2535.1DESCRIPTION
This Work consists of constructing a curb using bituminous Material.
2535.2MATERIALS
Use the same type of bituminous mixture for the curb as the type specified for the pavement wearing course in accordance with 2360, “Plant Mixed Asphalt Pavement.”
2535.3CONSTRUCTION REQUIREMENTS
A Tack Apply a tack coat as specified in 2357, “Bituminous Tack Coat,” on the pavement wearing course beneath the curb. B Equipment Place bituminous curb using an automatic curb machine that shapes and compacts the mixture to the profile shown on Standard Plate 7065. The Contractor may only manually place the bituminous curb in locations unreachable by the machine, if approved by the Engineer. C Finishing Place curb uniform in appearance and texture, and true to line and grade.
2535.4METHOD OF MEASUREMENT
The Engineer will measure bituminous curb by length along the face of the curb at gutter line.
2535.5BASIS OF PAYMENT
The Contract linear foot price for Bituminous curb includes the cost of construction and providing the bituminous mixture. The Department will pay for Bituminous curb on the basis of the following schedule: Item No. Item Unit
2535.503 Bituminous Curb linear foot