B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
TRAFFIC CONTROL DEVICES AND HIGHWAY LIGHTING

729INTELLIGENT TRANSPORTATION SYSTEMS

AL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 625–0 Save this section

Ask about Section 729

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

729.01Description

This Section shall cover the work of furnishing, installing and testing Intelligent Transportation Systems (ITS). Descriptions and definitions of the equipment, words and terminology used in the furn ishing and installing of Intelligent Transportation Systems (ITS) equipment are given in the Manual of Uniform Traffic Control Devices (MUTCD) and the publications of the Institute of Transportation Engineers (ITE), the National Electrical Manufactures Ass ociation (NEMA), the National Fire Protection Association (NFPA), and the International Municipal Signal Association (IMSA).

729.02Materials

All materials furnished for use shall conform to the requirements given in Section 893 and the requirements shown on the Plans, and/or listed on the Alabama Department of Transportation (ALDOT) “Materials, Sources, and Devices with Special Acceptance Requirements Manual” (MSDSAR). All

729.03Construction Requirements

furnished materials and equipment shall be new and free from defects. Existing equipment shall only be used if shown on the Plans to be re-used.

Construction Requirements

(a)General.

ITS devices/equipment (i.e., cabinets, cameras, Dynamic Message Signs, Vehicle Detection Systems, etc.) shall NOT be mounted on structural members until erection or final placement of the structure (i.e., Overhead Sign Bridge, ITS Pole, etc.).

1.Drawings and Specifications.

Installations shall comply with the regulations of the latest edition of the National Electrical Code (NEC) (a.k.a. NFPA 70), the latest edition of the National Electrical Safety Code (NESC) (a.k.a. ANSI/IEEE C2), and local Utility regulations.

2.Material and Equipment Lists, Shop Drawing Approval.

Material and equipment listings shall be submitted to the Des ign Bureau’s Traffic Engineering Division for approval within thirty (30) calendar days after the issuance of the “ Notice to Proceed”. Material and equipment lists shall include catalog cutouts or published data sheets and shall be completed on the Department’s Material Submittal Form D- 40. Material Submittal package(s) and Form D-40 shall be electronically completed and submitted in accordance with Traffic Engineering Division’s procedures as outlined in the Form D -40 quick help guide and instruction doc uments. All components required for a complete system, sub-system and/or pay item shall be listed on the Form D-40 as defined in the form’s instruction documents. Partial listings or incomplete shop drawings for any individual pay item, system, or sub -system will not be accepted for consideration and shall be returned for correction without review. Any changes to the approved material and equipment lists must be requested in writing through proper channels. If requested by the Engineer, the Contractor shall submit for inspection and approval samples of both the specified and proposed substitute items at no cost to the Department. The Department will not be liable for any equipment purchased or work done, or any delay incurred before such approval. Failure of the Engineer to note unsatisfactory equipment as received will not relieve the Contractor from responsibility. Manufacturers’ warranties and guaranties furnished on equipment used in the work shall be delivered to the Engineer; likewise, instruction sheets and parts lists shall be delivered to the Engineer upon receipt of the equipment. Throughout the entire project, the same manufacturer shall make all units of any one item.

3.Supporting Structures and ITS Poles.

Supporting Structures and ITS Poles used for mounting the equipment shall conform to the requirements given in Section 718 and Section 891. Concrete ITS Pole with metal tenon extension shall be installed per the manufacturer’s recommendations and as shown on the Plans.

4.As-Built Drawings.

The Contractor shall submit as- built documentation of work provided in accordance with this Specification upon completion of the Burn-In Period as required in Sub-Article 729.03(s), “Burn-In”. As-built submittal packages are to be neat, legible, and orderly. All electronic/digital copies shall be submitted via Department approved media. Except for standard bound materials, bind all letter-size (8.5 inch x 11 inch) documentation, including ledger-size (11 inch x 17 inch) drawings folded to letter- size (8.5 inch x 11 inch), in logical groupings in loose -leaf binders of 3-ring, plastic comb, or plastic coil/spiral type. All binders and media shall have typed labels affixed identifying its contents. The following documents, at a minimum and as they are applicable, shall be included: [Contractor shall furnish at least two (2) sets of bound documentation.]

a.User/Operation Manual.

The Contractor shall furnish a manual containing detailed operating instructions for each different type or model of equipment. The Contractor shall deliver two (2) hard copies and one (1) electronic searchable copy of each User/Operation Manual to the Engineer upon completion of the Project. The User/Operation Manuals shall be for the ITS elect ronic equipment and any software provided on the Project. The

Construction Requirements

User/Operation Manuals should be grouped into the following ITS component areas: camera, VDS, network devices and other equipment.

b.Maintenance Procedures Manuals.

The Contractor shall furnish a manufacturer’s manual containing detailed preventative and corrective maintenance procedures for each different type or model of equipment.

c.System Connection Diagrams.

The Contractor shall furnish diagrams showing the ITS site detailing the wiring between devices.

d.Drawings.

The Contractor shall furnish a corrected set of plans showing in detail all changes made during construction from the original plans. These corrected drawings shall also include: (a) schematic wiring/circuit diagrams; (b) cabinet wiring diagrams; (c) actual route location and depth of conduits, encasements and CommBoxes; and, (d) aerial cable route locations including poles and pole attachment heights (at a minimum). Cable and conduit route locations shall be collected in Department approved GPS format with a horizontal tolerance of ±6 inches {15 cm} and a vertical tolerance of ±12 inches {30 cm}. These readings for cable and conduit are to be taken every 50 feet {15 m} and at changes in direction unless otherwise directed by the Engineer. GPS readings shall also be taken at the top center of installed CommBoxes. Resulting field survey data shall be provided in an ESRI ArcGIS shapefile format and include any necessary descriptive fields. These corrected drawings and field survey shall be furnished as an electronic copy. These corrected drawings should not be finalized for submittal until after all equipment and materials have been installed at their final location and a successful Acceptance Test has been completed. Along with these corrected drawings, all testing documentation and test results as required within the Specification shall be included in the as-built submittal package.

e.ALDOT OSP Database Forms.

The Contractor shall provide the Department with completed Out side Plant (OSP) Database Forms which document fiber optic cable and ITS device installation information. These ALDOT forms should be supplied in PDF file format to the Contractor by the Engineer at the Pre -Construction meeting. These forms are to be pri nted and hand -completed by the appropriate technician (i.e. Fiber Optic Technician for fiber optic cables; and ITS Technician for ITS device/equipment) in the field at each site as corresponding form installation occurs, unless otherwise directed by the Engineer. The Engineer shall field verify submitted forms for accuracy; and then transmit acceptable forms to the Area Traffic Management Center Supervisor for OSP database entry. Copies of these forms should also be sent to Design Bureau’s Traffic Design ITS Group for their records. If any data is missing or any questions regarding form entries are noted at data entry, the forms in question will be returned to the Contractor for corrective action. The Contractor must complete these forms and submit them in a timely manner for review and entry. Otherwise, the Acceptance Test and Burn-In will be subject to being held up.

5.Approved Intelligent Transportation System Devices and Materials.

Some materials and equipment required to be furnished under this Section will be standard production type products. Acceptance will be made by the Engineer based on selected confirmation tests, the manufacturer’s certification of the materials and equipment, and visual inspection at the job site. Approved devices are sh own on the Department’s List VI “Approved Intelligent Transportation System Devices and Materials” . Information concerning this list is given in Sub- Article 106.01(f), “Use of Materials with Special Acceptance Requirements ” and ALDOT-355, “General Information Concerning Materials, Sources, and Devices with Special Acceptance Requirements”.

6.Coordination of Work.

Coordination with roadway work and with bridgework shall be of prime importance to prevent undue damage to completed items of work and to existing facilities. Any damage to existing facilities caused by the installation of the material or equipment required under this Specification shall be repaired by the Contractor at no additional cost to the Department. The Contractor shall field verify equipment locations with the Engineer prior to installation.

Construction Requirements

7.Restoration of Site.

During the installation of the underground systems, removal of brush, trees, fencing, and other obstructions within the right -of-way shall comply with Section 201 and shall be paid for separately under that Section. Landscaping shall be restored to original or better condition if disturbed.

8.Excavating and Backfilling.

Excavation required for the installation and placement of conduits, foundations, CommBoxes, ITS poles and other appliance shall be performed in such manner as to cause the least possible injury to pavement, curbs or other improvements. Trenches shall not be excavated wider than necessary for the proper installation of the required conduits, wires and/or fiber optic cables. Excavating shall not be performed until immediately before installation of conduit and other appliances. The material from the excavation shall be placed in a position where the least interference with the surface drainage will occur. Any trenches required for construction shall be backfilled the same day. Surplus excavated material shall be removed from the site the same day and disposed of by the Contractor, or as directed by the Engineer. Compaction shall be accomplished to the extent necessary to prevent future settlement of the backfill. The Contractor shall be required to restore any areas disturbed by his work to their original condition without additional cost to the Department.

9.License and Certifications.

The Contractor responsible for the performance of the work shall be licensed as a General Contractor authorized to perform electrical work by the Alabama State Licensing Board for General Contractors and in good standing. At least one out of every three persons in each work crew shall be a Journeyman licensed by the Alabama Electrical Contractors Board and in good standing. J ourneymen shall be present and shall have direct involvement with all work required for the installation and operational testing of electrical materials and equipment. The Contractor shall submit copies of the General Contractor license, Journeyman licenses and certifications to the Engineer as a part of the submittal of the list of materials proposed for installation. Work shall not begin on the installation of electrical materials or equipment until copies

of the licenses and certifications have been approved by the Engineer.

Fiber Optic related work shall be completed by qualified Fiber Optic Technicians as defined in

Item 729.03(b)1 “Fiber Optic Technician Qualifications”.

(b)Fiber Optic Cable.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working fiber optic cable as shown on the Plans and as specified within the Specifications. All items

that are required to complete the installation and ensure a fully functional and operational system shall

be supplied by the Contractor.

All optical fibers within each and every cable shall be usable and shall be 100% attenuation-tested

by the manufacturer. The minimum information required within these attenuation testing results are

defined in the materials section of this Specification (see Item 893.02(a)6, “Quality Assurance and

Packing” for details on the “cable reel data sheet”). The cable reel data sheet shall be provided with

each reel and affixed within the reel wrapping. When the cable reel is received from the manufacturer,

a copy of the cable reel data sheet (a.k.a. “manufacturer’s certified test report”) along with any other

shipping documentation shall be submitted to the Engineer. The cable reel tag is to be delivered to

the Engineer upon its removal during cable installation. Once the documentation is no longer needed

for their use, the Engineer should forward these items (or a copy) to the ALDOT Region TSM&O Engineer

for their permanent records and for fiber optic database storage.

The Contractor shall insure fiber optic cable is stored in temperatures that meet the

manufacturer’s recommendations.

1.Fiber Optic Technician Qualifications.

The Fiber Optic Technician qualifications shall be submitted with the Material Submittal package

for approval. The Contractor shall have the Engineer’s approval of the Fiber Optic Technician’s

qualifications prior to commencing work. These technicians shall be in possession of their

certification at all times and show this certification as often as asked by the Engineer. The

Department reserves the right to revoke the approval of any technician not demonstrating the skill

and knowledge to perform at accepted industry standards. Failure to provide proof to the Engineer

will result in a stop work being placed upon fiber optic work until such a time that proof of meeting

Construction Requirements

620

these Fiber Optic Technician Qualification requirements are met. Contract time will not be stopped

if the Contractor is unable to provide adequate proof or qualified staff.

Only technicians that meet all these requirements shall perform fiber work including splicing,

terminating fiber, and testing of fiber.

Technician performing fiber terminations, splicing, and testing shall have:

a.Education:

Attended and successfully completed at least one four (4) day class on installation of fiber optic

products conducted by major manufacturer of fiber products or an accredited/approved firm or

organization. The entity conducting the training, along with the class and materials, shall be current

and accredited for certification by one of the following United States based certification

organizations: Electronics Technicians Association (ETA), The Fiber Optic Association (FOA), or

International Municipal Signal Association (IMSA). Fiber Optic Technicians shall maintain their

certification and be in good standing with the applicable certification organization while performing

such work on ALDOT projects. Technicians with expired or suspended certification shall not be

allowed to conduct work.

b.Work History:

Technicians shall have a minimum of two (2) years of work experience with one year continuous

for splicing, terminating and testing fiber optic cable. Work experience shall be within the last 5

years. The applicant shall submit a resume providing a summary of qualifications and a general

description of professional experience, education and training in the fiber optic installation

techniques (termination, splicing and testing). The applicant shall also provide a work record for

the previous two years detailing specific project, types of installations, testing and a customer

reference for each project. The applicant should include as much additional detail as reasonable

to facilitate approval.

2.Fiber Optics Material Installation.

It shall be the Contractor’s responsibility to protect reeled fiber optic cable from vandals or

other sources of possible damage while unattended. The sections of cable intended for duct

installation are produced to meet specific length requirements. Any damage to the cable sections

may require replacement of the entire section, at the discretion of the Engineer.

The Contractor shall be responsible for damage to the cable during handling and placing, and

responsible for all cost to replace damaged fiber optic cable. The cable manufacturer's specifications

regarding tensile strength, pulling capacity, and bending radius, etc. shall not be violated.

Whenever unreeled cable is placed on the pavement or surface above a manhole, the Contractor

shall provide barricades or other means of preventing vehicular or pedestrian traffic through the area.

The “figure-eight” configuration shall be used when installing fiber optic cables. Fiber optic

cable should not be coiled in a continuous direction except for lengths of 100 feet {30.5 m} or less.

The preferred size for the “figure-eight” is about 25 feet {7.6 m} in length, with each loop 9 feet {2.7

m} to 14 feet {4.3 m} in diameter. Traffic cones spaced 10 feet {3.0 m} apart are useful guides during

“figure-eighting”. When “figure-eighting” long lengths of cable, care should be taken to relieve

pressure on the cable at the crossover of the eight.

On projects where a fiber optic cable is to be mechanically or hand pulled, a “Pull Tape” as

specified in Sub-Article 893.10(d) shall be factory or field installed within conduit for the purpose

of attaching to, and the pulling of said cable. PULL ROPES NOT SPECIFICALLY DESIGNED FOR FIBER

OPTIC AND ELECTRICAL CABLE INSTALLATION SHALL NOT BE USED ON ANY ALDOT PROJECT.

If a mechanical pulling machine is used, it shall be equipped with a monitored or recording

tension meter. At no time shall the cable manufacturer’s recommended maximum pulling tension be

exceeded. The fiber optic cable’s central strength member and aramid yard shall be attached directly

to the pulling eye/pulling grip in accordance with the cable manufacturer’s Standard Operation and

Installation Procedures (SOP). Contractor shall use cable manufacturer approved pulling grips to

ensure that the cable’s optical and mechanical characteristics are not degraded during installation.

a.Installation and Standard Operation Plan.
i.Manufacturer’s Operation and Installation Procedures.

The Contractor shall install in accordance with the cable manufacturer’s Standard Operation

and Installation Procedures (SOP). These procedures shall be provided upon the request of the

Engineer.

Construction Requirements

621

ii. Contractor’s Installation Plan.

The Contractor shall submit to the Engineer for approval a detailed installation plan for all

fiber optic cable installed as part of this project. The Contractor shall have the Engineer’s written

approval prior to commencing any fiber optic cable installation.

This installation plan shall include all proposed end-to-end cable splice points which shall be

in a CommBox that was already designated as a splice point. The Contractor will be required to

limit the amount of splice points within the network and maximize the length of each cable run.

Reel lengths and end-to-end cable splice points shall be submitted by the Contractor and approved

by the Engineer prior to the ordering of the fiber optic cable.

b.Designated Cable Slack (Maintenance Coil).

Throughout the fiber optic cable installation, the Contractor shall be required to pull and store

excess cable slack at designated intervals. The following lengths of slack cable shall be minimums

used unless otherwise shown on the Plans:

CommBox with Splice Closure 75 ft. {23 m} per cable end

CommBox without Splice Closure 150 ft. {46 m} per cable

Pull Box 100 ft. {30 m}

ITS Cabinet/Controller Cabinet 10 ft. {3 m}

Hub Building 100 ft. {30 m}

TMC/Transportation Control Center

(TCC)(OSP Entrance)

100 ft. {30 m}

c.Slack Storage.

The Contractor shall not leave slack cable lying free on the ground, bottom of a CommBox,

bottom of a pull box, or floor of a Hub/TMC/TCC. Only during the actual pulling process will this

be allowed. If channeling rack is not available on existing, the Contractor may leave slack upon

approval of the Engineer.

d.Aerial Lashing.

Aerial cable shall be lashed to a separate stranded steel messenger wire within a Medium

Density Polyethylene (MDPE) jacket. The fiber optic trunk cable shall not be lashed to messenger

wire also used for signal heads or other similar items.

e.Riser Duct.

Riser duct shall be in accordance with RISER ASSEMBLY requirements within this Specification

and as shown on the Plans.

3.Fiber Optic Cable Tag and Labeling.
a.General.

The Contractor shall label all fiber optic cabling with a unique identification in a permanent

and consistent manner that is approved by the Engineer prior to installing fiber cable. The Engineer

shall provide the Contractor with the identifications to be used. Fiber optic cable tag labels shall

meet the material requirements within this Specification and as shown on the Plans. The Contractor

shall provide these unique cable tag identifications on all test results or fiber related documents

provided to the Engineer.

Metal or non-metal fiber optic cable tags are to be primarily used within CommBoxes, ITS

Cabinets, and Hub Buildings. Special non-metal aerial fiber optic cable tag labels are to be used for

aerial installations. Cable tag labels shall be affixed to the cable per the manufacturer’s

recommendations; and shall be affixed in a manner which will not cause damage to the fiber.

Handwritten labels shall not be allowed.

The Contractor shall install cable tags within 1 foot {0.3 m} of each splice and/or termination

point. Each tag label shall identify the cable type, fiber count, and each fiber optic cable origination

and termination points (or next ITS site that the cable is connecting).

b.Aerial Fiber Cable Labeling.

Aerial fiber optic cable tags shall meet the material requirements within this Specification and

as shown on the Plans.

Aerially-mounted fiber optic cable tags shall be placed at 500 ft. {152 m} increments linearly

along the fiber optic cable path and shall be identifiable as ALDOT fiber when viewed from ground

level.

Construction Requirements

622

A “proof check” sample, of quantity one, shall be produced and provided to the Engineer prior

to procurement of the remaining units. The Contractor is required to obtain the Engineer’s approval

of the “proof check” sample prior to subsequent procurements by the Contractor. If the Contractor

does not obtain approval prior to subsequent procurements, the Contractor assumes the risk of the

aerial fiber optic cable tags being rejected even after installation. No payment shall be made to

the Contractor if the aerial fiber optic tag is rejected.

4.Fiber Optic Testing.

The Contractor shall supply all equipment, materials and software necessary to perform the

test as specified within the Specifications. Fiber optic testing shall be performed by certified Fiber

Optic Technicians approved as specified within the Specifications.

Test for attenuation, decibel loss, shall be measured in dB/km. The Contractor required fiber

tests shall be done by a certified Fiber Optic Technician in the presence of the Engineer or his/her

designee.

a.Fiber Optic Test Methods.
i.Power/Light Meter Test.

A typical Power/Light Meter Test consists of the following steps/conditions:

• Connect the light source to the terminated fiber at the location identified by the

Engineer. Connect a power meter to the other end of the fiber at the location

identified by the Engineer. Record the results in accordance with standard industry

practice and submit the test report to the Engineer.

• Use the light frequencies of 1310 nm and 1550 nm for single-mode unless otherwise

directed by the Engineer.

• Perform the test bi-directionally.

A Project Inspector shall witness and approve the results before final acceptance by the

Engineer.

ii. Optical Time Domain Reflectometer (OTDR) Test.

OTDR shall be used for fiber testing as a means of determining the integrity of the fiber

strands. A launch cable of a length exceeding the “dead zone” of the OTDR or a factory “fiber

box” of 246 feet {75 m} minimum with no splices within the box shall be used for testing with the

OTDR. If a patch cable is utilized, the length of patch cable shall be stored on a fiber storage

bobbin with a 5 inch {127 mm} minimum diameter. Termination of the fiber for testing shall be

the factory fiber via “lab splice”, mechanical splice, or fusion splice, bare fiber adapter, or

mechanical termination. Supplemental patch cables and barrel connectors to transition between

connector types shall not be allowed. The traces shall demonstrate dB/km loss not to exceed +3%

of the factory test documentation that came with that reel of fiber or 1% of the cable’s published

production dB loss per km as specified within the Specifications plus the maximum OTDR error

level as noted by the manufacturer of the OTDR (typically +2%). The OTDR should be calibrated

to show anomalies of 0.1 dB minimum. When a “gainer” appears in an OTDR trace, that strand

shall be bi-directionally tested. Each trace shall include the following data:

• The trace itself with a launch transition not to exceed 6 dB;

• Measurement results - cursor, marker, distance between cursor and marker, total

loss between launch point and end of fiber, attenuation calculation in dB/km;

• Cable information - fiber identification (if not the filename), cable identification

(reel number and manufacturer’s identification reel number), OTDR location, end of

fiber location, operator identification, date shot, time shot; and,

• Set up parameters - wavelength, pulse width, refractory index, range, and horizontal

scale.

b.Fiber Optic Test Times (Milestones).

The following fiber optic testing times/milestones should be observed and/or documented to

the satisfaction of the Engineer.

i.Manufacturer’s On-Site Testing.

The cable manufacturer shall provide necessary documents to validate test equipment along

with test results delivered and provide to the Engineer upon cable delivery.

Construction Requirements

623

ii. General Receiving Test.

The Contractor shall provide the ALDOT Region TSM&O Engineer the fiber cable

manufacturer’s OTDR test results and Power/Light Meter readings for each strand of outdoor fiber

(i.e., trunk, drop, aerial, and armored) prior to performing the fiber optic cable receiving test.

Prior to any work, the Contractor shall certify to the Engineer that any and all fiber optic

cable that is to be used on said project has been delivered to the work site and/or the Contractor’s

storage facility and meets the requirements as specified within the Specifications and was

undamaged during shipping. Compliance with this requirement shall be accomplished in the

following manner.

The Contractor is recommended to OTDR test each fiber strand per loose tube on each reel

of cable 14 days prior to installation.

The Contractor and Engineer shall jointly inspect and test all reels of cable for damage prior

to installation. The fiber optic cable shall meet the following factory attenuation criteria:

• Fiber cable attenuation specified herein for 1310 nm and 1550 nm,

• Strand lengths are consistent in the OTDR reports,

• Launch Transition < 0.6 dB, and

• No event shown in the OTDR trace > 0.10 dB.

Upon completion of these test procedures, the Contractor shall issue to the Engineer all test

data as specified and a “Letter of Quality Assurance” from said Contractor stating that the fiber

cable has been delivered to the construction site and/or the Contractor’s storage facility and

meets the requirements as specified within the Specifications.

Upon the Engineer’s acknowledgment of the receipt and acceptance of the Letter of Quality

Assurance, the Contractor may commence installation of said cable at the Contractor’s risk. No

fiber optic cable shall be installed prior to the receiving test and the acceptance of the Engineer.

iii. Existing Fiber Testing.

The Contractor shall test any existing fiber cable to be used on the project before beginning

any fiber work on those fibers. Existing dark fibers, whether to be used on the project or remain

dark, shall be OTDR tested. Testing of any existing fiber strands that are currently lit shall be

coordinated with the Engineer for scheduling when the lit fiber may be taken offline for testing.

A minimum of seven (7) calendar day notice shall be given to the Engineer before testing lit existing

fibers. These fiber test reports shall be submitted to the Engineer for review and acceptance.

iv. Installation and Post Fiber Testing.

As the cable is pulled off the reel, it shall be carefully inspected for jacket defects. If defects

are noticed, the pulling operation shall be stopped immediately. The Contractor shall submit to

the Engineer the proposed corrective action to be taken for review and acceptance.

Armored fiber optic cable shall be properly grounded upon cable installation. This grounding

system shall be tested in accordance with the Specifications.

Post installation testing ensures the integrity of the fiber strands have not been damaged

during the installation process. Once the fiber cable has been installed, the Contractor shall OTDR

test each fiber strand before proceeding to splicing and/or terminations. These OTDR test results

shall be compared to the receiving OTDR test results for determining if any fibers were damaged

by the Contractor’s work during construction. In such case that there is damage done during

construction the Contractor shall be responsible for all equipment, materials and labor to repair

the damage to the satisfaction of the Engineer at no additional cost to the Department. The

Engineer has the final determination of what constitutes damage during construction. At

minimum, no event shall exceed 0.10 dB post installation. The process for repair and/or

replacement of cable shall be submitted to the Engineer for review and acceptance prior to

conducting the work. Repaired and/or replaced cable shall be retested to ensure compliance with

standards. Test reports shall be submitted to the Engineer for review and acceptance.

v.Termination/Splicing Complete Testing.

Upon completion of the installation of fiber cables, drop cables, splices, and termination of

cable ends; dependent on the project requirements as shown on the Plans, each fiber terminated

and spliced shall be OTDR and Power/Light Meter tested.

The Contractor shall review the OTDR and Power/Light Meter results to ensure the fiber

attenuation, splice loss, and connector pairs meet the requirements as specified within the

Specifications. The reviewer (also a certified Fiber Optic Technician) shall be different from the

certified Fiber Optic Technician who performed the installation and tests. The Contractor shall

Construction Requirements

624

clean, polish, re-terminate, and/or re-splice in order to bring the results within specified

tolerances.

vi. Fiber Optic Test Reporting.

Upon completion the Contractor shall issue to the Engineer all traces and loss/length print

outs. These are to be submitted in a suitable binder organized by cable and strand number. A

cover sheet is required for each binder indicating which cable(s) were tested, the OTDR user’s

name, the certified reviewer’s name, the type of test performed, and the date(s) of the test.

Cover sheets for final test results bearing the reviewer’s signature, the date signed, and a

statement indicating that the installation complies with the Specification’s requirements are

required. The Contractor’s employee who has reviewed the traces is required to sign or initial

them. A check mark is required on all traces that satisfy the Specification’s requirements. For

intermediate test results, the Contractor shall flag any discrepancies that may exist with a short

description of the proposed corrective action (e.g. re-splice). Where test results do not satisfy

the requirements as specified within the Specifications, the Contractor shall provide justification

as to why the testing and/or material are notable to prove meeting the requirements as specified

within the Specifications. This binder/package is to be submitted to the Engineer for fiber work

acceptance and distribution. Also with this binder/package, the Contractor shall submit to the

Engineer on a data compact disk or other approved electronic media the raw OTDR fiber trace files

along with the OTDR documentation (manufacturer/model/serial number). The Contractor may

alternately submit this binder/package as an electronic submittal (preferably in PDF format or as

approved by the Engineer).

No payment for splices or terminations shall be made unless fiber optic test reports and

ALDOT’s OSP Database Forms have been accurately completed by the Contractor and submitted to

the Engineer.

(c)Fiber Distribution Units (FDU), Connectors, and Fan-Out Kit.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working Fiber Distribution Unit as shown on the Plans and as specified within the Specifications. All

items that are required to complete the installation and ensure a fully functional and operational

system shall be supplied by the Contractor.

1.Distribution Hardware.

The following distribution equipment specifications cover installations of Fiber Distribution Units

from the headend and hub, primary fiber distribution unit (PFDU) to secondary fiber distribution unit

(SFDU)which are utilized within the individual cabinets and communication closets within buildings

or within hub buildings.

When splicing in the field within a CommBox or aerial installation, a splice closure shall be

provided as indicated on the Plans and in accordance with Article 729.03(q)2, “Installation of Splice

Closure (Underground and Aerial)”.

2.Fan-Out Kit.

Fan-out kits shall be installed per fan-out kit and/or fiber optic cable manufacturer procedures

and standard fiber connector installation training. Fan-out kit shall be compatible with the fiber

optic cable being terminated and shall be color-coded to match the optical fiber scheme or as

specified within this Specification.

3.Fiber Connectors.

Installer of fiber connectors shall have been trained to perform the installation of the type of

connector being installed. Manufacturer guidelines shall be followed. Prior to testing connector,

installer shall visually verify connector end is clean of foreign materials using a fiber scope. Heat

cure epoxy connectors are the preferred method and shall be used unless otherwise indicated on the

Plans.

4.Cable Management.

The Contractor shall ensure that fiber cables are installed in the manner in which they were

designed for the FDU. Cables shall be secured in the locations designed by the FDU manufacturer

using zip ties while ensuring the fiber cable is not overly bound causing attenuation loss in the fiber

cable. The excess end of zip ties shall be cleanly cut flush. Fiber cable shall not be stretched, kinked,

or bound when run within the cable management system.

Construction Requirements

625

5.Splice and Termination Procedure.

The procedure for fusion splicing shall be submitted to the Engineer for approval. This submittal

shall consist of:

a.OSP Database Form(s);
b.manufacturer/model of fusion splicer and date of last calibration;
c.form of splice protection; and
d.means of accessibility for splice protection and traffic control.

The Contractor shall only splice fibers at locations as shown on the Plans unless otherwise

approved by the Engineer.

All splices shall be protected and stored in fiber optic splice units or integrated fiber optic splice

and termination units that are housed in field cabinets, pull boxes, CommBoxes, hubs, and other

buildings.

The Contractor shall document all splice and terminations on forms provided by the Engineer.

No payment for splices or terminations shall be made unless forms have been accurately completed

by the Contractor and accepted by the Engineer.

Fiber optic cables shall terminate in a fiber optic splice closure or fiber distribution unit where

ends are protected. During installation, fiber optic cable ends must be protected per manufacturer

recommended methods and as approved by the Engineer.

6.Pre-terminated Connector Assemblies.

Pre-terminated Connector Assemblies (i.e., Factory Connector Build-Outs, or pigtails) may be

spliced onto a cable as an alternative to installing heat cure epoxy or mechanical connectors. Pre-

terminated Connector Assemblies shall be installed per manufacturer’s standard operating procedures

of the fiber optic cable and fiber distribution unit; and, as approved by the Engineer.

Pre-terminated Connector Assemblies (PTCA) cables shall be labeled where the buffer tube being

spliced is permanently indicated on the PTCA cable jacket. This labeling is to be done prior to

splicing.

7.Fiber Optic Patch Cable.

Fiber optic patch cables (a.k.a. patchcords or jumpers) shall be appropriately sized for the length

of run. Excess patch cable is to be limited to no more than one slack coil of 6 inch diameter. Fiber

optic patch cables and connectors shall be compatible with the fiber optic cable and equipment to

which it will connect.

(d)Network Devices.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working Network Device as shown on the Plans and as specified within the Specifications. All items

that are required to complete the installation and ensure a fully functional and operational system shall

be supplied by the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape. Final network

device locations shall be accepted by the Engineer prior to installation.

1.Managed Ethernet Switch.
a.Installation.

Managed Ethernet Switch (MES) shall be installed as shown on the Plans and mounted using

manufacturer recommended parts. Ensure that the switch is resistant to all Electromagnetic

Interference (EMI). Verify that the switch is mounted securely and is fully accessible by field

technicians. Wiring shall be run within wire raceways and secured using zip ties.

2.Wireless Network Device.
a.Wireless Equipment Selection and Installation.

The Contractor shall be responsible for determining field conditions of licensed and unlicensed

wireless radio site including interference (noise). The Contractor shall perform wireless path loss

analysis to determine appropriate radio equipment and antennas and mounting heights necessary

for each site. This analysis shall be provided to the Engineer for review and acceptance. The

Contractor shall be responsible for selecting equipment which meets the minimum performance

requirements shown within the Specifications with the required annual availability at the most

constrained modulation (i.e., smallest dB range in modulation to obtain for that radio unit).

Construction Requirements

626

Prior to deploying and operating a licensed frequency, the Contractor is responsible for

performing a frequency coordination, filing a public notice, and submitting an application (Form

601) with the FCC to ensure that no one else is already operating on the same frequency or a

frequency that will inject interference on existing systems. If licensed radios encounter

interference, it is typically resolved with the assistance of the regulatory body.

b.Antenna Installation.

Technicians performing installation work shall have a hardware certification by the microwave

manufacturer on the product being installed.

Prior approval from the Engineer shall be obtained for the installation and sealing process when

field drilling is required to mount an antenna on an existing cabinet and/or support structure.

Antenna mounts shall be secured to prevent movement of antennas in high wind conditions.

Once the antennas are aligned, the position shall be marked with torque marking paint that shows

any movement about the azimuth and elevation axis. Pictures of these marks shall be submitted as

part of the as-built plan set submittal. These marks shall be made such that they do not deteriorate

in the weather or sun.

c.Cable Installation.

Cable shall be routed as shown on the Plans. When the Plans do not denote a specified route,

prior approval from the Engineer shall be obtained for the proposed route. Cables mounted internal

to structure supports shall use a hoisting grip to properly secure each cable type at the top of the

support structure. Lightning arrestors shall be installed as shown on the Plans and grounded on the

support structure. Wiring connections in supports shall be environmentally sealed using a minimum

of watertight electrical connectors, mastic electrical splicing tape, and standard electrical tape. A

drip loop shall be provided where cable enters a support structure; the bottom of the loop shall be

lower than the cable entry point. Structure entries shall be through a weatherhead, grommet or

sealed using butyl rubber.

(e)Camera.
1.General.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working Closed-Circuit Television (CCTV) camera as shown on the Plans and as specified within the

Specifications. All items that are required to complete the installation and ensure a fully functional

and operational system shall be supplied and installed by the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape.

The Contractor shall provide a camera installation complete with associated detection

equipment, control equipment, power supplies, and any other camera-related field electronic

equipment and transient voltage surge suppression as shown on the Plans and as specified within the

Specifications. The Contractor shall provide an installation kit with mounting brackets, data cables,

power cables, hardware and any incidentals required by the manufacturer.

The Contractor shall maintain full responsibility for the camera housing mounting to the support

structure and confirm that the camera can be properly mounted on the support structure prior to

installation. The Contractor shall securely mount the camera on the support structure. The camera

shall be constructed and shall be adjusted to obtain optimum function of the camera.

The camera, cabinet, and other components shall be mounted at locations as shown on the Plans.

The Contractor is responsible to ensure that the camera does not interfere with the operation of any

other ITS electronic equipment when installed.

The Contractor shall be responsible for camera configuration and initial settings (i.e., date/time

stamp, compass orientation, time server IP address, alert settings, camera ID label, SNMP settings,

and initial user account login defaults). These camera settings shall be coordinated with the ALDOT

Region TSM&O Engineer prior to placing camera and associated equipment in service.

a.Cabinet Equipment.
i.Controller Cabinet Installation.

The Contractor shall install the camera controller in the designated space of the ITS Cabinet.

The Contractor shall install any associated camera equipment per the manufacturer’s

requirements and as shown on the Plans.

Construction Requirements

627

ii. Wiring and Connections.

Upon completion of wiring and connections, bundle all incoming cables and hold in place with

nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point

only.

Install cables and connectors so that the manufacturer's rated minimum bending radius and

pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during

installation.

b.Cables and Electrical Power Service.

The Contractor shall install the conduit for electrical cable between the service pole and the

ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article

(m) and Article 893.13, “Electrical Power Service and Transformer”

All camera data shielded cables shall be routed separate from any 120 Vac or greater power

wiring or surge suppressor ground wiring. “Power-Over-Ethernet” (POE) communications cables

shall be permitted where installation and cable is in accordance with NEC Chapter 8.

Cable, shield or conductor used for camera control, power supply, or grounding shall not be

spliced.

c.Interface Protocol.

The Contractor shall provide the Engineer with the manufacturer’s open software

interface/protocols for the Camera so that it can be fully integrated into the Department’s current

ALGo ATMS software.

d.Manufacturer’s Software.

The Contractor shall provide the manufacturer’s configuration and diagnostic software along

with all licenses, software installation media and documentation/manuals to the Engineer at the

completion of the Burn-In. Any special camera configurations or firmware updates shall also be

delivered to the Engineer with this package.

(f)Vehicle Detection Systems (VDS).
1.General.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working VDS as shown on the Plans and as specified within the Specifications. All items that are

required to complete the installation and ensure a fully functional and operational system shall be

supplied by the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape.

The Contractor shall provide a VDS installation complete with associated detection equipment,

control equipment, power, and communications equipment as shown on the Plans and as specified

within the Specifications. The Contractor shall provide an installation kit with mounting brackets,

data cables, power cables, hardware and any incidentals required by the manufacturer.

The Contractor shall maintain full responsibility for the VDS housing mounting to the support

structure and confirm that the VDS can be properly mounted on the support structure prior to

installation. The Contractor shall securely mount the VDS on the support structure. The VDS shall be

constructed and shall be adjusted to obtain optimum function of the VDS.

The VDS, cabinet, and other components shall be mounted at locations as shown on the Plans.

The Contractor is responsible to ensure that the VDS does not interfere with the operation of any

other ITS electronic equipment when installed.

The Contractor shall be responsible for VDS configuration and setting up initial pre-sets using

the manufacturer’s software.

a.Cabinet Equipment.
i.VDS Controller Cabinet Installation.

The ITS Cabinet for remote control of the VDS from ground level shall conform to the

requirements in Sub-Article 729.03(l) and Article 893.12, “ITS Cabinet”. The ITS Cabinet shall

be installed at locations as shown on the Plans unless otherwise designated and approved by the

Engineer.

The Contractor shall install the VDS controller in the designated space of the ITS Cabinet.

The Contractor shall install any associated VDS equipment per the manufacturer’s requirements

and as shown on the Plans.

Construction Requirements

628

ii. Wiring and Connections.

Upon completion of wiring and connections, bundle all incoming cables and hold in place with

nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point

only.

Install cables and connectors so that the manufacturer's rated minimum bending radius and

pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during

installation.

b.Cables and Electrical Power Service.

The Contractor shall install the conduit for electrical cable between the service pole and the

ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article

(m) and Article 893.13, “Electrical Power Service and Transformer”

All VDS data cables shall be routed separate from any 120 Vac or greater power wiring or surge

suppressor ground wiring.

Cable, shield or conductor used for VDS control, power supply, or grounding shall not be spliced.

c.Interface Protocol.

The Contractor shall provide the Engineer with the manufacturer’s open software

interface/protocols for the environmental sensor.

d.Manufacturer’s Software.

The Contractor shall provide the manufacturer’s configuration and diagnostic software along

with all licenses to the Engineer at the completion of the Burn-In.

2.Radar Vehicle Detection System (RVDS).

Structure mounted equipment shall be installed per the manufacturer’s recommendations for

elevation and orientation.

After installation, the RVDS shall be tested for accuracy by comparing data collected by the RVDS

to manual count data under the conditions as specified within the Specifications or as approved by

the Engineer to verify the RVDS is operating within the accuracy requirements as specified within the

Specifications.

3.Magnetometer Vehicle Detection System (MVDS).

In ground magnetometer units shall be installed per the manufacturer’s recommendations for

depth, orientation, and sealant. Structure mounted equipment shall be installed per the

manufacturer’s recommendations for elevation and orientation.

After installation, the MVDS shall be tested for accuracy by comparing data collected by the

MVDS to manual count data under the conditions as specified within the Specifications or as approved

by the Engineer to verify the MVDS is operating within the accuracy requirements as specified within

the Specifications.

4.Bluetooth Data Collection System (BDCS).

Structure mounted equipment shall be installed per the manufacturer’s recommendations for

elevation and orientation.

After installation, the BDCS shall be verified as operational by confirmed matches of discoverable

and/or non-discoverable Bluetooth devices between two BDCS locations for travel time purposes.

(g)Dynamic Message Sign (DMS).
1.General.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working DMS as shown on the Plans and as specified within the Specifications. All items that are

required to complete the installation and ensure a fully functional and operational system shall be

supplied by the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape.

The Contractor shall provide a DMS installation complete with associated control equipment, 120

Vac power, and communications equipment as shown on the Plans and as specified within the

Specifications. The Contractor shall provide an installation kit with mounting brackets, data cables,

power cables, hardware and any incidentals required by the manufacturer.

The Contractor shall maintain full responsibility for the sign housing mounting to the support

structure and confirm that the sign can be properly mounted on the sign support structure prior to

installation. The Contractor shall securely mount the sign on the sign support structure. Initially,

the Contractor is to set the housing at a 3 degree tilt forward toward traffic and adjust the housing

Construction Requirements

629

under both day and night conditions to optimize the view of the sign from the roadway by a motorist

and eliminate random reflections as directed by the Engineer. Alternatively, the housing may be

constructed at a 3-degree tilt toward traffic, if approved by the Engineer, but shall be adjusted to

obtain the same optimization of the viewing of the sign from the roadway.

The Contractor shall attach and secure all mechanical hardware for initial attachment prior to

the reopening of lanes to traffic. The Contractor shall complete attachment of hardware prior to the

release of crane cables. The Contractor shall also install and connect the DMS wiring and

communications cables to the ground cabinet and disconnect switch in the controller cabinet only

after attaching and securing the sign to the sign structure.

During the Acceptance Testing, the Engineer will evaluate the initial setting of the sign and direct

the Contractor to adjust the sign tilt if necessary. The Contractor shall use nylon stop washers with

mounting attachments. For all structural aspects, stainless lock washers and nuts are unacceptable;

use stainless steel nuts with nylon inserts for locking.

The Contractor will lift and install the DMS housing and display in place on the overhead structure

only with prior approval of, and in the presence of the Engineer. Do not lift and install the DMS

housing and display until all equipment, materials, and labor are available such that the DMS can be

operated with messages from the local DMS controller within 72 hours of installation on the overhead

structure. The Contractor shall only program message displays on the DMS at the direction of the

Engineer. Make sight alignment adjustments to the DMS housing and display as directed by the

Engineer.

Securely install mounting hardware to the torque recommended by the overhead sign support

manufacturer.

The DMS shall be mounted at locations shown on the Plans. The DMS shall be mounted using the

manufacturer supplied mounting brackets.

The Contractor is responsible to ensure that the DMS does not interfere with the operation of

any other ITS electronic equipment when installed.

The Contractor shall be responsible for DMS configuration and setting up initial pre-sets using the

manufacturer’s software.

a.Photosensor System.

The Contractor shall aim one sensor in the northerly direction (away from nearby lights) and

scale it for a reading of up to 100 lux (horizon type). The other two sensors shall be aimed in

opposite directions and perpendicular to the sign face. These two sensors shall be scaled for a

reading of up to 100,000 lux. The sensors are to be mounted on the top of the housing near the

right side for ease of maintenance. The aiming angle of the sensors shall be adjustable. The

Contractor shall aim the photosensors and calibrate the dimming system consistent with field

conditions found for each sign as a part of the installation process. This work is to be completed

prior to any Acceptance Testing.

b.Cabinet Equipment.
i.Controller Cabinet Installation.

The ITS Cabinet for remote control of the DMS from ground level shall conform to the

requirements in Sub-Article 729.03(l) and Article 893.12, “ITS Cabinet”. The ITS Cabinet shall

be installed at locations as indicated on the Plans unless otherwise designated and approved by

the Engineer. The ITS Cabinet shall be mounted to the support pole(s) at a height of 42 inches

{107 cm} from ground level to the bottom of the cabinet housing and shall be easily accessed by

maintenance personnel.

The Contractor shall install the DMS controller unit in the designated space of the ITS Cabinet.

The Contractor shall install any associated DMS equipment per the manufacturer’s requirements

and as shown on the Plans.

ii. Wiring and Connections.

Make all connections to terminal boards or screw-type equipment terminals with insulated

fork-tongue compression connectors only when using stranded cable. Make all wiring to bulkhead

connectors on equipment housings with MS bayonet-type connectors. Solder connector joints for

use with extra-low voltage systems, with the joint metals preheated to the flow temperature of

the solder or crimped using ratchet-type positive crimp tools and a double crimp (conductor and

jacket) connector.

Remove the outer jacket of data and communications cables to expose approximately 6 in.

{150 mm} of the shielding or drain wire. Twist together and solder the shielding or drain wire for

Construction Requirements

630

all cables serving a similar function with a 10 AWG minimum insulated (green jacketed) ground

lead securely connected to the cabinet ground bus. Make the ground lead routing as short as

possible. Cut the shield off and leave it isolated at the other end.

Upon completion of wiring and connections, bundle all incoming cables and hold in place with

nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point

only.

The controller will be powered from the power distribution assembly provided in the ITS

Cabinet. Bond the shields of all extra-low voltage cables to the ground bus inside the cabinet.

The shield inside the sign enclosure shall be unconnected and insulated. Route low voltage cables

and extra-low voltage cables installed in the cabinet on opposite sides of the cabinet. Group

similar extra- low voltage cables in the controller cabinets, between common locations, together

with cable ties.

Install cables and connectors so that the manufacturer’s rated minimum bending radius and

pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during

installation.

c.Cables and Electrical Power Service.

The Contractor shall install the conduit for electrical cable between the service pole and the

ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article

(m) and Article 893.13, “Electrical Power Service and Transformer”

All DMS data cables shall be routed separate from any 120 Vac or greater power wiring or surge

suppressor ground wiring.

Cable, shield or conductor used for DMS control, power supply, or grounding shall not be

spliced. The shield of low voltage instrumentation cables shall be grounded at one end only.

d.Use and Operations of DMS Prior to Final Acceptance.

The Department will approve or control any and all DMS displays at all times that a display is

in potential public view to ensure compliance with current MUTCD. When potential public view

exists, no message or graphical display of any kind or activation of any DMS display component is

permitted without prior approval of the Engineer. At such time as the Engineer determines that any

given DMS is ready for Department control, the Department will exercise complete and total control

of that DMS display and all central and local communications with that local DMS controller. Prior

to any action, coordinate with the Engineer any remaining work or any testing or maintenance that

may affect that DMS display. Do not interpret such DMS display control as acceptance of the project

in whole or in part. Do not construe such action as a waiver by the Engineer of any provision of this

Specification. Do not consider such use part of the Burn-In Period.

e.Interface Protocol.

The Contractor shall provide the Engineer with the manufacturer’s open software

interface/protocols for the DMS.

f.Manufacturer’s Software.

The Contractor shall provide the manufacturer’s configuration and diagnostic software along

with all licenses to the Engineer at the completion of the Burn-In.

2.DMS Supporting Structure.

Supporting Structure used for mounting the DMS and equipment shall conform to the

requirements given in Sections 715, 717, and 718.

For each DMS, the Contractor shall provide a complete Supporting Structure design which shall

include all structural dimensions for the supporting structure and associated foundations.

a.DMS Housing Structural Design.

Professional Engineer calculations and a complete set of sealed DMS housing drawings shall be

included within the DMS manufacturer’s submittal to the Engineer. [See Item 893.07(a)3,

“Material and Process Standards” and Item 893.07(a)4, “Sign Housing” for special material

submittal requirements regarding: (a) Professional Engineer Certification of DMS Housing Structural

Design and (b) welding inspection certification.]

A lifting mechanism shall be provided for transporting and installing the DMS and shall be a

permanent, integral part of the DMS housing structural frame. Professional Engineer analysis of the

DMS housing design shall include a certification of the DMS lifting mechanism.

Construction Requirements

631

3.Concrete Foundation.

The Contractor shall submit Concrete Foundation design for each DMS Supporting Structure in

accordance with Section 718. The foundation design shall include all dimensions and reinforcing

steel configuration.

The Contractor shall contact the Utility Companies to determine the location of underground

utilities in the area where the foundations are to be located. The Contractor shall be responsible for

repairing, to the satisfaction of the Utility Company, any utilities damaged by the Contractor.

4.DMS Acceptance Test.

The Contractor shall perform Acceptance Test on the DMS and ITS electronic equipment installed

under this Project and have materials specified within this Specification. The Acceptance Test shall

be in accordance with Sub-Article 729.03(r), “Testing”.

The Visibility Inspection of the Field Test shall include the continuous display of a test message

on each sign for a period of twenty 24-hour days. If any sign fails unacceptably (traveling motorist

cannot recognize the test message) to complete the 20 day Burn-In due to component failure, the

component shall be replaced and the 20 day Burn-In Period shall be started again from day one.

Acceptable failures are those that do not inhibit the motoring public from message recognition.

Any component failures that occur within the acceptable failure shall be replaced prior to final

acceptance.

The Field Test of the Acceptance Test procedure shall prove that Central and Field Controller

software comply with the Specifications, and it shall demonstrate that all DMS system equipment is

fully integrated and operational.

The Field Test procedure shall include the successful exercising of all diagnostic features

provided with the DMS. Testing of the DMS Central Software and Computer shall include

demonstrating proper data transfer to and from each remote site.

(h)Environmental Sensor.
1.General.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working environmental sensor as shown on the Plans and as specified within the Specifications. All

items that are required to complete the installation and ensure a fully functional and operational

system shall be supplied by the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape.

The Contractor shall provide an Environmental Sensor installation complete with associated

control equipment, 120 Vac power, and communications equipment as shown on the Plans and as

specified within the Specifications. The Contractor shall provide an installation kit with mounting

brackets, data cables, power cables, hardware and any incidentals required by the manufacturer.

The Contractor shall maintain full responsibility for the sensor housing mounting to the support

structure and confirm that the sensor can be properly mounted on the support structure prior to

installation. The Contractor shall securely mount the sensor on the support structure. The sensor

shall be constructed and shall be adjusted to obtain optimum function of the sensor.

The sensor, cabinet, and other components shall be mounted at locations as shown on the Plans.

The Contractor is responsible to ensure that the sensor does not interfere with the operation of any

other ITS electronic equipment when installed.

The Contractor shall be responsible for environmental sensor configuration and setting up initial

pre-sets using the manufacturer’s software.

a.Cabinet Equipment.
i.Controller Cabinet Installation.

The ITS Cabinet for remote control of the environmental sensor from ground level shall

conform to the requirements in Sub-Article 729.03(l) and Article 893.12, “ITS Cabinet”. The

ITS Cabinet shall be installed at locations as shown on the Plans unless otherwise designated and

approved by the Engineer.

The Contractor shall install the environmental sensor data processing unit in the designated

space of the ITS Cabinet. The Contractor shall install any associated environmental sensor

equipment per the manufacturer’s requirements and as shown on the Plans.

Construction Requirements

632

ii. Wiring and Connections.

Upon completion of wiring and connections, bundle all incoming cables and hold in place with

nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point

only.

Install cables and connectors so that the manufacturer's rated minimum bending radius and

pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during

installation.

b.Cables and Electrical Power Service.

The Contractor shall install the conduit for electrical cable between the service pole and the

ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article

(m) and Article 893.13, “Electrical Power Service and Transformer”

All environmental sensor data cables shall be routed separate from any 120 Vac or greater

power wiring or surge suppressor ground wiring.

Cable, shield or conductor used for environmental sensor control, power supply, or grounding

shall not be spliced.

c.Interface Protocol.

The Contractor shall provide the Engineer with the manufacturer’s open software

interface/protocols for the environmental sensor.

d.Manufacturer’s Software.

The Contractor shall provide the manufacturer’s configuration and diagnostic software along

with all licenses to the Engineer at the completion of the Burn-In.

(i)Highway Advisory Radio (HAR).
1.General.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working HAR as shown on the Plans and as specified within the Specifications. All items that are

required to complete the installation and ensure a fully functional and operational system shall be

supplied by the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape.

The Contractor shall provide a HAR installation complete with associated control equipment,

power, and communications equipment as shown on the Plans and as specified within the

Specifications. The Contractor shall provide an installation kit with mounting brackets, data cables,

power cables, hardware and any incidentals required by the manufacturer.

The Contractor shall maintain full responsibility for the HAR housing and antenna mounting to

the support structure and confirm that the HAR can be properly mounted on the support structure

prior to installation. The Contractor shall securely mount the HAR on the support structure. The HAR

shall be constructed and shall be adjusted to obtain optimum function of the HAR.

The HAR, cabinet, and other components shall be mounted at locations as shown on the Plans.

The Contractor is responsible to ensure that the HAR does not interfere with the operation of any

other ITS electronic equipment when installed.

The Contractor shall be responsible for HAR configuration and setting up initial pre-sets using

the manufacturer’s software.

a.Cabinet Equipment.
i.Controller Cabinet Installation.

The ITS Cabinet for remote control of the HAR from ground level shall conform to the

requirements in Sub-Article 729.03(l) and Article 893.12, “ITS Cabinet”. The ITS Cabinet shall

be installed at locations as shown on the Plans unless otherwise designated and approved by the

Engineer.

The Contractor shall install the HAR controller in the designated space of the ITS Cabinet.

The Contractor shall install any associated HAR equipment per the manufacturer’s requirements

and as shown on the Plans.

ii. Wiring and Connections.

Upon completion of wiring and connections, bundle all incoming cables and hold in place with

nylon cable ties. Connect the front panel and chassis to the cabinet ground bus from a single point

only.

Construction Requirements

633

Install cables and connectors so that the manufacturer’s rated minimum bending radius and

pulling tension are not exceeded. Take proper care to prevent abrasions to the cable jacket during

installation.

b.Cables and Electrical Power Service.

The Contractor shall install the conduit for electrical cable between the service pole and the

ITS Cabinet load center. Electrical Power Service shall conform to the requirements of Sub-Article

(m) and Article 893.13, “Electrical Power Service and Transformer”

All HAR data cables shall be routed separate from any 120 Vac or greater power wiring or surge

suppressor ground wiring.

Cable, shield or conductor used for HAR control, power supply, or grounding shall not be

spliced.

c.HAR Antenna Grounding.

The HAR antenna grounding design and design submittal shall be either conducted by or signed

off by the HAR equipment manufacturer. The Contractor’s HAR submittal package shall include

antenna and grounding details showing design configuration and proposed equipment and materials,

supporting design calculations, recommended installation methods/procedures to be utilized, and

equipment and proposed material specifications/cut-sheets.

d.Interface Protocol.

The Contractor shall provide the Engineer with the manufacturer’s open software

interface/protocols for the environmental sensor so that it can be fully integrated.

e.Manufacturer’s Software.

The Contractor shall provide the manufacturer’s configuration and diagnostic software along

with all licenses to the Engineer at the completion of the Burn-In.

(j)Conduit, Conductor, Locate Tone Wire, Warning Tape, and Messenger.

Work shall be performed in accordance with the highest industry standards, meeting the

requirements of the latest editions of the NEC, NESC, and NEMA.

1.Installation of Buried Duct and Conduit.

Conduit shall be installed by means of open trenching, plowing, or precision directional boring.

Spare conduit shall have Pull Tape installed in the duct. Maximum spacing between supports and

spacing between expansion fittings shall be as shown on the Plans or, if not shown, according to the

manufacturer’s recommendations.

If rocky soil conditions are encountered during precision directional bore installations, SDR-9

HDPE conduit may be required as approved by the Engineer.

Coiled non-metallic conduit shall be treated by a line tamer prior to underground (or below

grade) installation.

If more than one run of underground conduit is required, install in one trench unless in conflict

with NEC requirements.

Extend conduit ends 2 inches {51 mm} above concrete surfaces and 4 inches {100 mm} above

crushed stones bases; and install with bushings. For metallic conduit, install metallic bushings. For

non-metallic conduit, install non-metallic bushings. Where conduit connects to a panel, box, or other

enclosure, use a locknut in addition to the bushing.

Where non-metallic conduits join metal conduits, connection shall be made using appropriate

couplings to form a watertight raceway.

All conduits entering concrete foundations shall be provided with appropriate bushings at the

ends. Conduits shall be stubbed approximately 2 inches {51 mm} above concrete and shall be provided

grounding type bushings on conduit ends in the base of poles with copper bonding jumpers.

Bends and offsets shall be avoided where possible, but where necessary, shall be made with a

proper pipe bender or conduit bending machine. Conduit that has been crushed or deformed due to

improper bending or handling shall not be installed.

Surface damage to RMC conduit shall be repaired in accordance with the Specifications. Exposed

threads shall be regalvanized.

After installation, conduits shall be tested for clearance with a 2-inch long mandrel (a.k.a., pig)

having a diameter 1/4 inch smaller than the inside diameter of the conduit. Conduits not allowing

passage of the mandrel shall be rejected.

After placement of conduit, all conduits shall be capped to prevent moisture or foreign matter

from entering until the fiber optic cable or conductor installation is started. Upon installation of fiber

Construction Requirements

634

optic cable and/or conductor, conduit ends shall be sealed with duct sealer. Duct sealer shall be a

water-blocking, closed-cell, easily removable/re-enterable, polyurethane foam material as

recommended by the cable manufacturer and approved by the Engineer. Duct sealer shall be

identified for use with the fiber optic cable and conductor insulation; and should not cause

deterioration of the insulation over time. For underground conduit adjacent to gasoline service

stations or other installations of underground gasoline or diesel storage, piping or pumps, and which

lead to a cabinet, circuit breaker panel, service or any enclosure where an arc may occur during

normal operation, the Contractor shall refer to the NEC for Class 1, Hazardous Locations.

2.Installation of Hanging Duct and Conduit.

Maximum spacing between supports and spacing between expansion fittings shall be as shown on

the Plans or, if not shown, according to the manufacturer’s recommendations.

The conduit system shall include mechanisms such as expansion fittings or joints to ensure that

the expansion and contraction stresses are normalized. Spacing or expansion fitting shall be based

upon manufacturer standards for the location conditions/environment of the installation.

After placement of conduit, all conduits shall be capped to prevent moisture or foreign matter

from entering until the fiber optic cable or conductor installation is started. Upon installation of fiber

optic cable and/or conductor, conduit ends shall be sealed as permitted by the current NEC. If duct

sealer is allowed and used, then the duct sealer shall be a water-blocking, closed-cell, easily

removable/re-enterable, polyurethane foam material as recommended by the cable manufacturer

and approved by the Engineer. Duct sealer shall be identified for use with the fiber optic cable and

conductor insulation; and should not cause deterioration of the insulation over time.

The Contractor shall be fully responsible in the event defective conduit is installed and shall be

held fully responsible for replacement (material and labor) of any conduit found to be defective due

to manufacture error, improper construction, or improper installation for one year after the State’s

acceptance of the project.

a.Installation of RTRC.

The conduit shall be packaged for shipment at the factory. The conduit shall be assembled

into manageable bundles. Each section of conduit shall be shipped with protective caps over each

end of the section. Conduit that arrives at the job site without the protective cover in place over

both ends will be rejected by the Engineer.

Conduit connections for RTRC shall be sealed with epoxy adhesive. Joints for RTRC shall be

joined until the conduit ends are together. Once connected the joint pullout rating shall be equal

to the tensile strength of the conduit. No reducing couplings shall be permitted in a conduit run.

b.Installation of RMC.

The conduit shall be packaged for shipment at the factory. The conduit shall be assembled

into manageable bundles. Each section of conduit shall be shipped with protective caps over each

end of the section. Conduit that arrives at the job site without the protective cover in place over

both ends will be rejected by the Engineer.

3.Installation of Conductor.

On projects where a conductor(s) and/or electrical cables are to be mechanically or hand pulled,

a “Pull Tape” as specified in Sub-Article 893.10(d) shall be factory or field installed within conduit

for the purpose of attaching to, and the pulling of said conductor/cable. PULL ROPES NOT

SPECIFICALLY DESIGNED FOR FIBER OPTIC AND ELECTRICAL CABLE INSTALLATION SHALL NOT BE USED

ON ANY ALDOT PROJECT.

Conductors shall have the appropriate identification on the outer jacket. Conductors not

meeting this requirement or with illegible identification are not allowed.

Wiring within pull boxes and CommBoxes shall be neatly arranged and labeled/tagged. All ends

of hardwire shall be taped to exclude moisture and shall be so kept until splices are made and terminal

appliances attached.

The ends of spare conductors shall be protected as permitted by the current NEC (capped method

is preferred). End of fiber optic cables shall be protected from moisture by methods as shown on the

Plans or as approved by the Engineer.

Splices and taps in electrical conductors shall only be made in pull boxes, CommBoxes and pole

bases. They shall be made with solderless split bolt connectors. Splices and taps shall be protected

and sealed in silicone gel filled enclosures to provide a waterproof connection and to ensure the

required electrical insulation. Silicone gel filled enclosures shall be re-enterable; shall be ultra-violet

Construction Requirements

635

(UV)resistant, listed for temperatures from -40°F to 194°F {-40°C to 90°C}; and shall be impact and

abrasion resistant. The enclosure shall be sized as shown in the following table:

CONDUCTOR SIZE GEL ENCLOSURE SIZE

4 AWG and smaller #2

2 AWG #2.5

Larger than 2 AWG #3

Installation of conductors shall be in accordance with the NEC. Conductors shall not be pulled

into a conduit until the installation of the conduit is complete. Prior to the installation of conductors,

the Contractor shall ensure the conduit is free of water and debris by blowing air and pulling a foam

ball, mandrel, or brush through the conduit. The ends of conduit shall be cleaned of bures and capped

with a bushing to protect cables during installation.

Conductors in conduits shall be carefully pulled into place using approved methods so that the

conductors will not be damaged. Powdered soapstone, talc, or other inert lubricant specifically

designed for the purpose shall be used when pulling conductors through the conduit. All conductors

within a single conduit shall be pulled at the same time; and, shall be handled and installed in such

a manner as to prevent kinks, bends or other distortion which could damage the conductor and outer

covering. When conductors are pulled through hand holes, pole shafts, etc., a pad of firm rubber or

other suitable materials shall be placed between the conductors and the edges of the opening to

prevent damage to the conductors.

The pulling tension on conductors shall not be exceeded. Friction reduction multiduct pulling

sleeves may be used as an alternate to lubricant. The Contractor shall not exceed the NEC conduit

fill capacity requirements. Fiber optic cables shall not be installed in conduits containing current

carrying conductors.

4.Installation of Locate Tone Wire.

Locate Tone Wire shall be installed along the entire underground conduit run for non-conductive

fiber optic cables in accordance with this Specification and as shown on the Plans. Ensure that the

Locate Tone Wire enters all CommBoxes and Pull Boxes as the fiber optic cable; and, that a minimum

of 10 feet {3 meters} of slack is coiled and neatly stored in each box. Locate Tone Wire shall be suited

for direct burial and shall be continuous.

Locate Tone Wire system does not require to be grounded since it is a non-current carrying

conductor used for locating fiber optic cable only. Locate Tone Wire shall not be installed inside ITS

Cabinets.

Where fiber optic conduit is installed via trenching operation, the Locate Tone Wire is to be

installed no more than 3 inches {7.62 cm} above the conduit. Where fiber optic conduit is installed

via boring operation, the Locate Tone Wire is to be installed in an encasement so that the Locate

Tone Wire is external to the conduit with no separation between conduit and wire. Locate Tone Wire

may also be placed in the void between the inner wall of encasement and inner conduits contained

within the encasement as long as no other cables are present within the void.

Locate Tone Wire may be installed inside conduit only when non-armored fiber optic cable is the

only other cable within the conduit for ease of utility locating.

The Contractor shall perform the Circuit Continuity Test and Insulation Test, as defined within

this Specification, on all Locate Tone Wires. The Contractor shall document and provide the test

results to the Engineer upon completion of these tests. The Contractor shall replace or repair

defective Locate Tone Wire at no additional cost to the Department.

5.Installation of Messenger Wire.

The Contractor shall furnish and install messenger wire, aerial lashing, down guy, mounting

hardware and fittings, insulators, and all other materials necessary to provide a support for fiber optic

and electrical service cables. Messenger wire shall be attached to poles at the locations as shown on

the Plans. Installations shall conform with all applicable NEC, NEMA and NESC requirements, along

with any special Utility Company pole attachment requirements for the pole being attached. The

suspension strand shall be placed on the roadside of the pole line unless otherwise directed by the

Engineer.

The installation of messenger wire shall meet all requirements of the National Electrical Safety

Code (NESC) regarding clearance from electrical lines and adjacent utility lines.

Construction Requirements

636

The Contractor shall be responsible for locating and drilling all holes required for the attachment

of the messenger wire to the poles. The Contractor shall not use any existing holes on utility poles

without prior authorization of the Engineer. Re-use of existing cable attachment hardware shall not

be permitted.

The Contractor shall install messenger wire in continuous segments from pole to pole except

where reel splice is required. Where splices are necessary, the Contractor shall maintain absolute

minimum number of splices for total length of run. Prior approval for these messenger wire splices

is required from the Engineer. The Contractor shall tension the unloaded messenger wire in

accordance with the recommendations of the messenger wire and fiber optic cable manufacturers,

to minimize the possibility of strand fatigue failure.

The length of the messenger wire shall be adjusted to ensure the vertical sag is not greater than

a two percent of the length between the support poles once loaded with fiber optic cable. Each

messenger wire shall be attached to the supporting structure with separate span wire clamps.

The messenger wire shall be grounded at all pole locations where attached in accordance with

NESC and the pole owner’s requirements. The Contractor shall not use existing Utility Company

grounds. The messenger wire shall be bonded with bonding conductors and clamps to the pole’s

ground conductor. For poles without an existing grounding system, the Contractor shall install

grounding electrodes. The messenger wire shall be bonded at maximum intervals of 1300 feet

{396 m}.

6.Installation of Guy Wire.

Guy wire (a.k.a. down guy) shall be installed where there is room on the pole to install a Teo

bolt attachment in compliance with the National Electrical Safety Code (NESC). Attach the guy

assembly and the guy cable to two separate bolts with one bolt for the span and one bolt for the guy

cable. Provide 8 to 12 inch {200 to 300 mm} separation between bolts or as required by the owner.

The back guy (down guy) shall be installed, wherever possible, to provide a minimum rise of 2

and run of 1.

Anchor holes should be dug to such depths that no more than approximately 6 inches {153 mm}

of anchor rods should be above ground after the strain is applied by the guys. Anchors should be in

line with the guys.

Install guy wire prior to installation of messenger wire and lashed fiber optic or electrical service

cable. The Contractor shall determine the guy locations and shall show each location to the Engineer

prior to installation of guy. Not more than 6 inches {153 mm} of rod shall remain out of the ground

after the load is applied.

Down guy shall have a guy marker (a.k.a. guy guard) installed in accordance with applicable

NESC, NEMA and local Utility standards.

The Contractor shall be wholly responsible for the direct interface with the Utility Company

whose pole is to be shared. The Contractor shall submit the drawing representing the aerial cable

installation to the said utility for that Utility Company’s determination and approval of the down guys

which may be required on each project. All guys and guying plans shall also adhere to the NESC.

Final guying plans shall be submitted for approval to the Engineer prior to the commencement of

installation.

7.Installation of Warning Tape.

For Type 1 “Open Trench” Conduit Installations, the Contractor shall place the warning tape

within the same ground cut (ditch) as the conduit and locate tone wire as shown on the Plans. Once

the conduit and locate tone wire are placed, the cut/ditch shall then be backfilled up to a point no

more than 12 inches {305 mm} below grade and at a maximum of 6 inches {152 mm} below grade

where the Contractor shall then apply on continuous, unbroken length of the warning tape between

the CommBoxes. The cut/ditch shall be completely filled in and prepared to its original state or as

specified by the Engineer.

For Type 5 “Directional Bore” Conduit Installations, the warning tape shall not be required unless

otherwise indicated on the Plans.

(k)Grounding, Lightning Protection, Insulation, and Circuit Continuity.
1.General.

Grounding electrodes (rods) shall be installed at all service equipment, cabinets, CommBoxes,

Pull Boxes, and pole foundations as shown on the Plans or as required by the Engineer and in

accordance with the NEC and NESC. CommBoxes and Pull Boxes require grounding electodes only

when armored fiber optic cables or electrical service conductors are being installed in said box [see

Construction Requirements

637

Item 729.03(q)4, “Installation of CommBox and Pull Box”]. Hub Building and Generator equipment

shall be grounded in accordance with their respective manufacturer requirements and in accordance

with the NEC and NESC. The ground resistance value shall meet the values as defined within this

Specification.

All metal enclosures, metallic conduits, raceways, armored fiber optic cable, and METALLIC

junction boxes containing electric wires and equipment shall be bonded together and grounded to

earth through the grounding electrode system.

The ITS Cabinet grounding system shall be isolated from any other grounding system, including a

support pole grounding system.

The locate tone wire system shall be isolated from any other grounding system and shall not be

extended into a cabinet or building [see Item 729.03(j)4, “Installation of Locate Tone Wire”].

Ground busbars shall be provided in equipment racks, enclosures, buildings, and structures as

necessary.

Single grounding electrodes (rods) shall be driven vertically until the top of the electrode (rod)

is at least 12 inches {305 mm} below the finished grade.

Where a grounding conductor passes through a metal conduit, a suitable grounding bushing shall

be placed on each end of the conduit and connected to a ground wire.

A grounding conductor, either bare or having a green colored insulation, shall be extended from

the service ground to all equipment and shall be used for grounding purposes only. The grounding

conductor must be installed in one continuous length.

Exposed grounding electrode conductors shall be protected against physical damage. Unless

otherwise indicated on the Plans or in these Specifications, the grounding electrode conductor shall

be connected to the grounding electrode by exothermic welding, listed lugs, pressure connectors or

clamps.

The ground conductor shall be isolated and insulated from any utility grounding equipment.

2.Grounding for Electrical Power Service.

For Electrical Power Service and in addition to the above general grounding requirements, the

Contractor shall install grounding electrode conductor (ground wire) up the wood pole to a point

adjacent to the uppermost span. This grounding electrode conductor shall be secured to the wood

pole with hot-dipped galvanized wire staples on 12 inch {300 mm} centers from ground level to 8 feet

{2.4 m}. Above 8 feet {2.4 m}, wire staples are to be installed on 24 inch {600 mm} centers.

Grounding electrode(s) (ground rod) shall be installed at the base of the pole and exothermically

weld the grounding electrode conductor (wire) to the grounding electrode (rod).

The messenger wire shall be bonded to the grounding electrode conductor using a clamp.

3.Lightning Protection.

Lightning Protection shall be installed as shown on the Plans at all poles greater than or equal to

75 feet {22.8 m} in height and at Overhead Sign Structures.

4.Insulation Testing.

The Insulation Testing (a.k.a. Isolation Test) shall be performed for each conductor in the cable

to determine insulation resistance. These tests shall be performed using the NEC as a guide. Any

connected ITS devices/equipment are to be removed prior to testing to prevent damage. Any reading

of less than 250,000 ohms to ground is unacceptable and shall be corrected. The Contractor shall

remove the defective cable, install new cable, and the test be repeated. These insulation resistance

tests shall be conducted in the presence of the Engineer.

5.Circuit Continuity Test.

The Contractor shall perform Circuit Continuity Tests. Each branch circuit shall be temporarily

jumpered at its termination and the temporarily loop circuit measured for continuity to assure that

no open circuits exist, that the branch circuit is according to Plan, that no high resistance connections

exist and that each circuit is properly identified. Each circuit shall be marked with typed labels.

6.Ground Resistance Test.

At each grounding electrode (rod) location, a resistance to ground test shall be conducted by the

Contractor in the presence of the Engineer. This test shall be conducted using a null balance earth

tester with two auxiliary ground rods placed 50 ft and 100 ft {15 m and 30 m}, respectively, from the

tested grounding electrode (rod). A reading of 5 ohms (Ω) or less is satisfactory. Any reading greater

than 5 ohms (Ω) will require the installation of additional grounding electrodes (rods) to be placed in

a pattern as shown on the Plans and in accordance with the NEC. After adjustments in the grounding

Construction Requirements

638

electrode (rod) configuration, the test shall be repeated (and grounding electrode configuration

adjusted) until a reading of 5 ohms (Ω) or less is obtained or to the satisfaction of the Engineer.

If a ground resistance measurement of 5 ohms or less cannot be achieved with the addition of

grounding electrodes totaling 80 feet in length, the Engineer may accept this 80 feet of grounding

electrodes where soil conditions prevent the grounding system from achieving the 5 ohms value so

long as the test results meet NEC requirement of no more than 25 ohms.

Commbox with conductive optical fiber cables or electrical service conductors shall be grounded

in accordance with the NEC. A reading of 25 ohms (Ω) or less is satisfactory. Any reading greater

than 25 ohms (Ω) will require the installation of additional grounding electrodes (rods) as detailed

above. These cables shall be bonded together and grounded to earth through the grounding electrode

in accordance with these specifications and the NEC.

Commbox with non-conductive optical fiber cables and locate tone wire installed will not require

a grounding system installed.

For aerial installations requiring a messenger wiring system, a grounding electrode shall be

installed in accordance with these grounding requirements and Item 729.03(j)5, “Installation of

Messenger Wire”. For this messenger wire system, a reading of 25 ohms (Ω) or less is satisfactory

unless otherwise directed by the pole owner and approved by the Engineer. Any reading greater than

the specified ohms (Ω) resistance value will require the installation of additional grounding electrodes

(rods)as detailed above.

Ground resistance test should not be performed after the earth surrounding the grounding

electrodes (rods) has become wet due to weather or other means. Normal soil conditions and moisture

content should be observed and noted on the ground resistance test results.

Ground enhancement materials (e.g. salts or other chemical treatments) are not to be allowed

as an alternative in reaching the designated soil resistivity level.

The Engineer may require additional ground resistance testing to be performed after the

completion of the Acceptance Test.

(l)Intelligent Transportation System (ITS) Cabinet.
1.General.

The Contractor shall assemble and install all necessary material and equipment and furnish a

working ITS Cabinet as shown on the Plans and as specified within these Specifications.

ITS Cabinets shall be installed on poles, Overhead Sign Bridge (OHSB) Structures, mounting pads,

or other methods as shown on the Plans and in accordance with these Specifications. Typically, ITS

Cabinets are mounted on ITS poles except for DMS installations which are mounted on the OHSB

structure supporting the DMS. ITS Cabinets being utilized as Hub Cabinets (i.e. fiber distribution hub

application) are to be pad mounted.

All ITS Cabinets shall be furnished with mounting plates and other necessary hardware to mount

the ITS Cabinet on a pole or foundation. The ITS Cabinet should be mounted as shown on the Plans

or as directed by the Engineer. All items that are required to complete the ITS Cabinet installation

shall be supplied by the Contractor.

ITS Cabinet installations shall include: power and communications run to and properly

terminated within the cabinet; any required work and hardware to mount and/or anchor the cabinet;

any fans, thermostat, or other electronic devices as shown on the Plans; any required patch cables

for equipment housed within; any DIN rails, racks, or panels required for mounting or grounding

equipment whether shown on the Plans or not; and any other equipment, materials, or labor needed

to provide fully operational equipment within the cabinet housing.

ITS Cabinets being utilized as fiber optic hub cabinets shall also house the following: the trunk

fiber optic cable storage and major routing points of the fiber optic network; the primary fiber

distribution units; any required network switch gear; electrical power equipment; and various other

devices. All hub cabinets shall be furnished with mounting plates and other necessary hardware to

mount the ITS Cabinet on a foundation.

2.Wiring, Conductors and Terminal Blocks.

The Contractor shall enclose all cabling and wiring entering the cabinet housing in conduit. The

Contractor shall securely and neatly dress all cabling and wiring inside the cabinet, including field

wiring. The Contractor shall provide sufficient slack, minimum 2 feet {600 mm}, for cabinet

equipment maintenance and re-termination of the field wiring. The Contractor shall route fiber drop

cables into the cabinet to provide as much physical protection as possible; secure these drop cables

through-out the cabinet; and strain-relieve these drop cables within the fiber termination unit.

Construction Requirements

639

The Contractor shall use stranded copper for all conductors, including those in jacketed cables,

except for earth ground conductors, which may be solid copper. Neatly arrange all wiring, firmly lace

or bundle it, and mechanically secure the wiring without the use of adhesive fasteners. All wiring

and cabling shall be routed and secured to avoid sharp edges and to avoid conflicts with other

equipment or cabling. Terminate all wiring on a terminal block, strip, busbar, or device clamp or lug;

do not splice any wiring. Use a minimum 12 AWG for all conductors of 120 Volts AC circuits, unless

otherwise shown on the Plans.

3.Surge Protection.

Surge-Protective Devices (SPDs) are required as defined in this Specification and shown on the

Plans.

Surge-Protective Devices (a.k.a. surge suppression) shall be installed to protect all copper wiring

and cabling entering the cabinet housing, except for the earth ground conductor. Terminate all wiring

between cabinet devices and the transient surge suppressors, except for the video signal coaxial feed,

on terminal strips. Use a minimum 16 AWG grounding of each surge-protective device, or larger if

recommended by the surge-protective device manufacturer. Insulated green wire and connected the

ground wire directly to the ground busbar. Do not “daisy chain” with the grounding wires of other

devices including other surge suppressors. Dress and route grounding wires separately from all other

cabinet wiring. Install grounding wires with the absolute minimum length possible between the surge-

protective device and the ground busbar. Label all surge-protective devices with silk-screened

lettering on the mounting panel.

Use minimum 18 AWG insulated black wiring between the surge-protective device sockets and

the terminal blocks for the protected circuits, or larger if recommended by the surge-protective

device manufacturer.

4.Component Installation.

All components/devices of the ITS Cabinet assembly shall be rack mounted with Phillips-head

machine screws. Install screws into tapped and threaded holes in the panels. These

components/devices include but are not limited to terminal blocks, busbars, panel and socket

mounted surge-protective devices, circuit breakers, accessory and equipment outlets, VDS interface,

video encoders, fiber distribution units and field network switches. Fasten all other cabinet

components with hex-head or Phillips-head machine screws installed with nuts (with locking washer

or insert) or into tapped and threaded holes. These other components include, but are not limited

to: door switches, fans, lights, thermostats, thermal blocks, and door lock mechanisms. Fasten stud-

mounted components to a mounting bracket providing complete access to the studs and mounting

nuts. All fastener heads and nuts (when used) shall be fully accessible with a complete ITS Cabinet

assembly, and any component/device shall be removable without requiring removal of other

components, panels, or mounting rails. Do not use self-tapping or self-threading fasteners.

5.Electrical Power Service.

The Contractor shall provide electrical power service in accordance with these Specifications

and as shown on the Plans.

6.Grounding.

The Contractor shall provide the ITS Cabinet assembly with grounding and shall be connected

upon ITS Cabinet installation in accordance with these Specifications and as shown on the Plans. The

Contractor shall measure the resistance to ground at each ITS Cabinet location in the presence of the

Engineer. Do not splice the ground conductor between the cabinet grounding terminal and the ground

rod.

7.Mounting Brackets.

Where the ITS Cabinet is pole or structure mounted, the ITS Cabinet shall be installed utilizing

mounting brackets and all appurtenances necessary in accordance with the Specifications and as

shown on the Plans. ITS Cabinet shall not move or flex on the structure/pole once installed and with

all equipment populated. Cabinet wall reinforcement by the cabinet manufacturer may be necessary.

8.Foundation (Mounting Pad).

Where the ITS Cabinet is pad mounted, a concrete mounting pad foundation shall be installed in

accordance with the Specifications and as shown on the Plans.

Construction Requirements

640

9.Concrete Pad (Service Platform).

Where the ITS Cabinet is pole or structure mounted, a poured in place concrete pad shall be

installed below the ITS Cabinet where the Plans show it as required. This concrete service platform

pad shall be installed in accordance with the Specifications and as shown on the Plans.

(m)Electrical Power Service and Transformer.

The entity (City, County, State, etc.) that will be responsible for the eventual operation and

maintenance of the fiber optic and/or ITS equipment will make application for electrical service upon

notification that power service will be required. The Contractor shall inform the Engineer when power

service is required at least 30 calendar days prior to the need of the electrical power service. This

same entity will be responsible for the cost of the service connection and the monthly service billings

thereafter.

The location of the utility service point and power source shown on the Plans is approximate. The

Contractor shall determine the exact location, voltage, procedure, and materials required by the Utility

Company. The Contractor shall obtain the Engineer’s approval of this exact power/service location

prior to installation.

When the service equipment is to be installed on a utility-owned pole, the Contractor shall furnish

and install riser, conduit, conductors, and other necessary material to complete the installation of the

service. The position of the riser and equipment will be determined by the Utility Company.

When the Contractor is to provide a lateral drop from the power source to the service pole, the

Contractor shall arrange with the serving Utility Company to complete the service connections. The

Contractor shall install the riser, conduit, conductors, enclosure and accessories, disconnect switch(es),

meter base and service pole.

No cable used for power supply shall be spliced.

1.Service Pole (Wood Pole).

Service Pole (Wood Pole) shall be installed below grade a minimum depth equal to one-sixth the

total pole height. Refer to AASHTO “Standard Specifications for Structural Supports for Highway

Signs, Luminaires, and Traffic Signals”, current edition.

All final pole locations shall be marked. The Engineer shall approve each location prior to the

commencement of drilling of each hole.

When service pole is installed on a slope of 2:1 or greater, the installation depth shall be increase

by 1 times the diameter of the pole (depth is to be measured from the down slope side of the pole.)

The backfill shall be native material in 1 foot {300 mm} lifts to match surrounding grade. Tamp

each lift to 90 percent compaction.

Existing wood poles and required wood poles used to support messenger wire or to serve as the

source of power shall be grounded.

2.Guy Wire.

Guy Wire (a.k.a. down guy) shall be installed in accordance with the requirements of this Section

and as shown on the details in the Special and Standard Highway Drawings, unless otherwise shown

on the Plans.

3.Transformer (Step-Up/Step-Down).

The Contractor shall provide step-up/step-down Transformers in accordance with these

Specifications and as shown on the Plans.

(n)Intelligent Transportation System (ITS) Pole.
1.Installation and Handling.

The Contractor shall handle and install ITS poles (especially concrete poles) in accordance with

the manufacturer’s standard operating procedures, the requirements of Section 718 and Section

891, and the following requirements:

a.Transportation, site handling and erection shall be performed by qualified personnel with

acceptable equipment and methods.

b.ITS poles shall be lifted and supported during the manufacturing, stock piling, transporting

and erection operations only at the lifting or support points, or both, as shown on the shop or

erection drawings.

c.Erection drawings for each ITS pole shall be provided which identify the structure number,

structure length, shipping weight, center of gravity and lifting points. Each ITS pole shall be clearly

marked with the corresponding information.

Construction Requirements

641

d.Prior to unloading concrete ITS pole, shop drawings shall be reviewed to identify proper

pick-up points for unloading, storage and erection procedures. A thru-hole may be provided at the

proper single point pick-up location to enable a steel bar to be inserted as a safety stop for slings

during the erection process (this bar is NOT a lifting device but serves only as a safety stop to prevent

the sling from sliding).

e.Each ITS pole shall be vertical installed within 1/8 inch per 10 feet {3 mm per 3 m} of

height.

f.The Contractor shall be responsible for digging holes for each concrete ITS pole. Concrete

ITS poles shall be placed in hole using appropriate equipment and held in vertical position until

backfill has been completed in order to maintain pole position.

2.Concrete Foundation.

For each ITS Pole that requires a concrete foundation, the Contractor shall submit Concrete

Foundation design in accordance with Section 718. The foundation design shall

The Contractor shall notify the Engineer, who shall insure that conduit and elbows are securely

attached, before concrete is poured.

The Contractor shall contact the Utility Companies to determine the location of underground

utilities in the area where the foundations are to be located. The Contractor shall be responsible for

repairing, to the satisfaction of the Utility Company, any utilities damaged by the Contractor.

3.Auger Base Foundation.

Auger Base Foundation (screw-in helix type) shall be for vehicle detection (i.e. radar and

magnetometers) installations on metal ITS poles only as shown on the Plans and defined within these

Specifications. Auger Base Foundation shall be installed by being augered into place per the

manufacturer’s installation and standard operating procedures. If the auger base foundation cannot

be installed by augering and upon the Engineer’s prior approval, the auger base foundation may be

installed by being encased in concrete.

If recommended by the auger base manufacturer, a pilot hole may be used to facilitate the

installation of an auger base foundation. The diameter and depth of the pilot hole shall not exceed

the maximum dimensions as calculated and specified by the manufacturer.

Auger Base Foundation shall also conform to the installation requirements of Section 718 and

The Contractor shall contact the Utility Companies to determine the location of underground

utilities in the area where the foundations are to be located. The Contractor shall be responsible for

repairing, to the satisfaction of the Utility Company, any utilities damaged by the Contractor.

(o)Hub Building.
1.General.

Hub Building components shall include, at a minimum, the following: hub building, foundation

footing, HVAC system, interior electrical distribution system, lighting, fire extinguisher, lightning

protection system, interior and exterior grounding, generator with automatic transfer switch, and

other items as indicated within these Specifications and shown on the Plans. This work shall include

site preparation, procurement, transportation, and installation of a Hub Building with conduit

connections to the size and number of conduits specified on the Plans.

Hub Building shall be placed at the designated location on and anchored to the concrete slab

with slab foundation being a minimum of 1 foot above grade, said slab supplied by the Contractor as

per the Specifications and as shown on the Plans. All Hub Building joints are to be sealed as

recommended by the building manufacturer.

The Contractor shall provide three (3) sets of Hub Building keys to the Engineer no more than 18

hours after Hub Building installation.

The required outside surface treatment (e.g. paving, graveling, etc.) and fencing around the Hub

Building shall be paid under their respective pay items and as shown on the Plans.

2.Electrical Power Service.

The Contractor shall provide Electrical Power Service in accordance with these Specifications

and as shown on the Plans. This includes a Generator with Automatic Transfer Switch and

Uninterruptible Power Supplies (UPSs).

3.Gas Utility Service.

The Contractor shall provide Gas Utility Service in accordance with these Specifications and as

shown on the Plans.

Construction Requirements

642

4.Grounding.

The Contractor shall provide grounding in accordance with these Specifications and as shown on

the Plans.

5.Security Fence.

A security fence shall be installed around the Hub Building as shown on the Plans. The security

fence and gate for the Hub Building will be paid for using other pay item(s) as shown on the Plans.

6.Hub Building Foundation.

A concrete foundation footing shall be installed in accordance with the Specifications and as

shown on the Plans.

(p)Gas Utility Service.

The location of the utility service point and gas source shown on the Plans is approximate. The

Contractor shall coordinate with the local gas Utility Company to determine the exact location,

procedure, and materials required for each service point. The Contractor shall obtain the Engineer’s

approval of this exact service location prior to installation. Depending upon local codes, a permit may

be required and is the responsibility of the Contractor.

The Contractor shall provide necessary items not provided by the local gas Utility Company to

make said service connection to the Hub Building Generator and associated equipment. This typically

includes the fuel line which consists of gas piping from the gas meter to the generator along with

connection to the generator. The local gas Utility Company typically provides the meter set (gas meter

along with a gas line pressure regulator if required) and the service line (piping from main distribution

line to meter set). The gas service components are to meet or exceed applicable installation

requirements of the American Gas Association (AGA), National Fuel Gas Code (NFGC), and the local gas

Utility Company.

Gas Utility Service shall also conform to the requirements of Section 646 and Section 861.

After Contractor completes the fuel line installation and prior to the Utility Company making

connection; this gas utility service installation will be subject to inspection and approval as required

by local codes.

The entity that will be responsible for the eventual operation and maintenance of the Hub Building

(or other infrastructure requiring such utility as shown on the Plans) will make application for gas utility

service upon notification that service will be required. The Contractor shall inform the Engineer when

gas service is required at least 30 calendar days prior to the need of said service. After which, the

Contractor may arrange with the serving gas Utility Company to complete the service connection. The

Department’s Area Office (or other entity as noted above or indicated on the Plans) will be responsible

for the cost of the service connection by the Utility Company and the monthly service billings

thereafter.

(q)Miscellaneous Infrastructure.

The Contractor shall assemble and install all necessary material and equipment and furnish working

equipment as shown on the Plans and as specified within the Specifications. All items that are required

to complete the installation and ensure a fully functional and operational system shall be supplied by

the Contractor.

Wiring connections in poles shall be environmentally sealed using a minimum of watertight

electrical connectors, mastic electrical splicing tape, and standard electrical tape.

1.Connector Termination Procedures.

The procedure to be used for the termination of the SC connectors used and shall meet that

process set out in that connector manufacturer’s Standard Operating Procedure for the field

installation. Fiber optic connectors shall meet the assertion loss for connectors as specified within

the Specifications.

The Contractor shall perform the final inspection of connector faces with a 200X scope.

2.Installation of Splice Closure (Underground and Aerial).

Splice Closures are required for housing and managing outside plant fusion splices, whether

installed in underground or aerial applications.

When splicing inside a building or cabinet, a splice center shall be provided in rack or wall space

utilizing fiber distribution units (FDUs) as indicated on the Plans and in accordance with Article

(c), “Fiber Distribution Units (FDU), Connectors, and Fan-Out Kit”

Splice Closure shall be installed per manufacturer’s Standard Operating Procedure, whether

installed underground or aerially.

Construction Requirements

643

The application and installation of an aerial splice closure shall be performed in such a manner

as to allow complete splice access after closure placement. This access shall be without the removal

of the closure or electrical bonds from the messenger wire. The splicing procedure and splice tray

storage within the closure shall be performed in such a process as to allow for aerial re-entry and

inspection of the closure.

The Contractor shall provide aerial splice closure with manufacturer recommended mounting

hardware for attaching to the messenger wire. The Contractor shall not be allowed to mount any

splice closures on utility poles.

The Contractor shall also provide and submit, for Engineer approval, the splice closure mounting

hardware cut-sheets with the Material Submittal package.

3.Installation of Riser Assembly.

The Contractor shall furnish and install Riser Assembly in accordance with the Plans. The Riser

Assembly shall consist of a metallic riser, backplates, mounting brackets, supports, any accessories,

and required hardware as defined within the materials section and as shown on the Plans. The Riser

Assembly shall be installed in conformance to the details shown on the Plans and meet all applicable

NEC, NEMA and NESC requirements, along with any special Utility Company pole attachment

requirements for the pole being attached.

For electrical service installations, the riser shall utilize a conduit, unless otherwise shown on

the Plans.

For fiber optic installations, the riser shall utilize a U-Guard with backplate, unless otherwise

shown on the Plans. The riser end attached to the wood pole shall be foam filled. The Contractor

shall be responsible to calculate the minimum bend radius of the fiber optic cable and shall install

the riser and fiber optic cable accordingly.

4.Installation of CommBox and Pull Box.

The Contractor shall install CommBoxes in the four steps specified in the Standard/Special

Project details. A poured in place concrete collar shall also be installed around the CommBox in

accordance with the Specifications when required by the Standard/Special Project Details and as

shown on the Plans. This concrete collar shall be formed separately from any ITS concrete pole or

structure foundations.

The Contractor shall install Pull Boxes as shown on the Plans.

The Contractor shall also install the Cable Rack for storing fiber optic cable maintenance coils

and mounting splice closures within the CommBox and Pull Box as specified within this Specification

and as shown on the Plans. The Contractor shall submit, for Engineer approval, the Cable Rack shop

drawings/cut-sheets of the materials to be installed with the Material Submittal package.

No drilled holes shall be allowed in CommBoxes or Pull Boxes unless specified otherwise as shown

on the Plans and accepted by the Engineer.

A grounding electrode (rod) shall be installed at CommBox and Pull Box locations where armored

fiber sheaths for fiber optic cables and electrical service conductors are required to be grounded in

accordance with the NEC and this Specification.

5.Installation of Fiber Marker Post.

Fiber Marker Post shall be installed according to the placement specified in the Standard/Special

Project details. Fiber marker post shall be anchored with manufacturer’s recommended anchoring

system.

A “proof check” sample for the fiber marker post dome graphics, of quantity one, shall be

produced and provided to the Engineer prior to procurement of the remaining units. The Contractor

is required to obtain the Engineer’s approval of the production fiber marker post including the dome

cover label graphics prior to subsequent procurements by the Contractor. If the Contractor does not

obtain approval prior to subsequent procurements, the Contractor assumes the risk of the fiber marker

post being rejected even after installation. No payment shall be made to the Contractor if the fiber

marker post is rejected.

Fiber marker post shall be placed no later than three days following the installation of the conduit

that shall contain fiber optic cables. The Contractor shall be responsible for safeguarding the conduit

and cables during the installation of the fiber marker posts. Any conduit or cables damaged during

marker post installation shall be removed and replaced at the Contractor’s expense.

Construction Requirements

644

6.Installation of Frequency Locate Marker.

Frequency Locate Markers shall be installed according to the placement specified in the

Standard/Special Project details. Frequency Locate Markers shall be anchored with manufacturer’s

recommended anchoring system.

Frequency Locate Markers shall be placed no later than three days following the installation of

the CommBox. The Contractor shall be responsible for safeguarding the conduit and cables during

the installation of the Frequency Locate Markers. Any conduit or cables damaged during Frequency

Locate Marker installation shall be removed and replaced at the Contractor’s expense.

7.Installation of Surge-Protective Devices.
a.All conducting cables (i.e. communication, data, and power) entering the ITS Cabinet shall

be surge protected as indicated on the Plans and in accordance with Sub-Article 893.17(i), “Surge

Protection”.

b.Hub Buildings shall be surge protected as indicated on the Plans and in accordance with

Article 893.15, “Hub Building” and Sub-Article 893.17(i), “Surge Protection”.

c.Electrical Power Service shall be surge protected as indicated on the Plans and in

accordance with Article 893.13, “Electrical Power Service and Transformer” and Sub-Article

893.17(i), “Surge Protection”

d.Dynamic Message Sign shall have surge protection in accordance with Item 893.07(a)9,

“Transient Protection” and Sub-Article 893.17(i), “Surge Protection”.

(r)Testing.
1.Terminology.

Wherever the following terms are used in Section 729 and Section 893 the intent and meaning

shall be interpreted as follows:

• ITS Electronic Equipment – Electronic equipment and/or devices paid for under Article

729.04and Article 729.05

• Interoperability – The capability to operate devices from different manufacturers or

different device types within the same communications system.

2.General.

Testing is a critical component of an ITS project. Not only does testing ensure the project was

constructed as shown on the Plans and as specified within the Specifications, but it also validates the

intent of the system. The following tests are conducted as part of each ITS project: Bench Testing,

Field Testing, and Acceptance Testing.

The Contractor shall secure a test site for the Bench Test as shown on the Plans and as specified

within this Specification. The test site must be submitted by the Contractor at the Pre-Construction

meeting for approval by the Engineer. The Contractor shall provide the test location and facility,

which shall be in the State of Alabama and within a twenty-five (25) mile radius of the project limits

unless otherwise approved by the Engineer. If the Contractor fails to get test location approval prior

to commencing any tests, the Contractor may be required to move testing to another site at the

Contractor’s expense.

There will be no direct payment to the Contractor for the cost of a suitable test site and for the

setting up of the equipment for these tests. Testing should include all applicable items required to

complete testing.

The Contractor shall notify the Engineer to schedule an Acceptance Test a minimum of seven (7)

calendar days before each proposed test date. After successfully confirming attendance of all

necessary personnel, the Engineer shall provide the approved test date to the Contractor and all

attendees.

The Contractor shall perform tests in the presence of the Engineer. When problems arise during

testing, the Engineer can require the Contractor to have a qualified technical representative on site

during the specific testing. The Contractor shall arrange, at no additional expense to the Department,

the attendance of the equipment manufacturer’s qualified technical representative.

Testing shall be in accordance with ALDOT’s Intelligent Transportation Systems Test Manual as

developed by the Bureaus of Design and Maintenance; and, be documented with the corresponding

ITS device’s testing checklist(s).

If any ITS electronic equipment requires re-test, the above minimum test information shall be

provided for each re-test per each piece of equipment.

Construction Requirements

645

Once a test is completed, a copy of the Test Result Documentation shall be submitted to the

Engineer within seven (7) calendar days following completion of test activities. Any given test session

is considered incomplete until the Engineer has approved the documentation for that test session.

It shall be the Contractor’s responsibility for successful completion of each test. Any equipment

which fails any tests shall be subject to re-test at no additional cost to the Department.

The Engineer’s approval of test procedures, Test Result Documentation, and witnessing of such

tests shall not relieve the Contractor of their responsibility to provide a completely acceptable and

operating ITS project.

3.Bench Test.

The Contractor shall perform a Bench Test on all ITS electronic equipment and ITS Cabinets prior

to installation. The Bench Test shall be performed by the Contractor at the approved test location

and witnessed by the Engineer.

The Bench Test shall consist of the following two test phases:

a.The Visual Inspection phase shall consist of visually inspecting all Intelligent Transportation

System (ITS) electronic equipment, ITS Cabinets and materials to insure there is no

physical damage; and that the equipment and cabinets conform to their approved material

submittal cut sheets.

b.The Manufacturer’s Startup and Diagnostics test phase shall consist of the Contractor

performing the manufacturer’s out-of-the-box startup and diagnostic test for each piece

of ITS electronic equipment, using the respective manufacturer’s recommended startup

diagnostics, configuration, and testing. The Contractor shall submit with the Material

Submittal the manufacturer’s recommended startup and diagnostic test procedures for

review and approval prior to conducting the Bench Test.

The Contractor shall supply all temporary wiring and cabling (e.g. CAT-5/6/6A, RS-232/422/485,

DVI, VGA, Coaxial, etc.), laptop, diagnostic software, and electrical service necessary for the Bench

Test.

Test Result Documentation for the Bench Test, for each item in full contract quantity, shall be

submitted to the Engineer for approval. The Engineer’s approval shall be in writing.

The Contractor shall deliver all manufacturers’ configuration and diagnostic software to the

Engineer at the completion of the Burn-In.

4.Field Test.

The Field Test shall demonstrate that the ITS electronic equipment is properly operating,

configured, and transmitting data to ALDOT’s Intelligent Transportation Systems software applications

as shown on the Plans and as specified within the Specifications. This test is conducted in the field

at each ITS device site.

The Contractor shall not begin the Field Test until all ITS electronic equipment has successfully

passed the Bench Test and its Test Result Documentation has been approved by the Engineer in

writing.

The Contractor shall review the standard ALDOT Acceptance Test “Functional Operations Test

Procedures (FOTP)” and submit any additional or modified items for review and acceptance to the

Engineer. Any supplemental items to be added to the standard FOTP shall:

• identify the additional functional site and/or remote requirements to be tested;

• define the test procedure steps required for additional testing of these functional

requirement(s); and,

• identify the expected results for successfully passing each additional test procedure.

The Contractor shall submit to the Engineer the standard Acceptance Test “FOTP” document or

the amended FOTP such that a thirty (30) day review process may occur by the Engineer. No Field

Test at any given site can begin until the Acceptance Test “FOTP” document has been accepted by

the Engineer.

The Contractor shall supply all temporary wiring and cabling (e.g. CAT-5/6/6A, RS-232/422/485,

DVI, VGA, coaxial, etc.), laptop, and diagnostic software necessary for the Field Test and performing

the Functional Operations Test Procedures.

The Contractor shall not begin any Field Test until all work at that location is complete.

The Contractor shall perform a Field Test for each individual device at the site.

The Field Test shall consist of the following:

Construction Requirements

646

a.Visual Inspection.

The Visual Inspection shall consist of the Engineer visually inspecting all ITS electronic

equipment, ITS Cabinets and materials to ensure that they were not damaged while being

transported from the Bench Test location to the project site and being installed.

b.Field Demonstration.

The Installation shall consist of the Contractor demonstrating to the satisfaction of the

Engineer the following minimum requirements:

• ITS electronic equipment, ITS Cabinets and associated materials have been installed

as shown on the Plans;

• ITS electronic equipment has been properly connected (including the patch cables,

fiber drop cable, and cable termination);

• Perform Continuity Test on supplied network, coaxial, DVI and VGA cabling; and,

• Inspect the installation of grounding and the surge protection systems (includes

performing and successfully completing the Insulation Test, Continuity Test, and

Ground Resistance Test as shown on the Plans and as specified within this

Specification).

c.Performing Functional Operation Test Procedures (FOTP).

The Contractor and the Engineer shall perform the “FOTP” tests for each device installed

at the site being tested. Results shall be documented on these “FOTP” test report forms.

The Contractor shall generate Test Result Documentation for the Field Test which shall be

broken down by project site and include all ITS electronic equipment installed at each site.

The complete package of the Test Result Documentation for the Field Test shall be submitted

to the Engineer for acceptance. The Engineer’s acceptance shall be in writing.

5.Acceptance Test.

The Acceptance Test shall demonstrate that the ITS electronic equipment installed in the field

is properly communicating, operating and configured through ALDOT’s Intelligent Transportation

Systems software applications.

The Contractor shall not begin the Acceptance Test until all ITS electronic equipment has

successfully passed the Field Test and its Test Result Documentation has been approved by the

Engineer in writing. The Acceptance Test is typically conducted at the ALDOT TMC closest to the

project location. However, the Engineer may approve a different location to conduct the Acceptance

Test at his/her discretion.

Should any additional test procedure to the standard ALDOT Acceptance Test FOTP be deemed

necessary for the Acceptance Test, the Contractor shall submit the additional test items following

the same methodology as performed prior to the Field Test.

The Contractor shall perform an Acceptance Test for each individual site.

The Contractor shall not begin the Acceptance Test until all work at each site is complete and

Field Test results accepted by the Engineer.

The Acceptance Test shall consist of performing the FOTP that were conducted as part of the

Field Test.

The Contractor shall generate Test Result Documentation for the Acceptance Test. The

Acceptance Test shall be submitted to the Engineer for acceptance. The Engineer’s acceptance shall

be in writing.

(s)Burn-In.

The Contractor shall perform Burn-In on the ITS electronic equipment, ITS Cabinets and materials

to ensure their proper operation, interoperability and service for an extended time frame within actual

field conditions and without any failures or maintenance problems.

The Contractor shall not begin the Burn-In until the Acceptance Test has been successfully

completed for all sites and approved by the Engineer in writing.

After confirming all sites have successfully completed the Acceptance Test, the Engineer shall

send written notice to the Contractor and all necessary personnel of the authorized Burn-In start date.

The Burn-In Period shall be thirty (30) consecutive calendar days without system failure. During

the Burn-In Period, the Contractor shall expeditiously perform any necessary adjustment and replace

any malfunctioning parts of the equipment required to place the system in an acceptable operational

condition to the satisfaction of the Engineer. No extra compensation will be allowed for any work so

required, such being considered incidental to furnishing and installing a complete operational system.

Construction Requirements

647

During the Burn-In Period, time charges shall be suspended if all other work has been completed

and accepted pending the results of the Burn-In.

The Contractor shall deliver the As-Built Drawing package and all the ITS device manufacturers’

Embedded Protocol Control software packages to the Engineer at the completion of the Burn-In.

The Burn-In Period is intended to be concurrent for all sites within the project. However, the

Engineer may elect due to a state of emergency to allow multiple concurrent Burn-In periods to occur

based on a breakdown of the project at his/her discretion (e.g., DMS sites, Camera sites, individual

sites, etc.).

An equipment failure during the Burn-In Period is defined as a condition where a component stops

functioning. A system failure is defined as a condition under which the system is unable to function as

a whole or in significant part to provide the services as designated. While a single component failure

may not constitute a system failure, chronic failure of that component or component type may be

sufficient to be considered a system failure as determined by the Engineer. What constitutes a chronic

failure shall be agreed upon in writing by the Contractor and the Engineer prior to beginning the Burn-

In.

ITS electronic equipment which has repeated failures (repeated failures are defined as more than

two in a thirty-day period) during the Burn-In Period shall be replaced by the Contractor at no cost to

the Department. Field Test must be conducted for the new equipment and the Engineer’s acceptance

shall be obtained for said testing. Upon satisfactory completion of the testing, the Engineer will provide

written authorization to commence with a thirty (30) day Burn-In Period for the new equipment.

Final acceptance shall mean successful completion of Burn-In to the satisfaction of the Engineer.

If any equipment or device fails to complete the thirty (30) day Burn-In Period, the Burn-In Period

shall be suspended and time charges resumed. The Burn-In Period will not be restarted except when

the following has been met:

• Repairs to the malfunctioning equipment/device have been satisfactory completed; and,

• The repaired equipment/device is to be re-tested and proven to be properly functioning.

Only upon the Engineer’s acceptance of the repaired equipment/device, will the Contractor be

allowed to resume the Burn-In Period.

General communication outage or failure due to hardware is considered a system failure in any

case. Communication failure due to a minor component may not be a system failure. Specifically

exempted as system failures are failures caused by accident, natural disasters, or other external forces.

The Engineer will advise the Contractor in writing when it considers that a system failure has occurred

or a chronic failure exists.

Each system failure during this Burn-In Period shall require restarting the clock plus an additional

two (2) calendar days of successful operation prior to being eligible for final acceptance (i.e., if there

are two system failures during the initial 30 day period, the period would be increased by 4 days).

Successful completion of the Burn-In Period shall occur at the end of thirty (30) complete calendar days

of operation without a system failure ascribable to hardware, software, or communications

components.

The Contractor shall generate Test Result Documentation for the Burn-In which shall include at a

minimum:

• Documentation for any ITS electronic equipment failures, system failures or communications

failures;

• Document corrective actions taken by the Contractor for equipment repairs;

• Any re-test documentation for the repaired or replacement equipment;

• All manufacturers’ ITS electronic equipment protocol control software; and,

• All manufacturers’ configuration and diagnostic software along with licenses transferred to

the Department.

This Test Result Documentation shall also consist of the minimum applicable information as

specified within Acceptance Test of the Specification. Once the Burn-In Period is successfully

completed, the Contractor shall submit the complete package of the Test Result Documentation for

Burn-In to the Engineer for acceptance. The Engineer’s acceptance shall be in writing, which

acknowledges receipt of the Test Result Documentation along with verification that Burn-In was

successfully completed.

If equipment or device failures occur, the Engineer may request for the Contractor to submit

advance copies of the Burn-In Test Result Documentation so as to gain insight to the equipment

problems and any corrective actions taken to date.

Construction Requirements

648

(t)Training.

The Contractor shall provide installation, operations and maintenance training for up to ten (10)

people. Training shall be performed by product manufacturer(s) for the ITS electronic equipment

installed on the Project; and shall be performed both in the field and in the office (or classroom).

Training shall include all applicable items required to complete training.

The Contractor shall notify the Engineer to schedule training a minimum of seven (7) calendar days

before the proposed training date. After successfully confirming attendance of all necessary personnel,

the Engineer shall provide the accepted training date to the Contractor and all attendees. The

Contractor shall be responsible for coordinating accepted training date with the product manufacturer

instructor(s), along with any field and in-office preparations for completing this training. The

Contractor shall take into consideration any time necessary for product manufacturer’s instructor(s)

travel (including lead times for booking flights and/or rental cars, time for actual commutes, and time

for any field or classroom setup).

The Contractor shall include in the cost of training all supplies, equipment, materials, user

manuals, handouts, travel, and subsistence necessary to conduct the training. A training notebook

shall be provided to each trainee in a labeled 3-ring binder.

The Contractor shall submit the proposed training package to the Engineer for acceptance. The

training package shall include detailed course curriculum(s), detailed daily training schedule, draft

manuals, handouts, and resumes of all instructors. This training package shall be submitted a minimum

of thirty (30) calendar days prior to scheduling training. The Engineer shall review the proposed training

materials and reserves the right to request modifications to the training program and materials as

appropriate. The Engineer’s acceptance of the training package shall be in writing.

Training shall not last for more than eight (8) hours of any given day (i.e., twenty-four (24) hours

of training would be conducted over at least a three (3) day period). Training shall be a mixture of

formal classroom and hands-on training, and at least half of the training shall be hands-on. Training

shall be conducted at a facility approved by the Engineer and shall be completed within sixty (60) days

after completion of Burn-In. Upon the request of the Contractor, the Engineer may approve training

to be conducted prior to completion of Burn-In.

The training shall be for the ITS electronic equipment as shown on the Plans or as specified within

the Specifications; and, for any modifications or enhancements made by the Contractor to ALDOT’s

Intelligent Transportation Systems software applications or overall ITS system.

Training material shall serve not only as training course guidance, but also as a quick reference

guide for future use by the attendee. A copy of all training material, in reproducible form, shall be

delivered to the Engineer after training is complete.

(u)Warranty.

The Contractor shall warrant and guarantee the satisfactory in-service operation of all ITS

equipment and all related apparatus, specified or implied within the Specifications and as shown on

the Plans, for a warranty period of one (1) year following the completion of partial acceptance for

maintenance. The Contractor’s warranty shall be a written guarantee that the ITS equipment will be

fully functional and will remain free of defects in material and workmanship during said warranty

period.

Upon successful completion of a required Burn-In Period, the Contractor may request partial

acceptance for maintenance, as addressed by Sub-Article 105.15(b), of the portion or component of

the work covered by the Burn-In. The Engineer will review the request and will issue partial acceptance

for maintenance if the installation has been acceptably completed. The warranty period will then start

for that portion or component of the work.

During the warranty period, the Contractor shall repair with new materials, or replace at no

charge, any device, product, or other material containing a warranty defect. During the support period,

the Contractor shall enter a precise description of any necessary repair work performed into a logbook.

All materials returned from warranty repairs shall be made through the distributor or manufacturer at

no additional charge. Warranty repairs and replacements shall be completed within two weeks from

date of return to the distributor or manufacturer.

Before final payment is made, the Contractor shall supply ALDOT’s Construction Bureau a letter

setting forth the dates of the guarantees giving a telephone number, an address, and a person to

contact for any required warranty service.

The Contractor shall transfer any available manufacturer’s warranties or guarantees to the

Department. These warranties and guarantees shall be continuous throughout their duration and state

that they are subject to such transfer.

729.05Basis of Payment

649

The Department will not make the final payment for work under this Section until the warranties,

guaranties and contact information are furnished to the Engineer.

Method of Measurement

The Intelligent Transportation Systems shall be measured for payment by the appropriate items

complete, in place, acceptably installed, tested and operational in accordance with the following:

ITEM 729-A: Fiber Optic Cable with number of fibers indicated shall be measured per linear foot.

ITEM 729-B: Fiber Distribution Unit, Fan-Out Kit, and Fiber Optic Patch Cable shall be measured

by each unit installed.

ITEM 729-C: Network Device shall be measured by each unit installed.

ITEM 729-D: Camera shall be measured by each unit installed.

ITEM 729-E: Vehicle Detection Systems shall be measured per each device installed.

ITEM 729-F: Dynamic Message Sign shall be measured by each unit installed.

ITEM 729-G: Environmental Sensor shall be measured by each unit installed.

ITEM 729-H: Highway Advisory Radio shall be measured by each unit installed.

ITEM 729-I: Conduit, Conductor, Locate Tone Wire, Messenger, and Warning Tape shall be

measured per linear foot.

ITEM 729-J: ITS Cabinet shall be measured by each unit installed.

ITEM 729-K: Electrical Power Service and Transformer shall be measured per each site/unit

installed.

ITEM 729-L: Pole shall be measured by each unit installed.

ITEM 729-M: Building shall be measured per lump sum.

ITEM 729-N: Miscellaneous Infrastructure shall be measured by each unit installed.

Basis of Payment

Unless otherwise indicated below, all payments shall be made in increments of:

1.Up to 70% of the contract unit price upon successful completion of the BENCH TEST and

installation of item(s) [Partial payments may be made in accordance with Article 109.07

up to this percentage.];

2.Additional 15% of the contract unit price upon completion of the FIELD TEST; and,
3.Final 15% of the contract unit price upon completion of the ACCEPTANCE TEST (BURN-IN).
(a)Unit Price Coverage.

ITEM 729-A. FIBER OPTIC CABLE, measured as noted above, will be paid for at the contract bid

price, which shall be full compensation for furnishing, installing, and testing, complete in place, as

shown on the Plans, with the following: fiber optic cable with the number of fibers indicated;

attached to messenger wire and pulled through conduit when required; all required connections;

fiber optic cable tags and labeling; aerial slack brackets; manufacturer and Contractor warranties;

and for all materials, labor, equipment, tools, transportation, and incidentals necessary to complete

this item of work. (Please Note: Conduit, Messenger Wire, Fiber Marker Post, and Fusion Splicing

are separate pay items.)

ITEM 729-B. FIBER DISTRIBUTION UNIT, FAN-OUT KIT, FIBER OPTIC PATCH CABLE, measured as

noted above, will be paid for at the contract bid price, which shall be full compensation for

furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:

a.Fiber Distribution Unit: including housing, panels, connectors, connector barrels, zip ties,

clamps, cable trays, cable management organization, and labels; all adapters/couplings,

for the number of fibers indicated, all required termination splicing; mounting brackets

and hardware;

b.Fan-Out Kit: fan-out kit with adapters/couplings, for the number of fibers indicated;
c.Fiber Optic Patch Cable: fiber optic patch cable of functional length required to connect

the associated equipment and FDUs; connectors, connector barrels, and associated

hardware;

d.manufacturer and Contractor warranties;
e.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

Basis of Payment

650

Fan-Out Kit and Fiber Optic Patch Cable will be paid at 100% of the contract bid price upon

completion of the installation of these items.

ITEM 729-C. NETWORK DEVICE, measured as noted above, will be paid for at the contract bid

price, which shall be full compensation for furnishing, installing, and testing, complete in place, as

shown on the Plans, with the following:

a.Network device with all necessary electrical components, including but not limited to

wiring, cabling, harnesses, and indicators;

b.Wireless Licensing (including wireless path loss analysis and testing, frequency

coordination, FCC application process, and associated costs/fees);

c.Network hook-up, fiber optic transceivers field and head-end, wireless communication

devices (antenna, dishes, remote and head-end), communication modules with data cables

(CAT 5E/6/6A patch cables, antenna cables and mounts);

d.Equipment mounts;
e.Power hook-up; power supplies with power cables;
f.Surge protection for communication/data and power; grounding system;
g.Manufacturer’s operational software package(s) and firmware;
h.Initial configuration, Acceptance Testing with Burn-In, complete device documentation,

manufacturer and Contractor warranties and support;

i.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-D. CAMERA, measured as noted above, will be paid for at the contract bid price,

which shall be full compensation for furnishing, installing, and testing, complete in place, as shown

on the Plans, with the following:

a.Camera assembly complete with all components including, but not limited to: camera,

lens, pan/tilt drive, control electronics and environmental enclosure, cables (power, video

and control), housing assembly and mounting brackets;

b.camera/video drivers, control and diagnostics software, initial configuration; complete

camera documentation/manuals;

c.Network connection and configuration;
d.Surge protection for communication/data and power;
e.Power supplies with cabling and connection;
f.Grounding system; air terminals and lightning protection system;
g.Testing (including all test report/packages, electronic files and deliverables), Training

(including all instructors, travel, classroom and field materials, electronic files and

deliverables), and Acceptance Testing with Burn-In;

h.Manufacturer and Contractor warranties and support;
i.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-E. VEHICLE DETECTION SYSTEMS, measured as noted above, will be paid for at the

contract bid price, which shall be full compensation for furnishing, installing, and testing, complete

in place, as shown on the Plans, with the following:

a.Vehicle Detection Systems complete with all components including, but not limited to:

vehicle detection unit(s) (e.g. sensors, repeaters, access points, antenna), control and

interface equipment (e.g. detection system processor, communication interface panel,

cabinet interface unit), cables (power, data and control), housing assembly, and mounting

brackets (with pole extensions if required);

b.Vehicle Detection device/equipment drivers, control and diagnostics software, initial and

post configuration (e.g. software setup and programming, adjusting detection zones,

adjustment for repeaters and access points); license(s); complete Vehicle Detection

Systems documentation/manuals;

c.Network connection and configuration;
d.Surge protection for communication/data and power;
e.Power supplies with cabling and connection;
f.Grounding system; air terminals and lightning protection system (if required);

Basis of Payment

651

g.Testing (including all test report/packages, electronic files and deliverables), Training

(including all instructors, travel, classroom and field materials, electronic files and

deliverables), and Acceptance Testing with Burn-In;

h.Manufacturer and Contractor warranties and support;
i.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-F. DYNAMIC MESSAGE SIGN, measured as noted above, will be paid for at the contract

bid price, which shall be full compensation for furnishing, installing, and testing, complete in place,

as shown on the Plans, with the following:

a.All electrical, electronic, or electromagnetic components use in any DMS assembly,

including but not limited to capacitors, potentiometers, resistors, semiconductor devices,

transformers, inductors, circuit breakers, switches, terminal blocks, wiring, cabling,

harnesses, indicators, electromechanical shutter units, light emitting diodes and modules,

lamps, driver boards, sign control logic boards, opto-isolation cards, photosensors, sign

electronics power supply, pin and socket connectors, PCB connectors, wire connectors,

PCB assemblies, fans, filters, and warning beacons;

b.All DMS housing components including, but not limited to: the walk-in housing assembly

and mounting hardware, DMS platform and housing door, and maintenance safety eyebolts;

c.DMS controller and remote controller, if any;
d.Network connection and configuration;
e.Power supplies with cabling and connection;
f.Surge protection for communication/data and power;
g.Grounding system; air terminals and lightning protection system;
h.Software/driver interfaces, control and diagnostics software, initial configuration;

complete DMS documentation;

i.Testing (including all test report/packages, electronic files and deliverables), Training

(including all instructors, travel, classroom and field materials, electronic files and

deliverables), and Acceptance Testing with Burn-In;

j.Manufacturer and Contractor warranties and support;
k.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-G. ENVIRONMENTAL SENSOR, measured as noted above, will be paid for at the

contract bid price, which shall be full compensation for furnishing, installing, and testing, complete

in place, as shown on the Plans, with the following:

a.Environmental Sensor system including, but not limited to: air temperature sensor,

relative humidity sensor, visibility sensor, precipitation rate sensor, barometric pressure

sensor, wind speed and direction sensor, pavement precipitation depth sensor, and either

an in-road or remote road pavement sensor, as shown on the Plans;

b.Environmental Sensor data processing unit and remote controller, if any;
c.All Environmental Sensor housing components including, but not limited to: the housing

assembly, and mounting brackets (with pole extensions if required) and hardware;

d.Environmental Sensor device/equipment drivers, control and diagnostics software, initial

and post configuration (e.g. software setup and programming, adjusting sensors);

license(s); complete Environmental Sensor(s) documentation/manuals;

e.All wiring, cabling, harnesses and connections; Network connection and configuration;
f.Surge protection for communication/data and power;
g.Power supplies with cabling and connection;
h.Grounding system; air terminals and lightning protection system (if required);
i.Testing (including all test report/packages, electronic files and deliverables), Training

(including all instructors, travel, classroom and field materials, electronic files and

deliverables), and Acceptance Testing with Burn-In;

j.Manufacturer and Contractor warranties and support;
k.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

Basis of Payment

652

ITEM 729-H. HIGHWAY ADVISORY RADIO, measured as noted above, will be paid for at the

contract bid price, which shall be full compensation for furnishing, installing, and testing, complete

in place, as shown on the Plans, with the following:

a.Highway Advisory Radio complete with all components including, but not limited to: radio

transmitter, digital recorder/player, GPS synchronizer, HAR enclosure/cabinet, antenna

subsystem, and mounting hardware;

b.HAR local and remote controller, if any;
c.Highway Advisory Radio device drivers/interfaces, HAR system software (including control

and diagnostics software), initial configuration; FCC license(s); complete HAR

documentation/manuals;

d.All wiring, cabling, harnesses and connections; Network connection and configuration;
e.Surge protection for communication/data and power;
f.Power supplies with cabling and connection;
g.Grounding system; air terminals and lightning protection system (if required);
h.Testing (including all test report/packages, electronic files and deliverables), Training

(including all instructors, travel, classroom and field materials, electronic files and

deliverables), and Acceptance Testing with Burn-In;

i.Manufacturer and Contractor warranties and support;
j.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-I. CONDUIT, CONDUCTOR, LOCATE TONE WIRE, MESSENGER, and WARNING TAPE,

measured as noted above, will be paid for at the contract bid price, which shall be full compensation

for furnishing, installing, and testing, complete in place, as shown on the Plans, with the following:

a.Conduit: including pull tape, locate tone wire (when fiber optic cable is to be installed in

conduit), conduit hangers, brackets, coupling, conduit lubricant, accessories, supports,

attachment hardware, hardware, fittings, trenching, placing, joining, attaching to

structure, backfilling, seeding and mulching of disturbed areas, disposal of debris;

b.Conductor or Locate Tone Wire: including hardware, fittings, trenching, placing, joining,

attaching to structure, backfilling, seeding and mulching of disturbed areas, disposal of

debris;

c.Messenger: messenger wire, lashing, down guy, mounting brackets, supports, accessories,

insulators, hardware and fittings, couplings, grounding electrode system;

d.Warning Tape: including print proofs, tape splicing components, trenching, placing,

backfilling, seeding and mulching of disturbed areas, disposal of debris;

e.Friction Reduction Multiduct Sleeve: sleeve material and pull tape;
f.Manufacturer and Contractor warranties; and for all materials, labor, equipment, tools,

transportation, and incidentals necessary to complete this item of work.

ITEM 729-I will be paid at 100% of the contract bid price upon installation.

ITEM 729-J. ITS CABINET, measured as noted above, will be paid for at the contract bid price,

which shall be full compensation for furnishing, installing, and testing, complete in place, as shown

on the Plans, with the following:

a.Cabinet complete with documentation, base mount foundation, pole mount attachment

hardware, incidental hardware;

b.Fully mounted, either pole, base, or pedestal, as shown on the Plans with all required

conduits.

c.Electrical wiring, transformers, breakers, fans, switches, interior lighting, terminal blocks,

receptacles, panel board, surge protection, cable racks, equipment bays, other devices as

indicated, and all associated incidental equipment inside the cabinet;

d.Grounding electrode system;
e.Manufacturer and Contractor warranties and support;
f.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

Basis of Payment

653

ITEM 729-K. ELECTRICAL POWER SERVICE and TRANSFORMER, measured as noted above, will

be paid for at the contract bid price, which shall be full compensation for furnishing, installing, and

testing, complete in place, as shown on the Plans, with the following:

a.Electrical Power Service: including enclosure, circuit breaker(s), disconnect switch(es),

transient/surge protection, weather head, vertical conduit(s) and riser; meter base

installation (as required by the utility);

b.Transformer: including enclosure, disconnect switch(es), transient/surge protection,

step-up/step-down transformer(s), vertical conduit(s) and riser;

c.All wiring from utility service to the meter base and connections (Please Note:

Lateral/horizontal conductors, after the service disconnect/meter base, are separate pay

items.);

d.Wood pole(s), guy wire, excavating, backfilling, attachment hardware, grounding system,

and attachment to local utility;

e.Manufacturer and Contractor warranties;
f.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-L. POLE, measured as noted above, will be paid for at the contract bid price, which

shall be full compensation for furnishing and installing, complete in place, as shown on the Plans,

with the following:

a.Complete Pole assembly with all components including, but not limited to: pole, tenon

(if required), foundation (if required, with reinforcing steel, rebar, anchor bolts, conduits,

auger and base plate), design calculations, weather head(s), vertical conduit and riser;

b.Guy wire (if required),
c.Drilling, excavation and backfill, attachment hardware;
d.Grounding system; air terminals and lightning protection system (if required);
e.Manufacturer and Contractor warranties;
f.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-L will be paid at 100% of the contract bid price upon completion of the installation of

the pole.

ITEM 729-M. BUILDING, measured as noted above, will be paid for at the contract bid price,

which shall be full compensation for furnishing, installing, and testing, complete in place, as shown

on the Plans, with the following:

a.Hub Building complete with all interior lighting, receptacles, switches, panel board,

wiring/conductors/conduits, surge protection, grounding system, security system, cable

racks, generator (with concrete pad), automatic transfer switch, and other devices as

indicated;

b.Installed complete on a foundation with all utilities connected and operational, incidental

hardware, and gas source for the generator, at no separate cost to the Department;

c.Manufacturer and Contractor warranties and support;
d.and for all materials, labor, equipment, tools, transportation, and incidentals necessary

to complete this item of work.

ITEM 729-N. MISCELLANEOUS INFRASTRUCTURE, measured as noted above, will be paid for at

the contract bid price, which shall be full compensation for furnishing, installing, and testing,

complete in place, as shown on the Plans, with the following:

a.Fusion Splicing: fusion splices, fusion heat shrink sleeves and incidentals, testing, and

documentation (All splices and terminations shall be accurately and fully documented on

forms supplied by the Department. No payment for splices or terminations shall be made

unless forms have been accurately completed by the Contractor and approved by the

Engineer.);

b.Splice Closure: splice closure housing with seals, splice organizer, splice trays, mounting

brackets, hardware, and accessories;

c.Riser Assembly: riser, backplate, conduit, couplings, weatherhead, standoffs, mounting

brackets, supports, hardware, and accessories;

Basis of Payment

654

d.CommBox: communication box with cover, cable rack system, attachment hardware, base

material, and concrete collar; grounding electrode system (where required); excavation,

backfilling, seeding and mulching of disturbed areas; disposal of debris;

e.Pull Box: pull box with cover, cable rack system, cable management, attachment

hardware, supports, and all necessary accessories; grounding electrode system (where

required);

f.Fiber Marker Post: post, dome with graphics label and sleeve, and anchor;
g.Frequency Locate Marker: locate marker unit and labeling;
h.Uninterrupted Power Supply: control/monitoring unit, batteries, transient/surge

protection, wiring, network card, mounting, and incidental hardware and software;

i.Manufacturer and Contractor warranties; and for all materials, labor, equipment, tools,

transportation, and incidentals necessary to complete this item of work.

Fusion Splicing, Splice Closure, Riser Assembly, CommBox, Pull Box, Fiber Marker Post and

Frequency Locate Marker will be paid at 100% of the contract bid price upon completion of the

installation of these items.

(b)Payment will be made under Item No.:

729-A Fiber Optic ( 1 ) Cable, ____ - per linear foot

729-B Fiber Distribution Unit, ( 2 ) - per each

Fan-Out Kit – per each

FO Patch Cable, ( 3 ) - per each

729-C Network Device, ( 4 ) - per each

729-D Camera, ( 5 ) - per each

729-E Vehicle Detection System ( 6 ) - per each

729-F Dynamic Message Sign, ( 7 ) ( 8 ) - per each

729-G Environmental Sensor, ____ - per each

729-H Highway Advisory Radio, ( 9 ) - per each

729-I Conduit, ( 10 ) - per linear foot

Conductor, ( 11 ) - per linear foot

Locate Tone Wire - per linear foot

Messenger - per linear foot

Warning Tape - per linear foot

729-J ITS Cabinet, Type ____ - per each

729-K Electrical Power Service ( 12 ) - per each

Transformer ( 13 ) – per each

729-L Pole, ( 14 ) - per each

729-M Building, ( 15 ) - per lump sum

729-N Miscellaneous Infrastructure, ____ - per each

(1)Specify Cable Type [Trunk, Drop, or Armored]
(2)Specify Fiber Distribution Unit Type [Primary or Secondary]
(3)Specify FO Patch Cable Type and Length
(4)Specify Network Device Type
(5)Specify Camera Type [Fixed, Positioner, or Dome]
(6)Specify Detection Type [Radar, Magnetometer, or Bluetooth]
(7)Specify Dynamic Message Sign Type [Walk-In, Front Access, or Dedicated]
(8)Specify Dynamic Message Sign Size
(9)Specify Highway Advisory Radio Type [Permanent or Portable]
(10)Specify Conduit Type [Exposed, Underground, Rigid Metallic, Reinforced Thermosetting

Resin, or Friction Reduction Multiduct Sleeves] and Size [1 1/2”, …, 2 x 2 Inch]

(11)Specify Conductor Size [8 AWG, 6 AWG, 4 AWG, 2 AWG, 1 AWG, 1/0 AWG, 2/0 AWG, 3/0

AWG, 4/0 AWG, 250 KCMIL, 400 KCMIL, or 500 KCMIL]

(12)Specify site location
(13)Specify Transformer Type and/or Size
(14)Specify Pole Type [Concrete, Steel or Fiberglass]
(15)Specify Building Type and/or Site location

730.03Construction

INTELLIGENT TRANSPORTATION SYSTEMS in other states

Get an email when 729 changes

Alabama revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 625–0 of 934. View official source ↗

Ask about this section

Scoped to Alabama 2022 Standard Specifications for Highway Construction, Section 729 — INTELLIGENT TRANSPORTATION SYSTEMS. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.