General Provisions (00100-00999)

619Mobilization

WI · 2019 Standard SpecificationsBook pages 378378View official source ↗

Effective with the December 20 18 Letting 369 2019 Standard Spec ifications Section 619 Mobilization

619.1Description

(1)This section describes the work and operations necessary to mo ve personnel, equipment, supplies, and incidentals to the project site and to establish all of the contractor’s offices, buildings, sanitary accommodations, and other facilities necessary to work on the p roject. It also includes all other work and operations whose performance is required, or for costs nece ssarily incurred before beginning work on various items on the project site. 619.2 (Vacant) 619.3 (Vacant)619.4 Measurement (1)The department will measure Mob ilization once for the contract acceptably com pleted.

619.5Payment

(1)The department will pay for the measured quantity at the contr act unit price under the following bid item: ITEM NUMBER DESCRIPTION UNIT

619.1000 Mobilization EACH

(2)Payment for Mobilization is full compensation for supplying and providing materials, facilities, and services, and for performing all work necessary to complete this contract bid item. The department will make incremental payments as determined using department form W S6191 available at: https://wisconsindot.gov/Documents/doing-bus/eng-consultants/cnslt-rsrces/tools/estimating/ws6191.xls (3)If the contract does not include a separate Mobilization bid i tem, the work necessary for mobilization is incidental to work in cluded under other contract bid items.

Effective with the December 2018 Letting 370 2019 Standard Spec ifications Section 620 Concrete Corrugated Median and Concrete Median Nos e

620.1Description

(1)This section describes constru cting a concrete corrugated medi an or concrete median nose placed in

one course on a pr epared foundation.

620.2Materials

(1)Use materials conforming to the following:

Joint filler .................................................. ................................................................................................ 415.2.3

(2)Furnish grade A, A-FA, A-S, A-T , A-IS, A-IP, or A-IT concrete conforming to 501 as modified in 716.

Provide QMP for class II ancilla ry concrete as specified in 716.

620.3Construction

(1)The engineer will inspect concre te built under 620 for transverse cracking as specified in 415.3.17 for

ancillary concrete. Repair cracke d concrete as the engineer dir ects.

(2)Under the Concrete Corrugated M edian bid item, construct concr ete corrugated median including nose

section, placed in one course on a prepared foundation.

(3)Under the Concrete Median Blun t Nose bid item, construct a blunt concrete median nose section.
(4)Under the Concrete Median Sloped Nose bid item, construct a sl oped concrete median nose section.

620.3.1 Preparing the Foundation

(1)Prepare the foundation for the median by excavating to the lines, grade, and cross-section the plans

show and required for placing t he concrete. Remove and replace any soft or unsuitable material encountered with suitable material and thoroughly compact and f inish the foundation to a firm surface. Ensure the foundation is moist when placing the concrete. 620.3.2 Placing Concrete

(1)If forms are required, set them to line and grade and secure i n place before placing the concrete.
(2)Deposit the concrete to the pr oper depth, consolidate by spadi ng or vibrating, and strike off at the

required elevation and crown. For m the required corrugations with tools and equipment appropriate for the purpose, according to the plan details.

(3)If constructing the median adjacent to concrete pavement, plac e tie bars as specified for longitudinal

joints in concrete pavement under 415.3.7.2 .

(4)Broom finish the surface of the median unless specified otherw ise. Draw the broo m transversely

across the full width of the medi an surface with adjacent strokes slightly overlapping. Perform brooming in a way that produces corrugations uniform in appearance and not greater than 1/8 inch deep. Complete the brooming befor e the concrete’s condition causes the surface to tear or become rough from the operation. Provide a finished surface free from rough or porous areas, irregularities, and depressions resulting from improper broom handling. Ensure brooms are the quality, size, and construction appropriate for the job and operated to produce a surface finish meeting the engineer’s approval.

(5)Cure the concrete as specified in 415.3.12. If constructing concrete median during cold weather then

conform to 415.3.13 for cold weather conc reting. Conform to 415.3.14 for protection of concrete median.

(6)Remove and dispose of all excavation and surplus materials in the manner specified for in 205.3.12.

620.4Measurement

(1)The department will measure Conc rete Corrugated Median by the square foot acceptably completed,

including the nose section.

(2)The department will measure Concrete Median Blunt Nose and Con crete Median Sloped Nose by the

square foot acceptably completed, for the nose section only.

620.5Payment

(1)The department will pay for measured quantities at the contrac t unit price under the following bid

items: ITEM NUMBER DESCRIPTION UNIT

620.0100 Concrete Corrugated Median SF

620.0200 Concrete Median Blunt Nose SF

Source: Wisconsin Standard Specifications for Highway and Structure Construction, 2019 Edition. Pages 378378 of 601.