536-1 Description.
Construct guardrail, including end treatments, transition connections to rigid barrier, and other associated hardware, as specified in the Plans and in accordance with the Standard Plans, Index 536 series . Remove existing guardrail as specified in the Plans.
536-2 Materials.
Use components for guardrail, including posts, offset blocks, ste el panels, panel components, bolts, foundations, barrier delineators, end delineators, rub rail, pipe rail, and approach terminals , in accordance with Section 967. Prior to installation , submit a list of the APL numbers of all approach terminals, barrier d elineators, and composite offset blocks to be used on the project.
536-3 Construction.
536-3.1 Height Tolerance: Install guardrail panels at the height shown in the Standard
Plans with a tolerance of 1 inch above and 1/2 inch below the nominal height spec ified. Where unavoidable surface irregularities, including but not limited to across shoulder gutters, inlets, and roadway surface break lines, are encountered, a tolerance of 3 inches above and 1 inch below the nominal height is permissible.
536-3.2 Station Location Tolerance: Where guardrail feature stationing is called out in
the Plans, the longitudinal stationing tolerance is plus or minus 3 feet and 1 -1/2 inch, unless otherwise restricted by field conditions as determined by the Engineer. For transition connections to rigid barrier, install the thrie -beam terminal connector at a 1/4 inch tolerance relative to the end of the rigid barrier as defined in the Plans and Standard Plan s.
536-3.3 Setting Posts: Set posts plumb and to the soil depth shown in the Standard Plan s.
Use the deep post option only where specified in the Plans. Place posts in excavations, backfill the space around the posts, and thoroughly tamp the backfilled soil. As an alternate method, use a post-driving machine meeting the appr oval of the Engineer. For guardrail post replacement, backfill and tamp the existing soil hole prior to setting the replacement post. If driving timber posts, either block out holes in the asphalt pavement during the asphalt paving operation or cut hol es through the asphalt mat prior to the post installation. Blocked out or cut holes in the asphalt pavement must be at least 50% larger than the cross - sectional area of the timber post. After driving the posts, patch the area of asphalt around each post with hot bituminous mixture in accordance with Section 339. If driving steel posts, drive the post directly through the asphalt mat. Fill asphalt depressions or cracks with hot bituminous mixture in a manner meeting the approval of the Engineer. For post locations where subsurface miscellaneous rock or other solid material is obstructing the post placement, remove such material as follows:
536-3.4 Post Location Conflicts: When the construction of guardrail at the r equired post
spacing results in post(s) conflicting with sidewalks, gutter, underground utilities, or other permanent obstacles which cannot be removed as determined by the Engineer, the following options are permitted with the approval of the Engineer:
536-3.5 Deep Post: Mark deep posts on the back face, centered 4 inches below the top
edge, with a legible black letter ‘D’ approximately 2 inches vertical by 1 inch horizontal in size. Use a permanent black ink stamp or paint sten cil.
536-3.6 Special Steel Post: Mount to concre te structures using the following systems.
536-3.6 1 Adhesive Bonded Anchors: For concrete structures 9 inches deep and
greater, mount the base plate to the concrete using steel adhesive -bonded anchor bolts with a minimum tensile strength of 60 ksi and galvanized in accordance with ASTM A153. Stainless steel components may be substituted, but components plated in accordance with ASTM B633 are not acceptable. Use adhesive -bonded anchors in accordance with Section 937 and 416 (Type HSHV) and in accordance w ith the manufacturer’s specification. Drill holes in concrete, through reinforcing steel if encountered. Thoroughly clean and dry the holes immediately prior to setting anchors. At a minimum, meet the following strength capacities in Table 536-1: FY 2023-24 Return to Table of Contents Table 536-1 Anchor Strength Capacities Approach Slabs Other Structures Min. Tensile Load (Each Anchor) 14,000 lbs 8,000 lbs Min. Shear Load (Each Anchor) 15,000 lbs 7,800 lbs
536-3.6 2 Hex -Head Bolt: For concrete structures less than 9 inches deep, use a
3/4 inch Hex-Head bolt passing through a 7/8 inch drilled hole in the concrete structure and secured from underneath with a washer and nut. The threaded bolt must not protrude more than 3/4 inches bey ond the tightened nut; trim the threaded portion as needed and galvanize in accordance with Section 562.
536-3.7 Steel Panels: Use straight panels to construct radii of 125 feet or greater. Use
fabricated shop -bent panels to accommodate radii of less than 125 feet.
536-3.8 Panel Slots and Holes: Use the panel’s unaltered, prefabricated slots and holes
as shown in the Standard Plans . Do not drill, punch, ream, or otherwise alter the prefabricated slots and holes, except when creating new post bolt slots fo r reduced post spacing (quarter spacing) and adjusting post spacing to avoid structure edge conflicts as shown in the Standard Plans. Where required, punch new post bolt slots to the dimensions given in the Standard Plans , spaced no closer than 4 inches me asured edge to edge from an existing slot. Galvanize new punched slots per Section 562.
536-3.9 Barrier Delineators: Mount barrier delineators on top of the guardrail post by
adhesive or mechanical means per the manufacturer’s recommendations.
536-3.10 End Delineators: Install the retroreflective sheeting on the approach face
(nose) of approach terminals, trailing anchorages, and controlled release terminal (CRT) end treatments where indicated in the Standard Plans . Mount the retroreflective sheeting ver tically centered on the approach face by adhesive or mechanical means per the manufacturer’s recommendations. Retroreflective sheeting must be a minimum 8 inches in height with a minimum area of 160 square inches for approach terminals and trailing anchora ges and 240 square inches for CRT end treatments.
536-3.11 Rub Rail: Treat field drilled holes in accordance with Section 562.
Rub rail must terminate at the nearest post outside of the rub rail stationing range indicated in the Plans.
536-3.12 Pipe Ra il: Treat field drilled holes in accordance with Section 562.
Pipe rail must terminate at the nearest post outside of the pipe rail stationing range indicated in the Plans.
536-3.13 Existing Guardrail: Stockpile guardrail, if specified, within the right -of-way at
a location approved by the Engineer. Dispose of all remaining guardrail not specified for stockpiling.
536-3.14 Approach Terminal Assemblies: Install approach terminal assemblies as
specified in the Plans and APL drawings and in accordance with the geometry and adjacent grading of the Standard Plans . The APL number must be permanently marked on each assembly at a readily visible location using legible lettering at least 3/4 inch in height. If the Plans call for an approach terminal assembly and do not identify the specific system to be used, the contractor has the option to construct any Department -approved approach terminal assembly identified on the APL that meets the applicable test criteri a, subject to the conditions identified in the Plans or the APL drawings. FY 2023-24 Return to Table of Contents
536-4 Acceptance.
Acceptance of material s and installation of guardrail will be based on conformance with the requirements of this Section and visual inspection by the Engineer.
536-5 Method of Measurement.
536-5.1 Guardrail: The quantity paid for will be the plan quantity, in linear feet,
constructed, in place and accepted. The length of guardrail is measured end -to-end following the centerline of the panels, between the begin/en d guardrail stations as defined in the Standard Plans and the Plans, including the full lengths of the adjoining end treatments and transition connections to rigid barrier.
536-5.2 Rub Rail: The quantity paid for will be the plan length, in linear feet,
constructed, in place and accepted.
536-5.3 Pipe Rail: The quantity paid for will be the plan length, in linear feet,
constructed, in place and accepted.
536-5.4 Special Guardrail Post: The quantity paid for will be the number of each,
constructed, in pla ce and accepted. Special guardrail posts include deep posts, special steel posts, encased posts, and frangible leave -outs as defined in the Standard Plans and indicated in the Plans.
536-5.5 Transition Connection to Rigid Barrier: The quantity paid for wi ll be the
number of each, constructed, in place and accepted.
536-5.6 Guardrail Post Replacement: The quantity paid for will be the number of each,
replaced.
536-5.7 Guardrail End Treatment: The quantity paid for will be the number of each
type as design ated, constructed, in place, and accepted. Guardrail end treatment types may include approach terminals, trailing anchorages, CRT end treatments, and double faced approach terminals as defined in the Standard Plans .
536-6 Basis of Payment.
536-6.1 Guardra il: Price and payment will be full compensation for all work specified
under this Section, except those items specified in 536 -6.2 through 536 -6.7. Price and payment include furnishing and installing posts, panels, barrier delineators, offset blocks, and all other materials as defined in the Plans and the Standard Plans . The price and payment will include any reduced post spacing, nested panels, shop-bent panels, end unit panels, and CRT posts as required in the Plans. The type of guardrail specified will be that which comprises the guardrail run between end treatments and transition connections to rigid barrier (including, but not limited to, w-beam general, w -beam double face, w -beam low -speed, modified thrie -beam). For guardrail systems wi th direct connections between end treatments and transition connections to rigid barrier, the type of guardrail specified will be w -beam for single face guardrail applications or double faced for double face guardrail applications.
536-6.2 Rub Rail: Price and payment will include all components specified in the Plans
and Standard Plans .
536-6.3 Pipe Rail: Price and payment will include all components specified in the Plans
and Standard Plans . Pipe rail will be shown and tabulated in the Plans for the cond ition that steel posts are installed at the indicated pipe rail location, however the pipe rail is not required if the timber post option is selected and installed at the indicated pipe rail location. FY 2023-24 Return to Table of Contents
536-6.4 Special Guardrail Post: Price and payment will include all costs for furnishing
and installing special guardrail posts that are in addition to the cost of items included in 536 -6.1, where special guardrail posts are installed instead of standard posts.
536-6.5 Transition Connection to Rigid Barrier: Price and payment will include all
costs for furnishing and installing all hardware for approach or trailing transition connections to rigid barrier per the Standard Plans that are in addition to the cost of items included in 536 -6.1. This includes costs f or the concrete transition block or alignment curb where shown in the Standard Plans and barrier delineators for existing post and beam bridge railings. This item applies for connections to concrete barrier, concrete pier protection barrier, and concrete o r metal bridge traffic railing, including thrie -beam retrofits.
536-6.6 Removal of Existing Guardrail: Price and payment will include all labor and
equipment required for removal and disposition of the existing guardrail as specified in the Plans. No addi tional payment will be made for the removal of transition connections, double faced guardrail, thrie -beam guardrail, nested panels, pipe rail, rub rail, or end terminals.
536-6.7 Guardrail End Treatment: Price and payment will include all costs for
furnishing and installing all guardrail end treatment assemblies specified in the Plans that are in addition to the cost of items included in 536 -6.1.
536-6.8 Payment Items: Payment will be made under:
Item No. 536 - 1- Guardrail - per foot. Item No. 536 - 5- Rub Rail - per foot. Item No. 536 - 6- Pipe Rail - per foot. Item No. 536 - 7- Special Guardrail Post - each. Item No. 536 - 8- Transition Connection to Rigid Barrier - each. Item No. 536 - 73- Removal of Existing Guardrail - per foot. Item No. 536 - 85- Guardrail End Treatment - each. FY 2023-24 Return to Table of Contents SECTION 538 RESETTING GUARDRAIL
538-1 Description.
Remove the existing guardrail system and reinstall using new and reusable components, at the locations shown in the Plans. Construct the reset guardrail in accordance with the Standard Plans using new and reusable components, excluding components defined as non -reusable in this Section. Furnish and install end treatment assemblies, approac h transition connections to rigid barrier, trailing end transition connections to rigid barrier, and bridge anchorage assemblies as required by the Plans.
538-2 Materials.
538-2.1 Planned Non -reusable Components: The following items are considered
planned non-reusable components and must be replaced with new components:
538-2.2 Unforeseen Non -reusable Components: During construction operations, the
Engineer may deem other existing components, excluding planned non -reusable components, as unacceptable for re -use. Such components are considered unforeseen non -reusable components and require replacement with new components. Unforeseen non -reusable components will be compensated in accordance with 4 -4. Components damaged during construction operations are not considered unforeseen non -reusable components and must be replaced with new components at no cost to the Department.
538-3 Construction Methods.
Construct the reset guardrail in accordance with Section 536. If the reset guardrail is to be placed in t he same location as the previous installation, do not use the previous installation’s in -ground post holes. Place the reset posts at the approximate midspan location of the previous installation. Backfill and thoroughly tamp the unused, in - ground holes at the previous post locations. To accommodate the new post locations, field punch new post bolt slots in the reusable guardrail panels where needed. Meet the dimension and treatment requirements of the Standard Plans and Section 536.
538-4 Method of Measure ment.
The quantities paid for will be the plan length quantity, in linear feet, constructed, in place and accepted. FY 2023-24 Return to Table of Contents