00210Mobilization

OR · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 223–223 Save this section

Ask about Section 00210

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

00210.90 157 PART 00200 - TEMPORARY FEATURES AND APPURTENANCES Description

00210.00 Scope - This Work consists of operations and preparatory Work necessary to become

ready to perform the Work or an item of Work . Constr uction

00210.40 Mobilization - Mobilization includes, but is not limited to, the following:

• Moving personnel, Equipment , supplies, and Incidental s to the Project Site. • Establish ing offices, buildings, and other facilities necessary for Work on the Proj ect. • Perform ing other Work and operations or incur costs as necessary before beginning Work on the Project. Obtaining and maintaining access to Doc Express®, and using Doc Express® to submit documents according to 00170.08. Measurement

00210.80 Measurement - No measurement of quantities will be made for Work performed under this

Section. Payment

00210.90 Payment - Payment for mobilization will be made at the Contract lump sum amount for the

item "Mobilization". The am ounts paid for mobilization in the Contract progress payment will be based on the percent of the original Contract A mount that is earned from other Contract items, not including advances on Materials, and as follows: • When 5 percent is earned, either 50 percent of the amount for mobilization or 5 percent of the original Contract A mount, whichever is the least. • When 10 percent is earned, either 100 percent of mobilization or 10 percent of the original Contract Amount, whichever is the least. • When all Work is completed, amount of mobilization exceeding 10 percent of the original Contract Amount. This schedule of mobilization progress payments will not limit or preclude progress payments otherwise provided by the Contract. When the Contract Schedule of Items does not indicate payment for mobilization, no separate or additional payment will be made for mobilization. Payment will be included in payment made for the appropriate items under which this Work is required. No separate or additional payment will be m ade for any costs associated with obtaining and maintaining access to Doc Express® or the use of Doc Express®.

Get an email when 00210 changes

Oregon revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 223–223 of 1,268. View official source ↗

Ask about this section

Scoped to Oregon 2024 Standard Specifications for Construction, Section 00210 — Mobilization. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.