SECTION 414: COLD MILLING

414.1 Description

This Work consists of cold milling pavement surfaces and remov ing, hauling, and disposing of cold-milled Materials.

414.2 MATERIALS—Reserved

414.3 Construction Requirements

414.3.1 Equipment

The Contractor shall use a cold milling machine that accuratel y controls the cross section depth and cross-slope within a 1/4 inch tolerance, unless other wise shown in the Contract. The Equipment must control cross section grade by using an inde pendent grade control or a 40 ft minimum external reference. The Contractor shall use Equipment that provides an enclosed c utting area and dust control. The milling Equipment must pro duce a uniform milled surface. The Contractor shall maintain the Equipment’s teeth and spacing to produce the desir ed texture. The Contractor shall immediately replace brok en, damaged, or excessively worn teeth.

414.3.2 Operations

The Contractor shall cold mill the existing pavement surface i n accordance with the Contract. The Contractor shall adjust the specified depth in maximum inc rements of 1/4 inch, as directed by the Project Manager. The Contractor shall minimize gouges, grooves, and ridges to create a uniform surface without deviations greater than 1/2 inch when measured with a ten

10.ft straightedge. The Contractor shall keep the milled sur face free of loose Material. The Contractor shall remove the cold milled pavement Material and d ispose of the surfacing Material in an environmentally Acceptable manner or stockpile i n accordance with the Contract. The Contractor shall perform milling operations adjacent to th e traveled lanes in accordance with the Department’s Administrative Directive (AD) – 241, “Drop off Guidelines” current at time of bid. The Contractor shall not expose the mi lled surface to traffic for more than 48 hours before beginning further surface operations unles s otherwise specified in the Contract. The Contractor shall remove any standing water. The Contractor shall correct unacceptable Work and damage to a djacent Structures caused by the operations and ob tain Project Manager’s approval of corrected Work. Repair damage to the milled surface, as directed by the Project Manage r. If the Project Manager determines that damage is due to conditions beyond the Contract or’s control, the Department will pay for correcting t he damage as Extra Work. The Contractor may use cold milled pavement Material as RAP or recycled concrete (RC) in accordance with the Contract.

414.4 Method of Measurement

Section 414: Cold Milling Page 193 The Department will measure cold milling to the nearest 1/4 in ch, if by the square yard- inch.

414.5 Basis of Payment

Pay Item Pay Unit Cold Milling (Asphalt) Square Yard-Inch or Square Yard Cold Milling (Concrete) Square Yard-Inch or Square Yard Patching of Milled Surface T o n

414.5.1 Work Included in Payment

The Department will consider as included in the payment for th e pay item(s) listed in this section and will not measure or pay separately for the followin g Work: 1. Water (hauling, supplying etc.); 2. Hauling & Stockpiling cold millings at Contract designated l ocations: a. Cross-sections shall be performed and sealed by a licensed N M Professional Surveyor of designated locations and provided to the Project Ma nager; 3. Debris cleaning & sweeping; 4. Disposal of cold millings no t to be retained by the Departme nt; 5. Dispose of removed asphalt pav ement Materials, not including minor sweepings, belonging to the Department using one (1) or more of the follow ing methods: a. Recycling and mixing it into Base Course, Subgrade or HMA of the new Roadway, with approval of the Project Manager; b. Break down asphalt surfacing removed from the Project to a n ominal two (2) inch size, or smaller, haul and stockpile the Material at a loc ation approved by the Project Manager or as i ndicated in the Plans; or c. If the Material is to be permanently placed within the Shoul der or Median, it shall be treated by using one (1) of the following methods: i. Machine-compacted; or ii. Sealed with an approved rejuvenating agent. Section 415: Pavement Surface R estoration Page 194

Source: New Mexico Standard Specifications for Highway and Bridge Construction, 2019 Edition. Pages 00 of 974.

Ask about this section

Scoped to New Mexico 2019 NMDOT Standard Specifications for Highway & Bridge Construction, Section 414 — Cold Milling. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.