Section 1735
17-29 1734 -3 Measurement and Payment
Remove Existing Communications Cable will be measured in horizontal linear feet of existing communications cable removed and accepted. Payment will be in linear feet. Sag, vertical segments or spare seg ments of communications cable will not be paid as these distances will be incidental to the removal of existing communications cable. No additional measurement will be made for multiple cables being removed from the same conduit or same pole. Where multiple adjacent conduits exist (each containing multiple cables), each conduit will be measured and paid separately. No payment will be m ade for cable that cannot be removed and is abandoned in place. No measurement will be made of the removal of messenger cable, pole attachment hardware and junction boxes, as these will be incidental to removing existing communications hardware. Payment wi ll be made under: Pay Item Pay Unit Remove Existing Communications Cable Linear Foot SECTION 1735 CABLE TRANSFERS 1735 -1 DESCRIPTION Remove and reinstall existing communications cable for pole relocations. 1735 -2 MATERIAL Refer to Division 10 Item Section Pole Line Hardware 1098 -7 1735 -3 CONSTRUCTION METHODS During project, transfers of existing communications cable to new poles may be required. Perform transfers as directed by the Engineer. Remove existing cables from pole to be r emoved and reinstall these cables and any existing attachment hardware on new pole. Remove all communications hardware from existing pole. Furnish and install any new attachment hardware as required. 1735 -4 MEASUREMENT AND PAYMENT Cable Transfer will be measured and paid as the actual number of cable transfers with attachment hardware to new poles furnished, installed and accepted. Payment will be made under: Pay Item Pay Unit Cable Transfer Each 1736 -1 DESCRIPTION Furnish and install a spread spectrum radio system (900 MHz Serial or 900 MHz Serial /Ethernet) with all necessary hardware and signage in accordance with the plans and specifications to provide a data link between field devices (i.e. traffic signal controllers, dynamic message signs, etc.). Provide a radio system with a bi-directional, full duplex communications channel between 2 “line -of-sight” antennas using license free, spread spectrum technology operating in the 902- 928 MHz frequency band.
17-30 Furnish material and workmanship conforming to the NEC, the NESC, UL or a third- party
listing agency acc redited by the North Carolina Department of Insurance and all local safety laws. Comply with all regulations and codes imposed by the owner of affected utility poles. 1736 -2 MATERIAL Refer to Division 10. Item Section Pole Line Hardware 1098 -7 Retroreflective Sheeting 1092 -2 Signs and Hardware 1092 -1 Spread Spectrum Radio 1098 -19 Wire 1091 -2 Furnish material, equipment and hardware under this section that is pre -approved on the ITS and Signals QPL available on the Department’s website. 1736 -3 CONSTRUCTION METHODS
17-31 Do not exceed t he one inch bend radius of the coaxial cable as it traverses from the cabinet
to the antenna assembly. Connect the lightning arrestor to the coaxial cable in the equipment cabinet. Properly ground and secure the arrestor in the cabinet. Permanently label all cables entering the cabinet. Ensure the power supply for the radio system is not connected to the GFCI receptacle circuit located in the cabinet. Place a copy of all manufacturer equipment specifications and instruction and maintenance manuals in t he equipment cabinet. At certain locations it may be necessary to integrate the radio system with a fiber -optic system. Follow the details shown in the fiber -optic splice plans.