guy Wire. Guy Wire (a.k.a. down guy) shall be installed in ac cordance with the requirements of this Section and as shown on the details in the Special and Standard Highway Drawings, unless otherwise shown on the Plans.
3.Transformer (Step -Up/Step -Down). The Contractor shall provide step -up/step -down Transformers i n accordance with these Specifications and as shown on the Plans.
n.Intelligent Transportation System (ITS) Pole.
1.Installation and Handling. The Contractor shall handle and install ITS poles (especially concrete poles) in accordance with the manufacturer’s standard operating procedures, the requirements of Section 718 and Section 891, and the following requirements:
a.Transportation, site handling and erection shall be performed by qualified personnel with acceptable equipment and methods.
b.ITS poles shall be lifted and supported during the manufacturing, stock piling, transporting and erection operations only at the lifting or support points, or both, as shown on the shop or erection drawings.
c.Erection drawings for each ITS pole shall be provided which identify the structure number, structure length, shipping weight, center of gravity and lifting points. Each ITS pole shall be clearly marked with the corresponding information.

729.03 Construction Requirements.

d.Prior to unloading concrete ITS pole, shop drawings shall be reviewed to identify proper pick-up points for unloading, storage and erection procedures. A thru -hole may be provided at the proper single point pick -up location to enable a steel bar to be inserted as a safety stop for sling s during the erection process (this bar is NOT a lifting device but serves only as a safety stop to prevent the sling from sliding).
e.Each ITS pole shall be vertical installed within 1/8 inch per 10 feet {3 mm per 3 m} of height.
f.The Contractor shall be responsible for digging holes for each concrete ITS pole. Concrete ITS poles shall be placed in hole using appropriate equipment and held in vertical position until backfill has been completed in order to maintain pole position.
2.Concrete Foundation . For each ITS Pole that requires a concrete foundation, the Contractor shall submit Concrete Foundation design in accordance with Section 718. The foundation design shall The Contractor shall notify the Engineer, who shall insure that conduit and elbows are securely attached, before concrete is poured. The Contractor shall contact the Utility Companies to determine the location of underground utilities in the area where the foundations are to be located. The Contractor shall be responsible for repairing , to the satisfaction of the Utility Company, any utilities damaged by the Contractor.
3.Auger Base Foundation. Auger Base Foundation (screw -in helix type) shall be for vehicle detection (i.e. radar and magnetometers) installations on metal ITS poles onl y as shown on the Plans and defined within these Specifications. Auger Base Foundation shall be installed by being augered into place per the manufacturer’s installation and standard operating procedures. If the auger base foundation cannot be installed by augering and upon the Engineer’s prior approval, the auger base foundation may be installed by being encased in concrete. If recommended by the auger base manufacturer, a pilot hole may be used to facilitate the installation of an auger base foundation. The diameter and depth of the pilot hole shall not exceed the maximum dimensions as calculated and specified by the manufacturer. Auger Base Foundation shall also conform to the installation requirements of Section 718 and Section 891, except for the con crete encasement allowance option as defined in this Section. The Contractor shall contact the Utility Companies to determine the location of underground utilities in the area where the foundations are to be located. The Contractor shall be responsible fo r repairing, to the satisfaction of the Utility Company, any utilities damaged by the Contractor.
o.Hub Building.
1.General. Hub Building components shall include, at a minimum, the following: hub building, foundation footing, HVAC system, interior electrical distribution system, lighting, fire extinguisher, lightning protection system, interior and exterior grounding, generator with automatic transfer switch, and other items as indicated within these Specifi cations and shown on the Plans. This work shall include site preparation, procurement, transportation, and installation of a Hub Building with conduit connections to the size and number of conduits specified on the Plans. Hub Building shall be placed at t he designated location on and anchored to the concrete slab with slab foundation being a minimum of 1 foot above grade, said slab supplied by the Contractor as per the Specifications and as shown on the Plans. All Hub Building joints are to be sealed as recommended by the building manufacturer. The Contractor shall provide three (3) sets of Hub Building keys to the Engineer no more than 18 hours after Hub Building installation. The required outside surface treatment (e.g. paving, graveling, etc.) and fenci ng around the Hub Building shall be paid under their respective pay items and as shown on the Plans.
2.Electrical Power Service. The Contractor shall provide Electrical Power Service in accordance with these Specifications and as shown on the Plans. Thi s includes a Generator with Automatic Transfer Switch and Uninterruptible Power Supplies (UPSs).
3.Gas Utility Service. The Contractor shall provide Gas Utility Service in accordance with these Specifications and as shown on the Plans.

729.03 Const ruction Requirements.

4.Grounding. The Contractor shall provide grounding in accordance with these Specifications and as shown on the Plans.
5.Security Fence. A security fence shall be installed around the Hub Building as shown on the Plans. The security fence and gate for the Hub Buildin g will be paid for using other pay item(s) as shown on the Plans.
6.Hub Building Foundation . A concrete foundation footing shall be installed in accordance with the Specifications and as shown on the Plans.
p.Gas Utility Service. The location of the ut ility service point and gas source shown on the Plans is approximate. The Contractor shall coordinate with the local gas Utility Company to determine the exact location, procedure, and materials required for each service point. The Contractor shall obtai n the Engineer’s approval of this exact service location prior to installation. Depending upon local codes, a permit may be required and is the responsibility of the Contractor. The Contractor shall provide necessary items not provided by the local gas Ut ility Company to make said service connection to the Hub Building Generator and associated equipment. This typically includes the fuel line which consists of gas piping from the gas meter to the generator along with connection to the generator. The local gas Utility Company typically provides the meter set (gas meter along with a gas line pressure regulator if required) and the service line (piping from main distribution line to meter set). The gas service components are to meet or exceed applicable inst allation requirements of the American Gas Association (AGA), National Fuel Gas Code (NFGC), and the local gas Utility Company. Gas Utility Service shall also conform to the requirements of Section 646 and Section 861 . After Contractor completes the fuel line installation and prior to the Utility Company making connection; this gas utility service installation will be subject to inspection and approval as required by local codes. The entity that will be responsible for the eventual operation and maint enance of the Hub Building (or other infrastructure requiring such utility as shown on the Plans) will make application for gas utility service upon notification that service will be required. The Contractor shall inform the Engineer when gas service is r equired at least 30 calendar days prior to the need of said service. After which, the Contractor may arrange with the serving gas Utility Company to complete the service connection. The Department’s Area Office (or other entity as noted above or indicated on the Plans) will be responsible for the cost of the service connection by the Utility Company and the monthly service billings thereafter.
q.Miscellaneous Infrastructure. The Contractor shall assemble and install all necessary material and equipmen t and furnish working equipment as shown on the Plans and as specified within the Specifications. All items that are required to complete the installation and ensure a fully functional and operational system shall be supplied by the Contractor. Wiring co nnections in poles shall be environmentally sealed using a minimum of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape.
1.Connector Termination Procedures. The procedure to be used for the termination of the SC connectors used and shall meet that process set out in that connector manufacturer’s Standard Operating Procedure for the field installation. Fiber optic connectors shall meet the assertion loss for c onnectors as specified within the Specifications. The Contractor shall perform the final inspection of connector faces with a 200X scope.
2.Installation of Splice Closure (Underground and Aerial). Splice Closures are required for housing and managing out side plant fusion splices, whether installed in underground or aerial applications. When splicing inside a building or cabinet, a splice center shall be provided in rack or wall space utilizing fiber distribution units (FDUs) as indicated on the Plans an d in accordance with Article 729.03(c), “Fiber Distribution Units (FDU), Connectors, and Fan -Out Kit” . Splice Closure shall be installed per manufacturer’s Standard Operating Procedure, whether installed underground or aerially.

729.03 Construction Requirements.

The application and install ation of an aerial splice closure shall be performed in such a manner as to allow complete splice access after closure placement. This access shall be without the removal of the closure or electrical bonds from the messenger wire. The splicing procedure and splice tray storage within the closure shall be performed in such a process as to allow for aerial re -entry and inspection of the closure. The Contractor shall provide aerial splice closure with manufacturer recommended mounting hardware for attachin g to the messenger wire. The Contractor shall not be allowed to mount any splice closures on utility poles. The Contractor shall also provide and submit, for Engineer approval, the splice closure mounting hardware cut -sheets with the Material Submittal pa ckage.

3.Installation of Riser Assembly. The Contractor shall furnish and install Riser Assembly in accordance with the Plans. The Riser Assembly shall consist of a metallic riser, backplates, mounting brackets, supports, any accessories, and required h ardware as defined within the materials section and as shown on the Plans. The Riser Assembly shall be installed in conformance to the details shown on the Plans and meet all applicable NEC, NEMA and NESC requirements, along with any special Utility Compa ny pole attachment requirements for the pole being attached. For electrical service installations, the riser shall utilize a conduit, unless otherwise shown on the Plans. For fiber optic installations, the riser shall utilize a U -Guard with backplate, unless otherwise shown on the Plans. The riser end attached to the wood pole shall be foam filled. The Contractor shall be responsible to calculate the minimum bend radius of the fiber optic cable and shall install the riser and fiber optic cable accordingly .
4.Installation of CommBox and Pull Box. The Contractor shall install CommBoxes in the four steps specified in the Standard/Special Project details. A poured in place concrete collar shall also be installed around the CommBox in accordance with the Sp ecifications when required by the Standard/Special Project Details and as shown on the Plans. This concrete collar shall be formed separately from any ITS concrete pole or structure foundations. The Contractor shall install Pull Boxes as shown on the Plan s. The Contractor shall also install the Cable Rack for storing fiber optic cable maintenance coils and mounting splice closures within the CommBox and Pull Box as specified within this Specification and as shown on the Plans. The Contractor shall submit, for Engineer approval, the Cable Rack shop drawings/cut -sheets of the materials to be installed with the Material Submittal package. No drilled holes shall be allowed in CommBoxes or Pull Boxes unless specified otherwise as shown on the Plans and accepted by the Engineer. A ground ing electrode (rod) shall be installed at CommBox and Pull Box locations where armored fiber sheaths for fiber optic cables and electrical service conductors are required to be grounded in accordance with the NEC and this Speci fication.
5.Installation of Fiber Marker Post. Fiber Marker Post shall be installed according to the placement specified in the Standard/Special Project details. Fiber marker post shall be anchored with manufacturer’s recommended anchoring system. A “proof check ” sample for the fiber marker post dome graphics, of quantity one, shall be produced and provided to the Engineer prior to procurement of the remaining units. The Contractor is required to obtain the Engineer’s approval of the production fiber ma rker post including the dome cover label graphics prior to subsequent procurements by the Contractor. If the Contractor does not obtain approval prior to subsequent procurements, the Contractor assumes the risk of the fiber marker post being rejected even after installation. No payment shall be made to the Contractor if the fiber marker post is rejected. Fiber marker post shall be placed no later than three days following the installation of the conduit that shall contain fiber optic cables. The Contract or shall be responsible for safeguarding the conduit and cables during the installation of the fiber marker posts. Any conduit or cables damaged during marker post installation shall be removed and replaced at the Contractor’s expense.

729.03 Construction Requirements.

6.Installation of Frequency Locate Marker. Frequency Locate Markers shall be installed according to the placement specified in the Standard/Special Project details. Frequency Locate Markers shall be anchored with manufacturer’s recommended anchoring system. Frequency Loca te Markers shall be placed no later than three days following the installation of the CommBox. The Contractor shall be responsible for safeguarding the conduit and cables during the installation of the Frequency Locate Markers. Any conduit or cables dama ged during Frequency Locate Marker installation shall be removed and replaced at the Contractor’s expense.
7.Installation of Surge -Protective Devices.
a.All conducting cables (i.e. communication, data, and power) entering the ITS Cabinet shall be surge protected as indicated on the Plans and in accordance with Sub-Article 893.17(i), “Surge Protection ”.
b.Hub Buildings shall be surge protected as indicated on the Plans and in accordance with

Article 893 — 15, “Hub Building ” and Sub-Article 893.17(i ), “Surge Protection ”.

c.Electrical Power Service shall be surge protected as indicated on the Plans and in accordance with Article 893.13, “Electrical Power Service and Transformer ” and Sub-Article 893.17(i), “Surge Protection ”.
d.Dynamic Message Sign shall have surge protection in accordance with Item 893.07(a)9, “Transient Protection ” and Sub-Article 893.17(i), “Surge Protection ”.
r.Testing.
1.Terminology. Wherever the following terms are used in Section 72 9 and Section 893 the intent and meaning shall be interpreted as follows: • ITS Electronic Equipment – Electronic equipment and/or devices paid for under Article

729.04 and Article 729.05 .

• Interoperability – The capability to operate devices from different m anufacturers or different device types within the same communications system.

2.General. Testing is a critical component of an ITS project. Not only does testing ensure the project was constructed as shown on the Plans and as specified within the Specif ications, but it also validates the intent of the system. The following tests are conducted as part of each ITS project: Bench Testing, Field Testing, and Acceptance Testing. The Contractor shall secure a test site for the Bench Test as shown on the Plan s and as specified within this Specification. The test site must be submitted by the Contractor at the Pre -Construction meeting for approval by the Engineer. The Contractor shall provide the test location and facility, which shall be in the State of Alab ama and within a twenty -five (25) mile radius of the project limits unless otherwise approved by the Engineer. If the Contractor fails to get test location approval prior to commencing any tests, the Contractor may be required to move testing to another s ite at the Contractor’s expense. There will be no direct payment to the Contractor for the cost of a suitable test site and for the setting up of the equipment for these tests. Testing should include all applicable items required to complete testing. The Contractor shall notify the Engineer to schedule an Acceptance Test a minimum of seven (7) calendar days before each proposed test date. After successfully confirming attendance of all necessary personnel, the Engineer shall provide the approved test dat e to the Contractor and all attendees. The Contractor shall perform tests in the presence of the Engineer. When problems arise during testing, the Engineer can require the Contractor to have a qualified technical representative on site during the specifi c testing. The Contractor shall arrange, at no additional expense to the Department, the attendance of the equipment manufacturer’s qualified technical representative. Testing shall be in accordance with ALDOT’s Intelligent Transportation Systems Test Ma nual as developed by the Bureaus of Design and Maintenance; and, be documented with the corresponding ITS device’s testing checklist(s). If any ITS electronic equipment requires re- test, the above minimum test information shall be provided for each re- test per each piece of equipment.

729.03 Construction Requirements.

Once a test is completed, a copy of the Test Result Documentation shall be submitted to the Engineer within seven (7) calendar days following completion of test activities. Any given test session is considered incomplete unt il the Engineer has approved the documentation for that test session. It shall be the Contractor’s responsibility for successful completion of each test. Any equipment which fails any tests shall be subject to re -test at no additional cost to the Department. The Engineer’s approval of test procedures, Test Result Documentation, and witnessing of such tests shall not relieve the Contractor of their responsibility to provide a completely acceptable and operating ITS project.

3.Bench Test. The Contractor shall perform a Bench Test on all ITS electronic equipment and ITS Cabinets prior to installation. The Bench Test shall be performed by the Contractor at the approved test location and witnessed by the Engineer. The Bench Test shall consist of the following two test phases:
a.The Visual Inspection phase shall consist of visually inspecting all Intelligent Transportation System (ITS) electronic equipment, ITS Cabinets and materials to insure there is no physical damage; and that the equipment and ca binets conform to their approved material submittal cut sheets.
b.The Manufacturer’s Startup and Diagnostics test phase shall consist of the Contractor performing the manufacturer’s out -of-the-box startup and diagnostic test for each piece of ITS electron ic equipment, using the respective manufacturer’s recommended startup diagnostics, configuration, and testing. The Contractor shall submit with the Material Submittal the manufacturer’s recommended startup and diagnostic test procedures for review and approval prior to conducting the Bench Test. The Contractor shall supply all temporary wiring and cabling (e.g. CAT -5/6/6A, RS -232/422/485, DVI, VGA, Coaxial, etc.), laptop, diagnostic software, and electrical service necessary for the Bench Test. Test Resul t Documentation for the Bench Test, for each item in full contract quantity, shall be submitted to the Engineer for approval. The Engineer’s approval shall be in writing. The Contractor shall deliver all manufacturers’ configuration and diagnostic softwa re to the Engineer at the completion of the Burn -In.
4.Field Test. The Field Test shall demonstrate that the ITS electronic equipment is properly operating, configured, and transmitting data to ALDOT’s Intelligent Transportation Systems software applicat ions as shown on the Plans and as specified within the Specifications. This test is conducted in the field at each ITS device site. The Contractor shall not begin the Field Test until all ITS electronic equipment has successfully passed the Bench Test an d its Test Result Documentation has been approved by the Engineer in writing. The Contractor shall review the standard ALDOT Acceptance Test “ Functional Operations Test Procedures (FOTP) ” and submit any additional or modified items for review and acceptan ce to the Engineer. Any supplemental items to be added to the standard FOTP shall: • identify the additional functional site and/or remote requirements to be tested; • define the test procedure steps required for additional testing of these functional require ment(s); and, • identify the expected results for successfully passing each additional test procedure. The Contractor shall submit to the Engineer the standard Acceptance Test “ FOTP ” document or the amended FOTP such that a thirty (30) day review process may occur by the Engineer. No Field Test at any given site can begin until the Acceptance Test “ FOTP ” document has been accepted by the Engineer. The Contractor shall supply all temporary wiring and cabling (e.g. CAT -5/6/6A, RS -232/422/485, DVI, VGA, coaxia l, etc.), laptop, and diagnostic software necessary for the Field Test and performing the Functional Operations Test Procedures. The Contractor shall not begin any Field Test until all work at that location is complete. The Contractor shall perform a Fiel d Test for each individual device at the site. The Field Test shall consist of the following:

729.03 Construction Requirements.

a.Visual Inspection. The Visual Inspection shall consist of the Engineer visually inspecting all ITS electronic equipment, ITS Cabinets and materials to ensure that they were not damaged while being transported from the Bench Test location to the project site and being installed.
b.Field Demonstration. The Installation shall consist of the Contractor demonstrating to the satisfaction of the Engineer the follow ing minimum requirements: • ITS electronic equipment, ITS Cabinets and associated materials have been installed as shown on the Plans; • ITS electronic equipment has been properly connected (including the patch cables, fiber drop cable, and cable termination); • Perform Continuity Test on supplied network, coaxial, DVI and VGA cabling; and, • Inspect the installation of grounding and the surg e protection systems (includes performing and successfully completing the Insulation Test, Continuity Test, and Ground Resistance Test as shown on the Plans and as specified within this Specification).
c.Performing Functional Operation Test Procedures (FOTP). The Contractor and the Engineer shall perform the “ FOTP ” tests for each device installed at the site being tested. Results shall be documented on these “ FOTP ” test report forms. The Contractor shall generate Test Result Documentation fo r the Field Test which shall be broken down by project site and include all ITS electronic equipment installed at each site. The complete package of the Test Result Documentation for the Field Test shall be submitted to the Engineer for acceptance. The E ngineer’s acceptance shall be in writing.
5.Acceptance Test. The Acceptance Test shall demonstrate that the ITS electronic equipment installed in the field is properly communicating, operating and configured through ALDOT’s Intelligent Transportation Systems software applications. The Contractor shall not begin the Acceptance Test until all ITS electronic equipment has successfully passed the Field Test and its Test Result Documentation has been approved by the Engineer in writing. The Acceptance Test i s typically conducted at the ALDOT TMC closest to the project location. However, the Engineer may approve a different location to conduct the Acceptance Test at his/her discretion. Should any additional test procedure to the standard ALDOT Acceptance Test FOTP be deemed necessary for the Acceptance Test, the Contractor shall submit the additional test items following the same methodology as performed prior to the Field Test. The Contractor shall perform an Acceptance Test for each individual site. The Contractor shall not begin the Acceptance Test until all work at each site is complete and Field Test results accepted by the Engineer. The Acceptance Test shall consist of performing the FOTP that were conducted as part of the Field Test. The Contractor shall generate Test Result Documentation for the Acceptance Test. The Acceptance Test shall be submitted to the Engineer for acceptance. The Engineer’s acceptance shall be in writing.
s.Burn-In. The Contractor shall perform Burn -In on the ITS electronic equipment, ITS Cabinets and materials to ensure their proper operation, interoperability and service for an extended time frame within actual field conditions and without any failures or maintenance problems. The Contractor shall not begin the Burn- In until the Acceptance Test has been successfully completed for all sites and approved by the Engineer in writing. After confirming all sites have successfully completed the Acceptance Test, the Engineer shall send written notice to the C ontractor and all necessary personnel of the authorized Burn -In start date. The Burn- In Period shall be thirty (30) consecutive calendar days without system failure. During the Burn- In Period, the Contractor shall expeditiously perform any necessary adju stment and replace any malfunctioning parts of the equipment required to place the system in an acceptable operational condition to the satisfaction of the Engineer. No extra compensation will be allowed for any work so required, such being considered inc idental to furnishing and installing a complete operational system.

729.03 Construction Requirements.

During the Burn -In Period, time charges shall be suspended if all other work has been completed and accepted pending the results of the Burn -In. The Contractor shall deliver the As -Built Drawing package and all the ITS device manufacturers’ Embedded Protocol Control software packages to the Engineer at the completion of the Burn -In. The Burn -In Period is intended to be concurrent for all sites within the project. However, the Engineer m ay elect due to a state of emergency to allow multiple concurrent Burn -In periods to occur based on a breakdown of the project at his/her discretion (e.g., DMS sites, Camera sites, individual sites, etc.). An equipment failure during the Burn -In Period is defined as a condition where a component stops functioning. A system failure is defined as a condition under which the system is unable to function as a whole or in significant part to provide the services as designated. While a single component failure may not constitute a system failure, chronic failure of that component or component type may be sufficient to be considered a system failure as determined by the Engineer. What constitutes a chronic failure shall be agreed upon in writing by the Contracto r and the Engineer prior to beginning the Burn - In. ITS electronic equipment which has repeated failures (repeated failures are defined as more than two in a thirty -day period) during the Burn -In Period shall be replaced by the Contractor at no cost to the Department. Field Test must be conducted for the new equipment and the Engineer’s acceptance shall be obtained for said testing. Upon satisfactory completion of t he testing, the Engineer will provide written authorization to commence with a thirty (30) day Burn -In Period for the new equipment. Final acceptance shall mean successful completion of Burn- In to the satisfaction of the Engineer. If any equipment or dev ice fails to complete the thirty (30) day Burn- In Period, the Burn -In Period shall be suspended and time charges resumed. The Burn -In Period will not be restarted except when the following has been met: • Repairs to the malfunctioning equipment/device have been satisfactory completed; and, • The repaired equipment/device is to be re -tested and proven to be properly functioning. Only upon the Engineer’s acceptance of the repaired equipment/device, will the Contractor be allowed to resume the Burn -In Period. General communication outage or failure due to hardware is considered a system failure in any case. Communication failure due to a minor component may not be a system failure. Specifically exempted as system failures are failures caused by accident, natur al disasters, or other external forces. The Engineer will advise the Contractor in writing when it considers that a system failure has occurred or a chronic failure exists. Each system failure during this Burn -In Period shall require restarting the clock plus an additional two (2) calendar days of successful operation prior to being eligible for final acceptance (i.e., if there are two system failures during the initial 30 day period, the period would be increased by 4 days). Successful completion of the Burn- In Period shall occur at the end of thirty (30) complete calendar days of operation without a system failure ascribable to hardware, software, or communications components. The Contractor shall generate Test Result Documentation for the Burn -In which shall include at a minimum: • Documentation for any ITS electronic equipment failures, system failures or communications failures; • Document corrective actions taken by the Contractor for equipment repairs; • Any re -test documentation for the repaired or repl acement equipment; • All manufacturers’ ITS electronic equipment protocol control software; and, • All manufacturers’ configuration and diagnostic software along with licenses transferred to the Department. This Test Result Documentation shall also consist of the minimum applicable information as specified within Acceptance Test of the Specification. Once the Burn -In Period is successfully completed, the Contractor shall submit the complete package of the Test Result Documentation for Burn- In to the Engineer f or acceptance. The Engineer’s acceptance shall be in writing, which acknowledges receipt of the Test Result Documentation along with verification that Burn -In was successfully completed. If equipment or device failures occur, the Engineer may request for the Contractor to submit advance copies of the Burn -In Test Result Documentation so as to gain insight to the equipment problems and any corrective actions taken to date.

729.03 Construction Requirements.

t.Training. The Contractor shall provide installation, operat ions and maintenance training for up to ten (10) people. Training shall be performed by product manufacturer(s) for the ITS electronic equipment installed on the Project; and shall be performed both in the field and in the office (or classroom). Training shall include all applicable items required to complete training. The Contractor shall notify the Engineer to schedule training a minimum of seven (7) calendar days before the proposed training date. After successfully confirming attendance of all necess ary personnel, the Engineer shall provide the accepted training date to the Contractor and all attendees. The Contractor shall be responsible for coordinating accepted training date with the product manufacturer instructor(s), along with any field and in -office preparations for completing this training. The Contractor shall take into consideration any time necessary for product manufacturer’s instructor(s) travel (including lead times for booking flights and/or rental cars, time for actual commutes, and t ime for any field or classroom setup). The Contractor shall include in the cost of training all supplies, equipment, materials, user manuals, handouts, travel, and subsistence necessary to conduct the training. A training notebook shall be provided to ea ch trainee in a labeled 3 -ring binder. The Contractor shall submit the proposed training package to the Engineer for acceptance. The training package shall include detailed course curriculum(s), detailed daily training schedule, draft manuals, handouts, and resumes of all instructors. This training package shall be submitted a minimum of thirty (30) calendar days prior to scheduling training. The Engineer shall review the proposed training materials and reserves the right to request modifications to the training program and materials as appropriate. The Engineer’s acceptance of the training package shall be in writing. Training shall not last for more than eight (8) hours of any given day (i.e., twenty -four (24) hours of training would be conducted ove r at least a three (3) day period). Training shall be a mixture of formal classroom and hands- on training, and at least half of the training shall be hands -on. Training shall be conducted at a facility approved by the Engineer and shall be completed with in sixty (60) days after completion of Burn -In. Upon the request of the Contractor, the Engineer may approve training to be conducted prior to completion of Burn -In. The training shall be for the ITS electronic equipment as shown on the Plans or as speci fied within the Specifications; and, for any modifications or enhancements made by the Contractor to ALDOT’s Intelligent Transportation Systems software applications or overall ITS system. Training material shall serve not only as training course guidance , but also as a quick reference guide for future use by the attendee. A copy of all training material, in reproducible form, shall be delivered to the Engineer after training is complete.
u.Warranty. The Contractor shall warrant and guarantee the satisfactory in -service operation of all ITS equipment and all related apparatus, specified or implied within the Specifications and as shown on the Plans, for a warranty period of one (1) year following the c ompletion of partial acceptance for maintenance. The Contractor’s warranty shall be a written guarantee that the ITS equipment will be fully functional and will remain free of defects in material and workmanship during said warranty period. Upon successfu l completion of a required Burn -In Period, the Contractor may request partial acceptance for maintenance, as addressed by Sub-Article 105.15(b) , of the portion or component of the work covered by the Burn -In. The Engineer will review the request and will issue partial acceptance for maintenance if the installation has been acceptably completed. The warranty period will then start for that portion or component of the work. During the warranty period, the Contractor shall repair with new materials, or repla ce at no charge, any device, product, or other material containing a warranty defect. During the support period, the Contractor shall enter a precise description of any necessary repair work performed into a logbook. All materials returned from warranty repairs shall be made through the distributor or manufacturer at no additional charge. Warranty repairs and replacements shall be completed within two weeks from date of return to the distributor or manufacturer. Before final payment is made, the Contract or shall supply ALDOT’s Construction Bureau a letter setting forth the dates of the guarantees giving a telephone number, an address, and a person to contact for any required warranty service. The Contractor shall transfer any available manufacturer’s war ranties or guarantees to the Department. These warranties and guarantees shall be continuous throughout their duration and state that they are subject to such transfer.

729.05 Basis of Payment.

The Department will not make the final payment for work under this Section until the warranties, guaranties and contact information are furnished to the Engineer.

729.04 Method of Measurement.

The Intelligent Transportation Systems shall be measured for payment by the appropriate items complete, in place, acceptably installed, tested and o perational in accordance with the following: ITEM 729- A: Fiber Optic Cable with number of fibers indicated shall be measured per linear foot. ITEM 729- B: Fiber Distribution Unit , Fan -Out Kit, and Fiber Optic Patch Cable shall be measured by each unit inst alled. ITEM 729- C: Network Device shall be measured by each unit installed. ITEM 729- D: Camera shall be measured by each unit installed. ITEM 729- E: Vehicle Detection Systems shall be measured per each device installed. ITEM 729- F: Dynamic Message Sign sha ll be measured by each unit installed. ITEM 729- G: Environmental Sensor shall be measured by each unit installed. ITEM 729- H: Highway Advisory Radio shall be measured by each unit installed. ITEM 729- I: Conduit , Conductor, Locate Tone Wire, Messenger, and Warning Tape shall be measured per linear foot. ITEM 729- J: ITS Cabinet shall be measured by each unit installed. ITEM 729- K: Electrical Power Service and Transformer shall be measured per each site/unit installed . ITEM 729- L: Pole shall be measured by eac h unit installed. ITEM 729- M: Building shall be measured per lump sum. ITEM 729- N: Miscellaneous Infrastructure shall be measured by each unit installed.

729.05 Basis of Payment.

Unless otherwise indicated below, all payments shall be made in increments of:

1.Up to 70% of the contract unit price upon successful completion of the BENCH TEST and installation of item(s) [Partial payments may be made in accordance with Article 109.07 up to this percentage.];
2.Additional 15% of the contract unit price upon completio n of the FIELD TEST; and,
3.Final 15% of the contract unit price upon completion of the ACCEPTANCE TEST (BURN -IN).
a.Unit Price Coverage. ITEM 729- A. FIBER OPTIC CABLE, measured as noted above, will be paid for at the contract bid price, which shall be f ull compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following: fiber optic cable with the number of fibers indicated; attached to messenger wire and pulled through conduit when required; all require d connections; fiber optic cable tags and labeling; aerial slack brackets; manufacturer and Contractor warranties; and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ( Please Note: Cond uit, Messenger Wire, Fiber Marker Post, and Fusion Splicing are separate pay items.) ITEM 729- B. FIBER DISTRIBUTION UNIT, FAN -OUT KIT, FIBER OPTIC PATCH CABLE, measured as noted above, will be paid for at the contract bid price, which shall be full compen sation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Fiber Distribution Unit : including housing, panels, connectors, connector barrels, zip ties, clamps, cable trays, cable management organization, and labels; all adapters/couplings, for the number of fibers indicated, all required termination splicing; mounting brackets and hardware;
b.Fan-Out Kit : fan -out kit with adapters/couplings, for the number of fibers indicated;
c.Fiber Optic Patch Cable: fiber optic patch cable of functional length required to connect the associated equipment and FDUs; connectors, connector barrels, and associated hardware;
d.manufacturer and Contractor warranties;
e.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work.

729.05 Basis of Payment.

Fan-Out Kit and Fiber Optic Patch Cable will be paid at 100% of the contract bid price upon completion of the installation of these items. ITEM 729- C. NETWORK DEVICE, measured as noted above, wil l be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:

a.Network device with all necessary electrical components, including but not li mited to wiring, cabling, harnesses, and indicators;
b.Wireless Licensing (including wireless path loss analysis and testing, frequency coordination, FCC application process, and associated costs/fees);
c.Network hook -up, fiber optic transceivers field and hea d-end, wireless communication devices (antenna, dishes, remote and head -end), communication modules with data cables (CAT 5E/6/6A patch cables, antenna cables and mounts);
d.Equipment mounts;
e.Power hook -up; power supplies with power cables;
f.Surge protection for communication/data and power; grounding system;
g.Manufacturer’s operational software package(s) and firmware;
h.Initial configuration, Acceptance Testing with Burn -In, complete device docu mentation, manufacturer and Contractor warranties and support;
i.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- D. CAMERA, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Camera assembly complete with all components including, but not limited to: camera, lens, pan/tilt drive, control electronics and environmental enclosure, cables (power, video and control), housing assembly and mounting brackets;
b.camera/video drivers, control and diagnostics software, initial configuration; complete camera documentation/manuals;
c.Netwo rk connection and configuration;
d.Surge protection for communication/data and power;
e.Power supplies with cabling and connection;
f.Grounding system; air terminals and lightning protection system;
g.Testing (including all test report/packages, electronic files a nd deliverables), Training (including all instructors, travel, classroom and field materials, electronic files and deliverables), and Acceptance Testing with Burn -In;
h.Manufacturer and Contractor warranties and support;
i.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- E. VEHICLE DETECTION SYSTEMS, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Vehicle Detection Systems complete with all components including, but not limited to: vehicle detection unit(s) (e.g. sensors, repeaters, access points, antenna), control and interface equipment (e.g. detection system processor, communication interface panel, cabinet interface unit), cables (power, data and control), housing assembly, and mounting brackets (with pole extensions if required);
b.Vehicle Detection device/equipment driv ers, control and diagnostics software, initial and post configuration (e.g. software setup and programming, adjusting detection zones, adjustment for repeaters and access points); license(s); complete Vehicle Detection Systems documentation/manuals;
c.Network connection and configuration;
d.Surge protection for communication/data and power;
e.Power supplies with cabling and connection;
f.Grounding system; air terminals and lightning protection system (if required);

729.05 Basis of Payment.

g.Testing (including all test report/packages, electronic files and deliverables), Training (including all instructors, travel, classroom and field materials, electronic files and deliverables), and Acceptance Testing with Burn -In;
h.Manufacturer and Contractor warranties and support;
i.and for all materi als, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- F. DYNAMIC MESSAGE SIGN, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing , installing, and testing, complete in place, as shown on the Plans, with the following:
a.All electrical, electronic, or electromagnetic components use in any DMS assembly, including but not limited to capacitors, potentiometers, resistors, semiconductor devices, transformers, inductors, circuit breakers, switches, terminal blocks, wiring, cabling, harnesses, indicators, electromechanical shutter units, light emitting diodes and modules, lamps, driver boards, sign control logic boards, opto -isolation cards, photosensors, sign electronics power supply, pin and socket connectors, PCB connectors, wire connectors, PCB assemblies, fans, filters, and warning beacons;
b.All DMS housing components including, but not limited to: the walk -in housing assembly and mount ing hardware, DMS platform and housing door, and maintenance safety eyebolts;
c.DMS controller and remote controller, if any;
d.Network connection and configuration;
e.Power supplies with cabling and connection;
f.Surge protection for communication/data and power;
g.Grounding system; air terminals and lightning protection system;
h.Software/driver interfaces, control and diagnostics software, initial configuration; complete DMS documentation;
i.Testing (including all test report/packages, electronic files and deliverables), Training (including all instructors, travel, classroom and field materials, electronic files and deliverables), and Acceptance Testing with Burn -In;
j.Manufacturer and Contractor warranties and support;
k.and for all materials, labor, equipment, tools, tra nsportation, and incidentals necessary to complete this item of work. ITEM 729- G. ENVIRONMENTAL SENSOR, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, comple te in place, as shown on the Plans, with the following:
a.Environmental Sensor system including, but not limited to: air temperature sensor, relative humidity sensor, visibility sensor, precipitation rate sensor, barometric pressure sensor, wind speed and direction sensor, pavement precipitation depth sensor, and either an in- road or remote road pavement sensor, as shown on the Plans;
b.Environmental Sensor data processing unit and remote controller, if any;
c.All Environmental Sensor housing componen ts including, but not limited to: the housing assembly, and mounting brackets (with pole extensions if required) and hardware;
d.Environmental Sensor device/equipment drivers, control and diagnostics software, initial and post configuration (e.g. software s etup and programming, adjusting sensors); license(s); complete Environmental Sensor(s) documentation/manuals;
e.All wiring, cabling, harnesses and connections; Network connection and configuration;
f.Surge protection for communication/data and power;
g.Power supplies with cabling and connection;
h.Grounding system; air terminals and lightning protection system (if required);
i.Testing (including all test report/packages, electronic files and deliverables), Training (including all instructors, travel, classroom and fi eld materials, electronic files and deliverables), and Acceptance Testing with Burn -In;
j.Manufacturer and Contractor warranties and support;
k.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of w ork.

729.05 Basis of Payment.

ITEM 729- H. HIGHWAY ADVISORY RADIO, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:

a.Highw ay Advisory Radio complete with all components including, but not limited to: radio transmitter, digital recorder/player, GPS synchronizer, HAR enclosure/cabinet, antenna subsystem, and mounting hardware;
b.HAR local and remote controller, if any;
c.Highway A dvisory Radio device drivers/interfaces, HAR system software (including control and diagnostics software), initial configuration; FCC license(s); complete HAR documentation/manuals;
d.All wiring, cabling, harnesses and connections; Network connection and configuration;
e.Surge protection for communication/data and power;
f.Power supplies with cabling and connection;
g.Grounding system; air terminals and lightning protection system (if required);
h.Testing (including all test report/packages, electronic files and deliverables), Training (including all instructors, travel, classroom and field materials, electronic files and deliverables), and Acceptance Testing with Burn -In;
i.Manufacturer and Contractor warranties and support;
j.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- I. CONDUIT , CONDUCTOR, LOCATE TONE WIRE, MESSENGER , and WARNING TAPE , measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Conduit : including pull tape , locate tone wire (when fiber optic cable is to be installed in conduit) , conduit hangers, brackets, coupling, c onduit lubricant, accessories, supports, attachment hardware, hardware, fittings, trenching, placing, joining, attaching to structure, backfilling, seeding and mulching of disturbed areas, disposal of debris;
b.Conductor or Locate Tone Wire : including hardw are, fittings, trenching, placing, joining, attaching to structure, backfilling, seeding and mulching of disturbed areas, disposal of debris;
c.Messenger: messenger wire, lashing, down guy, mounting brackets, supports, accessories, insulators, hardware and fittings, couplings, grounding electrode system;
d.Warning Tape : including print proofs, tape splicing components, trenching, placing, backfilling, seeding and mulching of disturbed areas, disposal of debris;
e.Friction Reduction Multiduct Sleeve: sleeve mat erial and pull tape;
f.Manufacturer and Contractor warranties; and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- I will be paid at 100% of the contract bid price upon installat ion. ITEM 729- J. ITS CABINET, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Cabinet complete w ith documentation, base mount foundation, pole mount attachment hardware, incidental hardware;
b.Fully mounted, either pole, base, or pedestal, as shown on the Plans with all required conduits.
c.Electrical wiring, transformers, breakers, fans, switches, inter ior lighting, terminal blocks, receptacles, panel board, surge protection, cable racks, equipment bays, other devices as indicated, and all associated incidental equipment inside the cabinet;
d.Grounding electrode system;
e.Manufacturer and Contractor warrant ies and support;
f.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work.

729.05 Basis of Payment.

ITEM 729- K. ELECTRICAL POWER SERVICE and TRANSFORMER , measured as noted above, will be paid for at the contract bid price, which sha ll be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:

a.Electrical Power Service: including e nclosure, circuit breaker(s), disconnect switch(es), transient/surge protection, weather head, vertical conduit(s) and riser; meter base installation (as required by the utility);
b.Transformer : including enclosure, disconnect switch(es), transient/surge protection, step- up/step -down transformer(s), vertical conduit(s) and riser;
c.All wirin g fro m utility service to the meter base and connections (Please Note: Lateral/horizontal conductors, after the service disconnect/meter base, are separate pay items.) ;
d.Wood pole(s), guy wire, excavating, backfilling, attachment hardware, grounding system, and attachment to local utility;
e.Manufacturer and Contractor warranties;
f.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- L. POLE, measured as noted above, will be paid for at t he contract bid price, which shall be full compensation for furnishing and installing, complete in place, as shown on the Plans, with the following:
a.Complete Pole assembly with all components including, but not limited to: pole, tenon (if required), found ation (if required, with reinforcing steel, rebar, anchor bolts, conduits, auger and base plate), design calculations, weather head(s), vertical conduit and riser;
b.Guy wire (if required),
c.Drilling, excavation and backfill, attachment hardware;
d.Grounding sy stem; air terminals and lightning protection system (if required);
e.Manufacturer and Contractor warranties;
f.and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- L will be paid at 100% of the contract bid price upon completion of the installation of the pole. ITEM 729- M. BUILDING, measured as noted above, will be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Hub Building complete with all interior lighting, receptacles, switches, panel board, wiring/conductors/conduits, surge protection, grounding system, security system, cable racks, generator (with concrete pad), automatic transfer switch, and other devices as indicated;
b.Installed complete on a foundation with all utilities connected and operational, incidental hardware, and gas source for the generator, at no separate cost to the Department;
c.Manufacturer and Contractor warranties and support;
d.and for all ma terials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. ITEM 729- N. MISCELLANEOUS INFRASTRUCTURE, measured as noted above, will be paid for at the contract bid price, which shall be full compensation fo r furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:
a.Fusion Splicing : fusion splices, fusion heat shrink sleeves and incidentals, testing, and documentation (All splices and terminations shall be accuratel y and fully documented on forms supplied by the Department. No payment for splices or terminations shall be made unless forms have been accurately completed by the Contractor and approved by the Engineer.);
b.Splice Closure : splice closure housing with seals, splice organizer, splice trays, mounting brackets, hardware, and accessories;
c.Riser Assembly : riser, backplate, conduit, couplings, weatherhead, standoffs, mounting brackets, supports, hardware, and accessories;

729.05 Basis of Payment.

d.CommBox : communication box with cov er, cable rack system, attachment hardware, base material, and concrete collar; grounding electrode system (where required) ; excavation, backfilling, seeding and mulching of disturbed areas; disposal of debris;
e.Pull Box : pull box with cover, cable rack sy stem, cable management, attachment hardware, supports, and all necessary accessories; grounding electrode system (where required) ;
f.Fiber Marker Post : post, dome with graphics label and sleeve, and anchor;
g.Frequency Locate Marker : locate marker unit and labeling;
h.Uninterrupted Power Supply : control/monitoring unit, batteries, transient/surge protection, wiring, network card, mounting, and incidental hardware and software;
i.Manufacturer and Contractor warranties; and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete this item of work. Fusion Splicing, Splice Closure, Riser Assembly, CommBox, Pull Box, Fiber Marker Post and Frequency Locate Marker will be paid at 100% of the contract bid price upon completi on of the installation of these items.
b.Payment will be made under Item No.: 729-A Fiber Optic ( 1 ) Cable, ____ - per linear foot 729-B Fiber Distribution Unit, ( 2 ) - per each Fan-Out Kit – per each FO Patch Cable, ( 3 ) - per each 729-C Network Device, ( 4 ) - per each 729-D Camera, ( 5 ) - per each 729-E Vehicle Detection System ( 6 ) - per each 729-F Dynamic Message Sign, ( 7 ) ( 8 ) - per each 729-G Environmental Sensor, ____ - per each 729-H Highway Advisory Radio, ( 9 ) - per each 729-I Conduit, ( 10 ) - per linear foot Conductor, ( 11 ) - per linear foot Locate Tone Wire - per linear foot Messenger - per linear foot Warning Tape - per linear foot 729-J ITS Cabinet, Type ____ - per each 729-K Electrical Power Service ( 12 ) - per ea ch Transformer ( 13 ) – per each 729-L Pole, ( 14 ) - per each 729-M Building, ( 15 ) - per lump sum 729-N Miscellaneous Infrastructure, ____ - per each
1.Specify Cable Type [Trunk, Drop, or Armored]
2.Specify Fiber Distribution Unit Type [Primary or Secondary]
3.Specify FO Patch Cable Type and Length
4.Specify Network Device Type
5.Specify Camera Type [Fixed, Positioner, or Dome]
6.Specify Detection Type [Radar, Magnetometer, or Bluetooth]
7.Specify Dynamic Message Sign Type [Wa lk-In, Front Access, or Dedicated]
8.Specify Dynamic Message Sign Size
9.Specify Highway Advisory Radio Type [Permanent or Portable]
10.Specify Conduit Type [Exposed, Underground, Rigid Metallic, Reinforced Thermosetting Resin, or Friction Reduction Multiduct Sleeves] and Size [1 1/2”, …, 2 x 2 Inch]
11.Specify Conductor Size [8 AWG, 6 AWG, 4 AWG, 2 AWG, 1 AWG, 1/0 AWG, 2/0 AWG, 3/0 AWG, 4/0 AWG, 250 KCMIL, 400 KCMIL, or 500 KCMIL]
12.Specify site location
13.Specify Transformer Type and/or Siz e
14.Specify Pole Type [Concrete, Steel or Fiberglass]
15.Specify Building Type and/or Site location

730.03 Construction.

SECTION 730 TRAFFIC SIGNALS

730.01 Description.

This Section shall cover the work of furnishing and installing of traffic signal control equipment. These requirements may be supplemented or amended by the requirements given elsewhere in the specifications, or on the plans and Special and Standard Highway Drawings. Descriptions and definitions of the equipment, words and termi nology used in the furnishing and installing of traffic signal control equipment are given in the Manual of Uniform Traffic Control Devices (MUTCD) publications of the Institute of Transportation Engineers (ITE), the National Electrical Manufactures Associ ation (NEMA), the National Electrical Code (NEC), and the International Municipal Signal Association (IMSA).

730.02 Materials.

All materials furnished for use shall conform to the requirements given in Section 890, shown on the plans, or listed in the ALDO T “Materials, Sources, and Devices with Special Acceptance Requirements Manual” (MSDSAR). All furnished materials and equipment shall be new and free from defects. Existing equipment shall only be used if shown on the plans to be re -used.

730.03 Constructi on.

a.Design and Construction Codes and Coordination of the Work .
1.Codes . All installations shall comply with the regulations of the latest edition of the National Electrical Code and the latest edition of the National Electrical Safety Code, and with the service rules of the Utility Company providing the electricity.
2.Structure Design and Construction . Structures for the support of traffic signal control equipment shall be designed, furnished, and installed in accordance with the requirements gi ven in Sections 718 and 891.
3.Coordination of the Work . Coordination of the work with roadway and bridge work will be of prime importance to prevent undue damage to completed items of work and existing facilities. Any damage to existing facilities caused by the installation of the material or equipment required under this Section shall be repaired by the Contractor at no additional cost to the Department.
4.Electrical Power . The entity that will be responsible for the eventual operation and maintenance o f the traffic signal unit and intersection lighting will make application for electrical service upon notification that power service will be required. The Contractor shall inform the Engineer when power service is required at least 30 calendar days prior to the need of the power service. This same entity will be responsible for the cost of the service connection and the monthly service billings thereafter. Power shall be single phase, 240 Volt, provided through a transformer that is not tapped to provide power to any other equipment.
b.Traffic Signal Technician . Technician(s) responsible for the performance of the work shall be certified by the IMSA as an IMSA Traffic Signal Level II Field Technician. The Contractor shall submit a copy of the IMSA certification to the Engineer with the first Material Submittal that is submitted for approval. The technician(s) shall be in possession of the certification at all times and show this certification as often as asked by the Engineer. Certified Traffic Signal Technicians shall be present and shall have direct involvement with all work required for the installation and operational testing of electrical materials and equipment (conduit, boxes, conductors, etc.). At least one out of every three persons in a cr ew shall be a certified IMSA Traffic Signal Level II Field Technician.
c.Drawings and Specifications . Omissions from the plans and specifications or errors in the details of work which are evidently necessary to carry out the intent of the plans and spe cifications or which are customarily performed, shall not relieve the Contractor from performing such omissions and details of work. In any case of
Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 625663 of 934.