513TEMPORARY BRIDGES

IL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 428–430 Save this section

Ask about Section 513

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Temporary Bridges Art. 513.03

b.Driving Piles. This work will be paid for at the contract unit price per foot (meter) for DRIVING PILES.
c.Extensions. Extensions for precast concrete and precast, prestressed concrete piles will be paid for according to Article 109.04.
d.Unplanned Splices. When the driven lengths exceed the estimated lengths specified in the plans, additional field splices for metal shell, steel, and timber piles required to provide those lengths will be paid for according to

Article 109 — 04.

e.Test Piles. Furnishing and driving test piles will be paid for at the contract unit price per each for TEST PILE, of the type specified. Driving test piles beyond the furnished test pile length will be paid for according to

Article 109 — 04.

f.Static Pile Load Tests. This work will be paid for at the contract unit price per each for PILE LOAD TEST.
g.Pile Shoes. The furnishing and installing of pile shoes, including those for test piles driven in production locations, will be paid for at the contract unit price per each for PILE SHOES.
h.Redriving of Piles. The redriving of piles to check for a gain in nominal driven bearing as specified in Article 512.11 will be paid for according to

Article 109 — 04.

i.Drilling and Setting Piles. The drilling and setting of piles will be paid for at the contract unit price per cubic foot (cubic meter) for DRILLING AND SETTING PILES (IN SOIL) or DRILLING AND SETTING PILES (IN ROCK). SECTION 513. TEMPORARY BRIDGES

513.01 Description. This work shall consist of the construction of temporary

bridges, their maintenance in a safe condition for traffic, and their removal and disposal.

513.02 Design. If complete plans are not furnished by the Department, the

details of design, materials to be used, sizes, spacing, and arrangement of members shall be determined by the Contractor. The highway loading, roadway width and overall length or waterway opening shall be as specified on the plans. The temporary bridge shall be designed according to the AASHTO LRFD Bridge Design Specifications. Temporary bridge plans furnished by the Contractor shall be sealed by an Illinois licensed Structural Engineer.

513.03 Materials. All materials shall be according to Division 1000, except as

modified herein. Used materials, except for anchor bolts, reinforcement bars, hardware for timber construction, and high strength bolts may be incorporated into the construction of temporary bridges provided those materials are in sound condition Art. 513.03 Temporary Bridges and suitable for the purpose intended. All materials shall meet the approval of the Engineer as to quality and suitability for the use intended. The outer bark shall be removed from piles in temporary bridges at points where bracing or backing is attached; otherwise, the requirements of Article 1007.08(c) concerning the removal of bark shall not apply. Galvanizing of high strength bolts, anchor bolts, and hardware for timber construction will not be required. Epoxy coating for reinforcement bars for cast-in-place construction will not be required. CONSTRUCTION REQUIREMENTS

513.04 Excavation and Backfill. Excavation and backfill shall be according

to Section 502.

513.05 Piling and Timber. Except as modified herein, all work involving

timber piles shall be according to the applicable portions of Sections 507 and 512. The requirements for treatment of piling, treatment of holes and pile tops, and metal coverings for piles shall not apply. Timber construction shall be according to the applicable portions of Section 507. The requirements regarding the use of treated timber shall not apply. Timber shall be either rough or surfaced. Countersinking will not be required, except in the vertical roadway face of wheel guards and under longitudinal floor planks.

513.06 Other Construction. Cast-in-place concrete shall be according to

Section 503. New precast concrete members shall be according to the applicable portions of Section 504. The use of used precast concrete members shall be limited to the configuration and intent contemplated for the original design of the member. No cutting or splicing of used precast members will be allowed. The furnishing and erecting of structural steel shall be according to Section 505, except no painting of structural steel will be required. Reinforcement bars shall be according to Section 508. Metal railings shall be according to Section 509.

513.07 Maintenance. The Contractor shall maintain such temporary bridge in

good condition. All labor and materials required for such maintenance, including the repair of any damage caused by traffic, shall be furnished by the Contractor.

513.08 Removal. After the need to maintain traffic on the temporary bridge

has ceased to exist, it shall be removed and disposed of according to Article 501.04. No excavation or other material will be allowed to remain in the stream channel.

513.09 Method of Measurement. Rock excavation will be measured for

payment according to Article 502.12.

513.10 Basis of Payment. This work will be paid for at the contract unit price

per each for TEMPORARY BRIDGE COMPLETE. Rock excavation will be paid for according to Article 502.13. Drilled Shafts Art. 516.02 SECTION 514. RESERVED SECTION 515. NAME PLATES

515.01 Description. This work shall consist of the furnishing and installing of

name plates.

515.02 Materials. Name plates shall be made of brass, bronze, or other

material as provided by the plans. CONSTRUCTION REQUIREMENTS

515.03 General. The general features of design; the type, size, and spacing

of letters and figures; the items of information to be shown on all name plates for structures constructed under a given contract; and the arrangement of these items shall be as shown on the plans. The surface of the name plate shall be polished.

515.04 Installation. Installation of name plates shall be as follows.

a.Concrete Structures. On concrete structures, the name plate shall be embedded in the concrete and fastened by means of four brass or bronze bolts with countersunk heads, or four lugs cast integral with the plate. The bolts or lugs shall project at least 3 in. (75 mm) into the concrete beyond the back of the plate.
b.Steel Truss. On steel truss spans, the plate shall be fastened on the steel member at the fabricating shop by brazing around the entire perimeter of the plate.
c.Steel Rails. On steel rails, the plate shall be bolted on with four, 3/8 x 1 in. (M10 x 25 mm) stainless steel or brass cap screws that are self-tapping or drilled and tapped in the field.

515.05 Basis of Payment. This work will be paid for at the contract unit price

per each for NAME PLATES. SECTION 516. DRILLED SHAFTS

516.01 Description. This work shall consist of constructing drilled shaft

foundations.

516.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Portland Cement Concrete (Note 1) ....................................................... 1020
b.Reinforcement Bars ........................................................................... 1006.10
c.Grout (Note 1) (Note 2) ...................................................................... 1024.01
d.Permanent Steel Casing ................................................................ 1006.05(d)

TEMPORARY BRIDGES in other states

Get an email when 513 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 428–430 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 513 — TEMPORARY BRIDGES. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.