629

6-117SECTION 629 – WATER SYSTEMS

629.01DESCRIPTION . This work shall consist of the construction or reconstruction of water lines and

appurtenances.

629.02MATERIALS . Materials shall meet the requirements of the following subsections:

Sand Borrow and Cushion ................................ ................................ ......................... 703.03 Coarse Aggregate for Concrete ................................ ................................ .................. 704.02 Granular Backfill for Structures ................................ ................................ ................. 704.08 Plastic Pipe, Flexible ................................ ................................ ................................ ..740.01 Plastic Pipe, Rigid (PVC) ................................ ................................ .......................... 740.02 Copper Tube, Seamless ................................ ................................ .............................. 740.03 Ductile Iron Pipe, Cement Lined ................................ ................................ ............... 740.05 Chlorine Solution ................................ ................................ ................................ .......742.01 Concrete shall conform to the requirements of Section 541 for Concrete, Class B, unless otherwise specified. Sleeves shall conform to the requirements of Section 625 . Crushed stone bedding shall be in accordance with Subsection 704.02 and meet the gradatio n requirements of Table 704.02 C. Ductile iron fittings shall be so -called compact or short -bodied fittings.

629.03GENERAL REQUIREMENTS . The Contractor shall not disrupt the operation of existing water

facilities without prior written approval of the Engineer. When existing underground utilities, which are not scheduled for removal or abandonment, are encountered in the excavation, they shall be adequately supported and protected from damage. Any damage to utilities shall be repaired promptly in accordance with Subsection 107.1 2 at no additional cost to the Agency. Any work associated with existing water lines or appurtenances shown on the Plans to be removed or abandoned in place will be considered incidental to the work under this section .

629

6-118The Co ntractor shall be responsible for the unloading, storing, hauling, and distribution of all materials

All such material that is damaged, destroyed, or lost during and after unloading shall be replaced at the Contractor’s expense. All pipes , pipe fittings, and accessories shall be handled to avoid shock. Pipe having factory -applied joint material shall be stacked and blocked to prevent damage to the joint material. Material not needed for immediate use shall be stored in a safe manner at locations selected b y the Contractor and approved by the Engineer. The Engineer shall approve the location of all pipes. The utility owner will provide the services of a professional engineer to oversee construction of the waterline, to ensure that state requirements are met and to sign and stamp all paperwork required by the Vermont Agency of Natural Resources , Department of Environmental Conservation , Water Supply Division . The professional engineer shall advise the Engineer, and the Engineer will provide direction to the Co ntractor.

629.04SUBMITTALS . Fabrication drawings shall be submitted in accordance with Subsection 105.06

for all water system components, including water pipe and copper tubing, fittings, valves, tapping sleeves and tapping valves, valve box alignment devices, corporation stops, curb stops with extension box, urethane insulation and all ancillary appurtenances. Manufacturers ’ technical data sheets shall be submitted for each type of pipe and fitting to be used on the project, including dimensions, specifications of material, gasket material, class and pressure rating, coatings, and linings, joint restraints, and appurtenances.

629.05EXCAVATION . Where the pipe is to be laid below the existing ground line, a trench shall be

excavated to the required depth and to a width sufficient to allow for joining of the pipe. The bedding and backfill material under and around the pipe sha ll be compacted per the applicable material specification. Where feasible, trench walls shall be vertical. The completed trench bottom shall be firm for its full length and width. Ledge rock, rocky or gravelly soil, hardpan, or other unyielding foundation material encountered at the normal grade of the pipe bed shall be removed and replaced with granular backfill for structures. The width of the pipe bed shall be equal to the inside diameter of the pipe plus 36 inches. The minimum depth shall be 12 inches b elow the pipe grade, unless otherwise shown on the Plans or directed by the Engineer. No tunneling will be permitted except with the written approval of the Engineer. Permission to tunnel will be granted only in short sections where, in the opinion of the Engineer, the pipe can be safely and properly installed and the backfill properly compacted.

629

6-119The Contractor shall conduct operations to prevent the accumulation of water, ice, and snow in

excavations or near excavated areas, and to pre vent water from interfering with the progress or quality of the work at all times. Under no conditions shall water be allowed to rise in open trenches after the pipe has been placed. Accumulated water, ice, and snow shall be promptly removed and disposed o f by pumping or other approved means. Disposal shall be carried out in a manner which will not create a hazard to public health; cause injury to public or private property, work completed or in progress, or public streets; or cause any interference in the use of streets and roads by the public. Pipes under construction shall not be used for drainage of excavations. Where pipes are to be placed in embankment fill, the excavation shall be made after the embankment has been completed to a height of 3 feet plus one pipe diameter above the designed grade of the pipe. Sheeting and bracing required for trenches shall be removed to the elevation of the pipe, but no sheeting will be allowed to be pulled, removed, or disturbed below the pipe.

629.06BEDDING FOR PIPE . Ductile iron pipe shall be laid on suitable soil and backfilled and

compacted to the centerline of the pipe with select material. Select material shall be sand, crushed stone bedding, or suitable material excavated from the trench, and free from rocks, fo reign materials, and frozen earth. Seamless copper tube shall be bedded and covered with sand borrow. Concrete cradle bedding shall be installed on approved subgrades when shown on the Plans or directed by the Engineer.

629.07LAYING PIPE . Installation of all water lines shall be in accordance with ANSI/AWWA C600,

Recommended Standards for Water Works , Recommended Standards for Wastewater Facilities , and the standards of the Vermont Drinking Water and Ground Water Protection Division. Pipe laying shall begin at the outlet end. The lower segment of the pipe shall be in contact with the shaped bedding throughout its full length. Bell or grooved ends of rigid pipes and the circumferential laps of flexible pipe shall be placed facing upstream. The long itudinal laps or seams of flexible pipe shall be at the sides. All pipes and fittings shall be carefully examined for defects, and no pipe or fittings that are known to be defective shall be laid. If any defective piece is discovered after laying, it shall be removed and replaced at the Contractor’s expense. All pipes and fittings shall be cleaned before they are laid and shall be kept clean until accepted in the completed work.

629

6-120The pipe shall be laid to conform to the lines and grades indicated on the Plans or as directed by the

Engineer. Each pipe shall be so laid as to form a closed joint with the next adjoining pipe and to bring the inverts continuously to the required grade. Each length of pipe shall be driven home against the pipe previously laid and held securely in position. Joints shall not be pulled or cramped unless permitted by the Engineer. Before any joint is made, the pipe shall be checked to ensure that a closed joint with the next adjoining pipe has been maintained and that the inverts are matched and conform to the required grade. The pipe shall not be driven down to grade by striking it. The Contractor shall take all necessary precautions to prevent flotation of the pipe in the trench. When pipe laying is not in progress, the open ends of the pipe shall be closed with temporary watertight plugs. If water is in the trench when work is resumed, the plug shall not be removed until all danger of water entering the pipe is eliminated. The use of concrete reaction blocking shall be limited to caps, tees, hydrants, and bends of 22.5° and greater. Blocking shall be placed only on the sides of each fitting in the direction of thrust and not underneath for use as a foundation or support. All other bends less than 22.5° shall be restrained by use of retainer glands at each bend and at all joints within three pipe lengths on each side of the bend. Separation of water mains and sewers shall conform to the requirements of Subsection 628.1 4.

629.08JOINING PIPE . Water pipe shall be joined in accordance with the detailed instructions of the

manufacturer. Where recommended by the manufacturer, the Contractor shall furnish coupling pullers for joining the pipe. Gasket feeler gauges shall be available for use by the pipe layer and the Engineer for checking the position of the rubber gaskets in the completed joint, if so directed by the Engineer. The electrical conductivity of the pipeline and attached services shall be maintained at all joints, couplings, valves, and fittings through the use of three brass wedges at each joint, or wi th conduction straps. No couplings shall be made at any point on the pipeline or attached services without incorporating provisions to maintain electrical conductivity. Any fittings showing a crack, and any fitting or pipe which has received a severe blow that may have caused a fracture, even though no such fracture can be seen, shall be marked as rejected and removed immediately. Water pipe shall be cut by means of a handsaw, metal -inserted abrasive wheels, or by pipe cutters with blades, not rollers, doin g the cutting. All cut ends shall be examined for possible cracks caused by cutting.

629 6-121 629.09 SETTING OF VALVES AND FITTINGS . Valves, fittings, plugs, and caps shall be set and joined to pipe in the manner specified above for laying and joining pipe. A valve box shall be provided for every valve that has no gearing or operating mechanism or in which the gearing or operating mechanism is fully protected with a gear case. The valve box shall not transmit shock or stress to the valve and shall be centered a nd plumb over the wrench nut of the valve, with the box cover flush with the surface of the finished pavement or other such level as directed by the Engineer. A masonry valve pit shall be provided for every valve that has exposed gearing or operating mecha nisms. The valve nut shall be readily accessible for operation through the opening in the manhole, which shall be set flush with the surface of the finished pavement, or such other level as specified by the Engineer. Pits shall be constructed to permit min or valve repairs and afford protection to the valve and pipe from impact where they pass through the pit walls. Mains shall be drained through drainage branches or blow -offs to dry wells from which the water can be pumped. Drainage branches, blow -offs, air vents, and appurtenances shall be provided with valves and shall be located and installed as shown on the Plans.

Drainage branches or blow-offs shall not be connected to any sewer, submerged in any stream, or be

installed in any other manner that will permit back siphonage into the distribution system.

All dead ends of new mains shall be closed with plugs or caps and shall be equipped with suitable blow-

off facilities.

Corporation stops shall, in all instances, be tapped into the main on the side in a horizontal position or in

such a position as will provide a minimum of 5 feet of cover over the connecting service line. The main

shall be tapped by skilled workers and the stop installed in accordance with the manufacturer’s

recommendations at the locations shown on the Plans or as directed by the Engineer. The stops may be

installed later, at which time the main may be tapped under pressure. All defective taps shall be repaired

or replaced at the Contractor’s expense.

Prior to installation, the Contractor shall thoroughly clean all exposed portions of any valves, removing

all labels and all traces of foreign substance using only a cleaning solution approved by the manufacturer

of the valve and being careful to avoid all damage to surfaces and coatings.

629.10SETTING OF HYDRANTS. Hydrants shall be located as shown on the Plans or as directed so as

to provide complete accessibility and minimize the possibility of damage from vehicles or injury to

pedestrians.

629

When placed behind the curb, the hydrant barrel shall be set so that no portion of the pumper or hose

nozzle cap is less than 6 inches or more than 12 inches from the gutter face of the curb.

When set in the area between the curb and the sidewalk, or between the sidewalk and the property line,

no portion of the hydrant or nozzle cap shall be within 6 inches of the sidewalk.

All hydrants shall stand plumb and shall have their nozzles parallel with, or at right angles to, the curb,

with the pumper nozzle facing the curb, except hydrants having two hose nozzles 90° apart shall be set

with each nozzle facing the curb at an angle of 45°. Hydrants shall be set to the established grade, with

nozzles at least 12 inches above the ground, as shown or as directed by the Engineer.

Each hydrant shall be connected to the main with a 6 inch or larger branch controlled by an independent

gate valve, unless otherwise specified.

If, as determined by the Engineer, the waste opening of any hydrant will be below the normal sub-surface

water elevation, the waste opening shall be securely plugged and no drainage pit will be required.

Wherever a dry-barrel hydrant is set in soil that is pervious, drainage shall be provided at the base of the

hydrant by placing coarse gravel or crushed stone mixed with coarse sand, from the bottom of the trench

to at least 6 inches above the waste opening in the hydrant, and 12 inches around the elbow. No drainage

system shall be connected to a sewer.

Wherever a dry-barrel hydrant is set in clay or other impervious soil, a drainage pit 24 inches wide × 24

inches long × 36 inches deep shall be excavated below each hydrant and backfilled with coarse gravel or

crushed stone mixed with coarse sand, and compacted under and around the elbow of the hydrant to a

level of 6 inches above the waste opening. No drainage pit shall be connected to a sewer.

629.11ANCHORAGE. The bowl of each hydrant shall be well braced against unexcavated earth at the

end of the trench with stone slabs or concrete backing, or the hydrant shall be tied to the pipe with suitable

metal tie rods, clamps, or retainer glands as shown on the Plans or directed by the Engineer.

All plugs, caps, tees, and bends, unless otherwise specified, shall be provided with a reaction backing, or

movement shall be prevented by attaching suitable metal rods or clamps as shown or specified.

Concrete reaction backing shall be placed between solid ground and the fitting to be anchored; the area of

bearing on the pipe and on the ground in each instance shall be that shown on the Plans or directed by the

Engineer. The backing shall, unless otherwise shown or directed, be placed in such a manner as to contain

the resultant thrust forces in such a way that the pipe and fitting joints will be accessible for repair.

A metal harness of tie rods, clamps, or retainer glands of adequate strength to prevent movement may be

used instead of concrete backing, as directed by the Engineer. Steel rods or clamps shall be galvanized or

otherwise rust proofed, or shall be painted as shown in the Plans or directed by the Engineer.

629

629.12PRESSURE AND LEAKAGE TESTS. Except as otherwise directed, all pipelines shall be tested

Pipelines laid in excavation or bedded in concrete shall be tested prior to field painting. Pipe to be insulated

shall be tested prior to installing insulation.

The Contractor shall furnish all gauges, testing plugs, caps, and all other necessary equipment and labor

to perform leakage and pressure tests in sections of an approved length. Each valved section or a maximum

length of 1,000 feet of pipe shall be tested. The Contractor shall provide and bear the costs of any

additional taps to the waterline necessary to perform the pressure and leakage test between valves.

All water required for testing shall be potable. All testing shall be conducted in the presence of the

Engineer.

The Contractor shall make the necessary provisions to tap the pipe at the high point to release all air and

shall plug the pipe after completing the test. Hydrants or blow-offs located at high points may be used for

air release instead of taps if approved by the Engineer.

For the pressure test, the Contractor shall develop and maintain for two hours, 150% of the working

pressure measured in pounds per square inch. Failure to hold the designated pressure for the two-hour

period will constitute a failure of the section tested.

The leakage test shall be performed for a duration of two hours, only after the pressure test has been

satisfactorily completed. During the leakage test, the Contractor shall measure the quantity of water

required to maintain the maximum operating pressure of the main. Leakage shall not exceed allowable

values for leakage presented in ANSI/AWWA C600, Table 6B. All testing shall be conducted in accordance

with ANSI/AWWA C600.

Should any section of pipe fail either the pressure or leakage test, the Contractor shall do everything

necessary to locate and repair or replace the defective pipe, fittings, or joints at no expense to the Agency.

If for any reason the Engineer should alter the foregoing procedure, the Contractor shall remain

responsible for the tightness of the line within the above requirements for the duration of the tests.

629.13DISINFECTING. Before being placed in service, the pipeline, valves, hydrants, etc., shall be

chlorinated in accordance with ANSI/AWWA C651. The entire procedure for chlorinating the pipes shall

be approved by the Engineer 14 calendar days prior to the time the work is performed. The location of

chlorination and sampling points will be determined by the Engineer in the field.

The general procedure for chlorination shall be to first flush out the lines until all dirty or discolored water

has disappeared, then to apply the chlorine in approved dosages through a tap at one end of the line while

water is being drawn at the other extremity of the line until the entire line contains chlorine solution. The

chlorine solution shall remain in the pipeline for a period of 24 hours.

629

Within 24 hours following the chlorination period, all treated water shall be flushed from the lines or

portions thereof at their extremities and replaced with water from the distribution system.

Special disinfecting procedures shall be used as directed by the Engineer where the above outlined method

is not practical, and when making connections to existing mains. The Contractor shall provide all

necessary apparatus, materials, and labor for disinfecting the mains and shall make the required taps for

this purpose. Disinfection of the mains shall be under the immediate direction of the Engineer during all

phases of the work.

Prior to being placed in operation for domestic use, all new portions of the system shall be flushed,

pressure tested, disinfected, and flushed again. Following this procedure, at least two water samples shall

be collected from representative sample points and sent to the Vermont Department of Health laboratory,

or another testing laboratory approved by the Vermont Department of Health, for bacteriological testing.

Passing sample results are required before the system may be placed on line for drinking. Sample bottles

shall be obtained from the same laboratory.

629.14HOUSE CONNECTIONS. Service lines disrupted within the project limits shall be repaired or

replaced as ordered by the Engineer. The actual location of each ordered house connection shall be

determined in the field by the Engineer.

All service lines shall be seamless copper water tube from the corporation stop to the curb stop. The copper

tubing shall be attached to the corporation stop and curb stop in a manner satisfactory to the Engineer.

Sufficient slack shall be left adjacent to the corporation stop and curb stop to prevent damage to the copper

tubing by movement of the pipeline.

Care shall be exercised in the placing and laying of copper tubing to be sure that the pipe does not have

kinks or lie directly on sharp stones or ledge which would cause damage to the pipe. The Contractor shall

place at least 6 inches of selected material as approved by the Engineer, adjacent to, above, and below the

tubing.

In making cuts in copper service pipe, a cutter or tool designed for tube cutting shall be used. The tubing

shall be reamed and after placing the coupling nut on the pipe, the pipe shall be flanged using a flanging

tool designed particularly for this purpose and connected. A compression fitting may also be used.

All services shall be tested for leakage and, in all instances, the corporation stops shall be left in the open

position upon completion of the installation.

629

The Contractor shall install the curb stop and the curb box at the end of the service line, usually at the

approximate property line, or as shown on the Plans and connect the stop to the water main with new

copper tubing. The curb box shall be installed vertically and centered over the operating key, with the

elevation of the top adjusted to conform to the finished grade. The Contractor shall adequately support the

curb box during backfilling to maintain its vertical alignment. The Contractor shall also ensure that the

curb box does not rest on the curb stop owner’s services and furnish any adapters or special couplings

needed for these connections.

Any necessary piping from the curb stop to the existing service shall match the existing service line, unless

otherwise directed by the Engineer. If no service exists, the Contractor shall furnish a curb stop for

connection to a copper service line.

Iron pipe threads shall be supplied under the tube nuts of curb stops and corporation stops.

629.15BACKFILLING

(a)General Requirements. Immediately prior to backfilling, all debris, forms, and similar materials

shall be removed from the excavation. Backfilling shall not be done in freezing temperature, with

frozen materials, or when materials already placed are frozen.

(b)Pipe Bedding Area. Prior to laying the pipe, bedding material shall be placed to the limits of the

excavation and to a depth beneath the pipe as specified. This material shall be sand, gravel, or

crushed stone and shall not contain large lumps or stones larger than 1 inch in diameter. The

Engineer may direct the use of material meeting the requirements for granular backfill for

structures. As the pipe is laid, bedding material shall be extended to the spring line of the pipe and

leveled along the width of the trench.

The pipe installation shall be inspected and approved by the Engineer before being covered.

(c)Pipe Envelope Area. The pipe envelope consists of selected suitable material placed from the

spring line of the pipe to a depth of 12 inches over the top of the pipe. The material shall be

carefully placed and spread over the width of the trench and compacted using an approved tamper.

The Contractor shall take necessary precautions during placement and compaction of the bedding

and pipe envelope materials to prevent either damage to or displacement of the pipe.

629

(d)Above Envelope Area. Unless otherwise shown on the Plans, material used for backfilling trenches

above the envelope area shall be suitable material that was removed during excavation, or obtained

from borrow, and when compacted shall make a dense stable fill. The material shall not contain

vegetation, porous matter, or stones larger than 6 inches in the widest dimension.

If additional material is required, it shall be furnished from approved sources.

Backfill material shall be evenly spread and compacted in lifts not more than 6 inches thick or as

approved by the Engineer. Previously placed or new material shall be moistened by sprinkling, if

required, to ensure proper bond and compaction and shall conform to the requirements of

Subsection 203.11(d).

When compacting backfill, care shall be taken that stones and lumps shall not become nested and

that all voids between stones shall be completely filled with fine material.

No compacting shall be done when the material is too wet to be compacted properly. If the material

is too wet, the work shall be suspended until the previously placed and new materials have dried

out sufficiently to permit proper compaction, or until other precautions are taken as necessary to

obtain proper compaction.

Backfill material shall be compacted to the maximum dry density percentage specified in Table

A and the in-place moisture content shall be not more than 2% above the optimum moisture

content, as determined by AASHTO T 180, Method C.

TABLE 629.15A – MAXIMUM DRY DENSITY FOR BACKFILL

Backfill Location Maximum Dry

Density

Around all structures, under roadway

paving, shoulders, and embankments 95%

All other areas 90%

629.16TRANSFER OF EXISTING SYSTEM TO NEW SYSTEM. The Contractor shall maintain the

existing water service during construction of the new water distribution systems and during the connection

of the new system to the existing system. The Contractor shall submit to the system owner, and where

required, to the Vermont Drinking Water and Ground Water Protection Division, a detailed construction

schedule and procedure for transferring service from the existing system to the new system and shall

receive approvals of the submittal prior to beginning work on the system.

629

Prior to making the transfer, the Contractor shall notify the owner and the Engineer 3 calendar days in

advance, in writing, that the system is ready to be transferred.

After the new connection is made, the Contractor shall divert the water to the new water main, disinfect

the system, transfer affected individual service lines to the new water main, and abandon the existing

system as shown on the Plans or as directed by the Engineer.

629.17METHOD OF MEASUREMENT. The quantity of Crushed Stone Bedding to be measured for

payment will be the number of cubic yards of material placed in the complete and accepted work within

the confines of the limits shown on the Plans or as directed by the Engineer.

The quantity of Seamless Copper Water Tube; Seamless Copper Water Tube, All-Inclusive; Plastic Water

Pipe, Flexible; Plastic Water Pipe, Flexible, All-Inclusive; Plastic Water Pipe, Rigid; Plastic Water Pipe,

Rigid, All-Inclusive; Ductile Iron Water Pipe, Cement Lined; and Ductile Iron Water Pipe, Cement Lined,

All-Inclusive of the size specified to be measured for payment will be the number of linear feet of the size,

type, and class specified installed in the complete and accepted work, as measured along the flow line of

the pipe.

The quantity of Extension Service Box and Curb Stop; Extension Service Box and Curb Stop, All-

Inclusive; Gate Valve with Valve Box; Gate Valve with Valve Box, All-Inclusive; Tapping Sleeve and

Valve with Valve Box; Tapping Sleeve and Valve with Valve Box, All-Inclusive; Adjust Elevation of

Valve Box; Blow-Off Assembly; Blow-Off Assembly, All-Inclusive; Permanent Manual Air Release;

Permanent Manual Air Release, All-Inclusive; Corporation Stop; Corporation Stop, All-Inclusive;

Hydrant; Hydrant, All-Inclusive; Relocate Hydrant; Remove Hydrant; and Expansion Assembly to be

measured for payment will be the number of units of each size and type specified installed in the complete

and accepted work.

The quantity of Transfer to New System, Water, All-Inclusive to be measured for payment will be on a

lump sum basis in the complete and accepted work.

629.18BASIS OF PAYMENT. The accepted quantity of Crushed Stone Bedding will be paid for at the

Contract unit price per cubic yard. Payment will be full compensation for furnishing, transporting,

handling, placing, and grading the material as specified and for the furnishing of all labor, tools,

equipment, and incidentals necessary to complete the work.

The accepted quantities of Seamless Copper Water Tube; Plastic Water Pipe, Flexible; Plastic Water Pipe,

Rigid; and Ductile Iron Water Pipe, Cement Lined of the size specified will be paid for at the Contract

unit price per linear foot. Payment will be full compensation for furnishing, transporting, handling,

installing, testing, and disinfecting the materials specified, including fittings and clamps; for making all

necessary connections; for furnishing and placing the concrete or other materials for reaction backing or

furnishing and installing tie rods, clamps, and restrained joints; and for furnishing all labor, tools,

equipment, and incidentals necessary to complete the work.

629

The accepted quantities of Seamless Copper Water Tube, All-Inclusive; Plastic Water Pipe, Flexible, All-

Inclusive; Plastic Water Pipe, Rigid, All-Inclusive; and Ductile Iron Water Pipe, Cement Lined, All-

Inclusive of the size specified will be paid for at the Contract unit price per linear foot. Payment will be

full compensation for furnishing, transporting, handling, installing, testing, and disinfecting the materials

specified, including temporary chlorination injection points, end caps with valves or temporary blow-offs

for flushing, for all fittings and clamps; for all tracer wire, tracer wire boxes, metallic tape and brass

wedges; for making all necessary connections; for furnishing and installing all required fittings including

elbows, tees, reducers and couplings as required, including mechanical joint retainer glands; for furnishing

and placing concrete or other materials for reaction backing or furnishing and installing tie rods, clamps,

and restrained joints including ductile iron pipe joint restraint harnesses; furnishing and installing all

sleeves, casing spacers, and insulation where required; for saw-cutting pavement and existing concrete

roadway, excavation, dewatering as required, pipe bedding and cover, pipe insulation, backfill,

compaction; and for furnishing all tools, labor, equipment and incidentals necessary to complete the work.

Excavation, including excavation support, bedding and cover, backfill operations, and disposal of

excavated material not suitable for backfill will not be paid for separately, but will be considered incidental

to the respective Contract item.

The accepted quantities of Extension Service Box and Curb Stop, Gate Valve with Valve Box, Tapping

Sleeve and Valve with Valve Box, Adjust Elevation of Valve Box, Hydrant, Relocate Hydrant, Remove

Hydrant, and Expansion Assembly will be paid for at their respective Contract unit price per each.

Payment will be full compensation for furnishing, transporting, handling, installing, and testing all

materials, including fittings and clamps; for painting hydrants and constructing drainage pits; for

furnishing and placing concrete or stone slabs for reaction backing or furnishing and installing tie rods

and clamps; for all other costs incidental to the work, including any cost involved for shipping, rental, or

royalty charges, or for manufacturer’s supervision in conjunction with the special work of installing

valves; and for furnishing all labor, tools, equipment, and incidentals necessary to complete the work.

The accepted quantities of Extension Service Box and Curb Stop, All-Inclusive; Gate Valve with Valve

Box, All-Inclusive; Tapping Sleeve and Valve with Valve Box, All-Inclusive; and Hydrant, All-Inclusive

will be paid for at their respective Contract unit price per each. Payment will be full compensation for the

furnishing, transporting, handling, installing, and testing all materials, including fittings and clamps; for

painting hydrants and constructing drainage pits; for furnishing and placing concrete or stone slabs for

reaction backing or furnishing and installing tie rods and clamps; for furnishing all labor, tools, equipment,

excavation, dewatering as required, backfill; for all other costs incidental to the work, including any cost

involved for shipping, rental, or royalty charges, or for manufacturer’s supervision in conjunction with

the special work of installing valves; and for furnishing all labor, tools, equipment, and incidentals

necessary to complete the work.

629

The accepted quantity for Blow-off Assembly will be paid for at the Contract unit price per each. Payment

will be full compensation for furnishing all labor, tools, equipment, branch piping, gate valves, fittings,

couplings, piping extensions where required, drainage aggregate, concrete thrust restraint, metal tie rods

and clamps, stainless steel screens, outlet flanges, concrete splash pads, stone fill; for painting blow-offs;

and for furnishing all labor, tools, equipment, and incidentals necessary to complete the work.

The accepted quantity for Blow-off Assembly, All-Inclusive will be paid for at the Contract unit price per

each. Payment will be full compensation for furnishing all labor, tools, equipment, including all

excavation, dewatering as required, backfill, compaction, branch piping, gate valve, fittings, couplings,

piping extensions where required, drainage aggregate, concrete thrust restraint, metal tie rods and clamps,

stainless steel screens, outlet flanges, concrete splash pads, stone fill; for painting blow-offs; and for

furnishing all labor, tools, equipment, and incidentals necessary to complete the work.

The accepted quantity of Permanent Manual Air Release will be paid for at the Contract unit price per

each. Payment will be full compensation for furnishing, transporting, handling, installing, and connecting

all components of the permanent manual air release, including the corporation stop, drilling and tapping

of the water main for the corporation stop, connecting the curb stop with rod, copper water tubing, valve

box and cover, fittings, couplings, end caps, piping extensions where required, testing, and disinfecting

the materials specified, and for furnishing all labor, tools, equipment, and incidentals necessary to

complete the work.

The accepted quantity of Permanent Manual Air Release, All-Inclusive, will be paid for at the Contract

unit price per each. Payment will be full compensation for furnishing, transporting, handling, installing,

and connecting all components of the permanent manual air release, including the corporation stop,

drilling and tapping of the water main for the corporation stop, connecting the curb stop with rod, copper

water tubing, valve box and cover, fittings, couplings, end caps, piping extensions where required, testing,

and disinfecting the materials specified, and for furnishing all labor, tools, equipment, excavation,

dewatering as required, backfill, and incidentals necessary to complete the work.

The accepted quantity of Corporation Stop will be paid for at the Contract unit price for each. Payment

will be full compensation for furnishing, transporting, handling, installing, and connecting the corporation

stop, including drilling and tapping of the water main, and for furnishing all labor, tools, equipment, and

incidentals necessary to complete the work.

The accepted quantity of Corporation Stop, All-Inclusive will be paid for at the Contract unit price for

each. Payment will be full compensation for furnishing, transporting, handling, installing, and connecting

the corporation stop, including drilling and tapping of the water main, and for furnishing all labor, tools,

equipment, excavation, dewatering as required, backfill, and all incidentals necessary to complete the

work.

629

The accepted quantity of Transfer to New System, Water, All-Inclusive will be paid for at the Contract

unit price per lump sum. Payment will be full compensation for performing all work items as directed by

the Engineer to abandon existing mains, laterals, and hydrants, closing existing valves and curb stops, for

maintaining existing water systems flows including temporary relocation of water main and service

piping; for construction, flushing, testing, and disinfection of all proposed temporary water mains,

services, and interconnections for maintenance of water service to users at all times during construction;

for preparation of a transfer of service and temporary water service plan; for performing all work

associated with final interconnections with existing water system piping; for removing existing valve

boxes and curb boxes, and removal of any existing main which conflicts with the construction necessary

to complete the transfer to the new system, including disinfection; for providing specialized labor,

materials, dewatering, and all concrete thrust restraints, for performing all exploratory excavation as

indicated in the exploratory excavation plan and per direction of the Engineer on each existing lateral

water service at the time of connection to the new water main, tools, and equipment for effecting the

transfer of systems as specified, and for furnishing all tools, labor, equipment, and incidentals necessary

to complete the work. Payment for excavatable flowable fill required to abandon existing sewer mains

and services will be made under item 541.4600.

When not using an all-inclusive item, excavation, including backfill and disposal of excavated material

not suitable for backfill, will be paid for at the Contract unit price per cubic yard as Trench Excavation of

Earth or Trench Excavation of Rock under Section 204. When material is required to replace poor

foundation material below the normal grade of the pipe, it will be paid for as Granular Backfill for

Structures.

When using an all-inclusive item, excavation including excavation support, bedding, backfill operations

and disposal of excavated material not suitable for backfill, will not be paid for separately, but will be

considered incidental to the respective Contract item. If the excavation and backfill for a water system

component is increased by more than 12 inches due to lowering the grade, changing the location, or poor

foundation material, additional excavation and backfill will be paid under the appropriate Contract items.

Payment will be made under:

Pay Item Pay Unit

00 Crushed Stone Bedding.............................................................................Cubic Yard

00 Seamless Copper Water Tube ...................................................................Linear Foot

03 Seamless Copper Water Tube, 0.75 Inch ..................................................Linear Foot

04 Seamless Copper Water Tube, 1 Inch .......................................................Linear Foot

05 Seamless Copper Water Tube, 1.25 Inch ..................................................Linear Foot

06 Seamless Copper Water Tube, 1.5 Inch ....................................................Linear Foot

07 Seamless Copper Water Tube, 1.75 Inch ..................................................Linear Foot

08 Seamless Copper Water Tube, 2 Inch .......................................................Linear Foot

629

Pay Item Pay Unit

00 Seamless Copper Water Tube, All-Inclusive ............................................Linear Foot

03 Seamless Copper Water Tube, All-Inclusive, 0.75 Inch ...........................Linear Foot

04 Seamless Copper Water Tube, All-Inclusive, 1 Inch ................................Linear Foot

05 Seamless Copper Water Tube, All-Inclusive, 1.25 Inch ...........................Linear Foot

06 Seamless Copper Water Tube, All-Inclusive, 1.5 Inch .............................Linear Foot

07 Seamless Copper Water Tube, All-Inclusive, 1.75 Inch ...........................Linear Foot

08 Seamless Copper Water Tube, All-Inclusive, 2 Inch ................................Linear Foot

00 Plastic Water Pipe, Flexible ......................................................................Linear Foot

03 Plastic Water Pipe, Flexible, 0.75 Inch .....................................................Linear Foot

04 Plastic Water Pipe, Flexible, 1 Inch ..........................................................Linear Foot

05 Plastic Water Pipe, Flexible, 1.25 Inch .....................................................Linear Foot

06 Plastic Water Pipe, Flexible, 1.5 Inch .......................................................Linear Foot

07 Plastic Water Pipe, Flexible, 1.75 Inch .....................................................Linear Foot

08 Plastic Water Pipe, Flexible, 2 Inch ..........................................................Linear Foot

00 Plastic Water Pipe, Flexible, All-Inclusive ...............................................Linear Foot

03 Plastic Water Pipe, Flexible, All-Inclusive, 0.75 Inch ..............................Linear Foot

04 Plastic Water Pipe, Flexible, All-Inclusive, 1 Inch...................................Linear Foot

05 Plastic Water Pipe, Flexible, All-Inclusive, 1.25 Inch ..............................Linear Foot

06 Plastic Water Pipe, Flexible, All-Inclusive, 1.5 Inch................................Linear Foot

07 Plastic Water Pipe, Flexible, All-Inclusive, 1.75 Inch ..............................Linear Foot

08 Plastic Water Pipe, Flexible, All-Inclusive, 2 Inch...................................Linear Foot

00 Plastic Water Pipe, Rigid ..........................................................................Linear Foot

03 Plastic Water Pipe, Rigid, 0.75 Inch .........................................................Linear Foot

04 Plastic Water Pipe, Rigid, 1 Inch ..............................................................Linear Foot

05 Plastic Water Pipe, Rigid, 1.25 Inch .........................................................Linear Foot

06 Plastic Water Pipe, Rigid, 1.5 Inch ...........................................................Linear Foot

07 Plastic Water Pipe, Rigid, 1.75 Inch .........................................................Linear Foot

08 Plastic Water Pipe, Rigid, 2 Inch ..............................................................Linear Foot

12 Plastic Water Pipe, Rigid, 3 Inch ..............................................................Linear Foot

16 Plastic Water Pipe, Rigid, 4 Inch ..............................................................Linear Foot

24 Plastic Water Pipe, Rigid, 6 Inch ..............................................................Linear Foot

32 Plastic Water Pipe, Rigid, 8 Inch ..............................................................Linear Foot

40 Plastic Water Pipe, Rigid, 10 Inch ............................................................Linear Foot

48 Plastic Water Pipe, Rigid, 12 Inch ............................................................Linear Foot

629

Pay Item Pay Unit

00 Plastic Water Pipe, Rigid, All-Inclusive ...................................................Linear Foot

03 Plastic Water Pipe, Rigid, All-Inclusive, 0.75 Inch ..................................Linear Foot

04 Plastic Water Pipe, Rigid, All-Inclusive, 1 Inch .......................................Linear Foot

05 Plastic Water Pipe, Rigid, All-Inclusive, 1.25 Inch ..................................Linear Foot

06 Plastic Water Pipe, Rigid, All-Inclusive, 1.5 Inch ....................................Linear Foot

07 Plastic Water Pipe, Rigid, All-Inclusive, 1.75 Inch ..................................Linear Foot

08 Plastic Water Pipe, Rigid, All-Inclusive, 2 Inch .......................................Linear Foot

12 Plastic Water Pipe, Rigid, All-Inclusive, 3 Inch .......................................Linear Foot

16 Plastic Water Pipe, Rigid, All-Inclusive, 4 Inch .......................................Linear Foot

24 Plastic Water Pipe, Rigid, All-Inclusive, 6 Inch .......................................Linear Foot

32 Plastic Water Pipe, Rigid, All-Inclusive, 8 Inch .......................................Linear Foot

40 Plastic Water Pipe, Rigid, All-Inclusive, 10 Inch .....................................Linear Foot

48 Plastic Water Pipe, Rigid, All-Inclusive, 12 Inch .....................................Linear Foot

00 Ductile Iron Water Pipe, Cement-Lined ...................................................Linear Foot

12 Ductile Iron Water Pipe, Cement-Lined, 3 Inch .......................................Linear Foot

16 Ductile Iron Water Pipe, Cement-Lined, 4 Inch .......................................Linear Foot

24 Ductile Iron Water Pipe, Cement-Lined, 6 Inch .......................................Linear Foot

32 Ductile Iron Water Pipe, Cement-Lined, 8 Inch .......................................Linear Foot

40 Ductile Iron Water Pipe, Cement-Lined, 10 Inch .....................................Linear Foot

48 Ductile Iron Water Pipe, Cement-Lined, 12 Inch .....................................Linear Foot

00 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive ............................Linear Foot

12 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive, 3 In. ...................Linear Foot

16 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive, 4 In. ...................Linear Foot

24 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive, 6 In. ...................Linear Foot

32 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive, 8 In. ...................Linear Foot

40 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive, 10 In. .................Linear Foot

48 Ductile Iron Water Pipe, Cement-Lined, All-Inclusive, 12 In. .................Linear Foot

629.2000 Corporation Stop .......................................................................................Each

03 Corporation Stop, 0.75 Inch ......................................................................Each

04 Corporation Stop, 1 Inch ...........................................................................Each

05 Corporation Stop, 1.25 Inch ......................................................................Each

06 Corporation Stop, 1.5 Inch ........................................................................Each

07 Corporation Stop, 1.75 Inch ......................................................................Each

08 Corporation Stop, 2 Inch ...........................................................................Each

629

Pay Item Pay Unit

629.2100 Corporation Stop, All-Inclusive ................................................................Each

03 Corporation Stop, All-Inclusive, 0.75 Inch ...............................................Each

04 Corporation Stop, All-Inclusive, 1 Inch ....................................................Each

05 Corporation Stop, All-Inclusive, 1.25 Inch ...............................................Each

06 Corporation Stop, All-Inclusive, 1.5 Inch .................................................Each

07 Corporation Stop, All-Inclusive, 1.75 Inch ...............................................Each

08 Corporation Stop, All-Inclusive, 2 Inch ....................................................Each

629.2200 Extension Service Box and Curb Stop ......................................................Each

03 Extension Service Box and Curb Stop, 0.75 Inch .....................................Each

04 Extension Service Box and Curb Stop, 1 Inch ..........................................Each

05 Extension Service Box and Curb Stop, 1.25 Inch .....................................Each

06 Extension Service Box and Curb Stop, 1.5 Inch .......................................Each

07 Extension Service Box and Curb Stop, 1.75 Inch .....................................Each

08 Extension Service Box and Curb Stop, 2 Inch ..........................................Each

629.2300 Extension Service Box and Curb Stop, All-Inclusive ...............................Each

03 Extension Service Box and Curb Stop, All-Inclusive, 0.75 In. ................Each

04 Extension Service Box and Curb Stop, All-Inclusive, 1 In. .....................Each

05 Extension Service Box and Curb Stop, All-Inclusive, 1.25 In. ................Each

06 Extension Service Box and Curb Stop, All-Inclusive, 1.5 In. ..................Each

07 Extension Service Box and Curb Stop, All-Inclusive, 1.75 In. ................Each

08 Extension Service Box and Curb Stop, All-Inclusive, 2 In. .....................Each

629.2400 Gate Valve with Valve Box ......................................................................Each

12 Gate Valve with Valve Box, 3 Inch ..........................................................Each

16 Gate Valve with Valve Box, 4 Inch ..........................................................Each

24 Gate Valve with Valve Box, 6 Inch ..........................................................Each

32 Gate Valve with Valve Box, 8 Inch ..........................................................Each

40 Gate Valve with Valve Box, 10 Inch ........................................................Each

48 Gate Valve with Valve Box, 12 Inch ........................................................Each

629.2500 Gate Valve with Valve Box, All-Inclusive ...............................................Each

12 Gate Valve with Valve Box, All-Inclusive, 3 Inch ...................................Each

16 Gate Valve with Valve Box, All-Inclusive, 4 Inch ...................................Each

24 Gate Valve with Valve Box, All-Inclusive, 6 Inch ...................................Each

32 Gate Valve with Valve Box, All-Inclusive, 8 Inch ...................................Each

40 Gate Valve with Valve Box, All-Inclusive, 10 Inch .................................Each

48 Gate Valve with Valve Box, All-Inclusive, 12 Inch .................................Each

629.2600 Tapping Sleeve and Valve with Valve Box ..............................................Each

629.2700 Tapping Sleeve and Valve with Valve Box, All-Inclusive .......................Each

629.2800 Adjust Elevation of Valve Box .................................................................Each

629

Pay Item Pay Unit

629.3000 Blow-Off Assembly ..................................................................................Each

629.3100 Blow-Off Assembly, All-Inclusive ...........................................................Each

629.3200 Permanent Manual Air Release ................................................................Each

629.3300 Permanent Manual Air Release, All-Inclusive .........................................Each

629.3400 Hydrant .....................................................................................................Each

629.3500 Hydrant, All-Inclusive ..............................................................................Each

629.3600 Relocate Hydrant ......................................................................................Each

629.3800 Remove Hydrant .......................................................................................Each

629.4000 Expansion Assembly .................................................................................Each

629.4300 Transfer to New System, Water, All-Inclusive .........................................Lump Sum

630

6-135SECTIO N 630 – UNIFORME D TRAFFI C OFFICERS AND FLAGGERS

630.0 1 DESCRIPTION . This work shall consist of furnishing uniformed traffic officers (UTOs) and flaggers for the handling of traffic in, around, and through work zones. Wherever used in this section , the term flaggers shall mean highway flaggers. UTOs and flaggers collectively are als o referred to as traffic control personnel . UTOs and flaggers shall be used to control and protect the traveling public and workers during construction operations as specified in Subsection 107.09 and as directed by the Engineer. UTOs and flaggers shall conform to the requirements of the Contract and the MUTCD . 630.0 2 GENERAL REQUIREMENTS .

(a)Standard Procedures . The Contractor shall designate a person responsible for coordinating traffic

control personnel in accordance with the reviewed for conformance traffic control plan and as directed by the Engineer. Traffic control personnel determined by the Engineer to be ineffective in their duties , as specified herein, shall be removed by the Contractor from all traffic control on the project . The Contractor shall immediately comply with the directive from the Engineer and shall suspend operations as necessary until a rep lacement, meeting the qualifications as specified herein, can be provided . Such a suspension of operations shall not be considered as a basis for a claim or an extension of time.

(b)Safety Apparel . Traffic control personnel shall wear safety apparel in accordance with the

MUTCD . Traffic control personnel deemed to have unsuitable safety apparel by the Engineer shall be considered ineffective and shall be removed. When operating during nighttime hours, between sunset and sunrise, traffic control personnel shall wear safety apparel meeting or exceeding performance Class 3 requirements of ANSI/ISEA 107 , including Class E pants or gaiters.

(c)Communication . The Contractor shall equip all traffic contro l personnel on the project with two -

way radios capable of maintaining all necessary communication within the work zone . The traffic control personnel shall use these radios to maintain communication and coordination whenever distance, noise, intervening op erations, dust, or other conditions make it difficult or impossible to communicate on a line -of-sight basis or whenever the use of two -way radios is ordered by the Engineer . The Contractor shall always keep sufficient spare batteries, parts, and complete units on the project so that no individual performing traffic control is without a working two -way radio for a period longer than 10 minutes.

Get an email when 629 changes

Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Vermont Standard Specifications for Construction, 2024 Edition. Pages 891–908 of 1,380. View official source ↗