General Provisions (00100-00999)

100GENERAL PROVISIONS

WV · 2023 Standard SpecificationsBook pages 924View official source ↗

Division 100

1 SECTION 101 DEFINITION OF TERMS 101.1 -ABBREVIATIONS : Whenever the following abbreviations are used in these Specifications, Plans or Contract Documents, they are to be construed the same as the respective expressions represented: AAN American Association of Nurserymen AASHTO American Association of State Highway and Transportation Officials ADA American Disability Act ADT Average Daily Traffic ACI American Concrete Institute AISC American Institute of Steel Construction, Incorporated AISI American Iron and Steel Institute AMS Aerospace Material Specification ANSI American National Standards Institute APD Appalachian Development Highway System AREMA American Railway Engineering and Maintenance of Way Association ASCE American Society of Civil Engineers ASD Aluminum Standards & Data -Aluminum Association ASTM American Society for Testing and Materials ATSSA American Traffic Safety Services Association AWPA American Wood Preserver’s Association AWWA American Water Works Association AWS American Welding Society DBE Disad vantaged Business Enterprise FHWA Federal Highway Administration FSS Federal Specifications and Standards, General Services Administration IEEE Institute of Electronic and Electrical Engineers IPCEA Insulated Power Cable Engineers Association MASH Manual for Assessing Safety Hardware MIL Military Specification MP Materials Pro cedure MSDS Material Safety Data Sheets MUTCD Manual on Uniform Traffic Control Devices NCHRP National Cooperative Highway Research Progam NEC National Electric Code NEMA National Electrical Manufacturer's Association NFPA National Fire Protection Association NHS National Highway System NPDES National Pollutant Discharge Elimination System NTPEP National Transportation Product Evaluation Program OSHA Occupational Safety and Health Administration UL Underwriters Laboratories SAE Society of Automotive Engineers SSPC Society for Protective Coatings TCP Traffic Control Plan 2 101.2 -DEFINITIONS : Access Connection -Any roadway facility by means of which vehicles enter or leave arterial highways. Advertisements -The public announcement, as required by law, inviting bids for work to be performed, or material to be furnished. Arterial Highway -A general term denoting a highway primarily for through traffic. Auxiliary Lane -The portion of the roadway adjoining the traveled way for parking, speed - change or other purposes supplementary to through traffic movement. Award -The acceptance by the Division of a bid. Base Course -A layer or layers of specified material of designated thic kness placed on a subbase or a subgrade to support a surface course or courses. Bidder -An individual, firm, corporation, or combination thereof, acting directly or through a duly authorized representative, and prequalified according to the requirements an d provisions of the Division, submitting a bid for the proposed work. Bridge -A structure, including supports, erected over a depression or an obstruction, such as water, a highway or railway and having a track or passageway for carrying traffic or other moving loads and having a length measured along the center of roadway of more t han twenty ( 20) feet between under copings of abutments or extreme ends of openings for multiple boxes. The length of a bridge structure is the overall length measured along the line of survey stationing back to back of abutments if present, otherwise, end to end of the bridge floor, but in no case less than the total clear opening of the structure. Roadway width is the clear width measured at right angles to the longitudinal centerline of the bridge between the bottom of curbs. Calendar Day -Every day shown on the calendar. Certified Technician -A Certified Technician is an individual who has been examined by the joint Industry -Division Certification Board and deemed competent in the particular technical field for which the individual has been examined. This competency is documented by written notification and issuance of a certificate to the individual and remains in effect for a given period of time as determined by the regulations of the Board. Should any questions develop concerning the status of an individual, verification may be made through the Training section of the Personnel Division of the Division. Change Order -A general term referring to force account work orders, supplemental agreements, and work orders of the Contract. Channel -A natural or artificial water course. City, Town or District -A subdivision of the county used to designate or identify the location of the proposed work. 3 Commissioner -West Virginia Commissioner of Highways. Completion -Contractor completes all specified work sati sfactorily and executes and delivers all required documents, certificates, and proofs of compliance. Construction Limits -The physical limits of construction as described by designated lines drawn on the Plans. Contract -The written agreement between the D ivision and the Contractor covering the performance of the work, the furnishing of labor, equipment and materials, and the basis of payment. The Contract includes the invitation of bids, proposal, contract form, contract bond, specifications, supplemental specifications, special provisions, plans, notice to proceed, any change orders and supplemental agreements that are required to complete the construction of the work in an acceptable manner, including authorized extensions thereof, all of which constitut e one instrument. Contract Bond -The approved form of security, executed by the Contractor and their surety, guaranteeing completion of the work and payment of all legal debts pertaining to the construction of the project. Contract Period -The period from the specified date of commencement of work to the specified date of completion of the work, both dates inclusive, as is specified in the Contract. Contract Time -The number of work or calendar days specified in the proposal, indicating the time allowe d for the completion of the work contemplated, including authorized time extensions. Contractor -The individual, firm or corporation, party of the second part to the Contract, acting directly or through their agents, employees, or subcontractors. Control Of Access, Full -The condition where the right of owners or occupants of abutting land or other persons to access, light, air or view in connection with a highway is fully controlled by public authority. The authority to control access is exercised to give preference to through traffic by providing access connections with selected public roads only and by prohibiting crossings at grade or direct driveway connections. Control Of Access, Partial -The condition where the right of owners or occupants of abuttin g land or other persons to access, light, air or view in connection with a highway is partially controlled by public authority. The authority to control access is exercised to give preference to through traffic to a degree that, in addition to access conn ections with selected public roads, there may be some crossings at grade and some private driveway connections. County -The County or Counties of West Virginia in which the work is to be done. Culvert -Any structure not classified as a bridge which provide s an opening under the roadway. Department -West Virginia Department of Transportation. Division -West Virginia Division of Highways Divided Highway -A highway with separated roadways for traffic in opposite directions. Easement -A right acquired by one party to use land belonging to another party for a specified purpose. Embankment -The structure of soils, soils aggregate and broken rock between the embankment foundation and the subgrade. Embankment Foundation -The material below the original ground surf ace whose physical characteristics affect the support of the embankment. Employee -Any person working on behalf of the project who is under the direction of the Contractor or any subcontractor. Engineer -The State Highway Engineer of the Division, or an au thorized representative, limited by the scope of duties assigned. Equipment -All machinery and equipment, together with the necessary supplies for upkeep and maintenance, and also tools and apparatus necessary for the proper construction and acceptable completion of the work. Estimates -The official written itemization of the value of materials in place and work performed. Expressway -A divided arterial highway for through traffic with full or partial control of access and generally with grade separations a t intersections. Extra Work -An item of work not provided for in the contract as awarded, but found essential to the satisfactory completion of the Contract within its intended scope. See further 104.3. Force Account Work Order -An order signed by the Engineer or an authorized representative, directing additional work to be performed, with payments based on labor, materials used, equipment cost, plus specified percentages. Freeway -An expressway with full control of access. Frontage Street or Road -A local street or road auxiliary to and located on the side of an arterial highway for service to abutting property and adjacent areas, and for control of access. Highway -The entire improvement comprising the entire right -of-way. See definition for Road in Section 101. Highway Grade Separation -Any structure carrying highway or street traffic over or under another highway or street. 5 Holidays -Official holidays are New Year's Day, Martin Luther King, Jr. Day, President’s Day, Memorial Day, West Virg inia Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, Christmas Day, and any day in which an election (Primary or General) is held through the State and such other days as the President, Governor, or other duly constituted authority shall proclaim to be holidays. If a holiday falls of Sunday, the following Monday shall be observed in lieu thereof. If a holiday falls on a Saturday, the previous Friday shall be observed in lieu thereof. Inspector -The Engineer's authorized representative assigned to make any or all necessary inspection of the work as further described in 105.10. Instructions to Bidders -The notice to Contractors containing all necessary information as to provisions, requirements, date and time of submitting Proposals. Invitation for Bids -The advertisement for bids, as required by law, inviting bids for work to be performed or material to be furnished. Item -A specifically described unit of work for which a price is provided in the contract. Labor atory -The testing laboratories of the Division or any other testing laboratory designated by the Division. Lot-A lot is an isolated quantity of specified material from a single source or a measured amount of specified construction assumed to be produced b y the same process. Materials -Any substances specified for use in the construction of the project and its appurtenances. Materials Procedure -A procedure defining standard methods or guidelines for the inspection, sampling, testing, evaluation, and documentation of the Material's Division activities relative to the quality assurance program for materials, products, and processes. Each Materials Procedure is identified by the letters MP followed by seven digits, (i.e. MP XXX.XX.XX). Median -The porti on of a divided highway separating the traveled ways for traffic in opposite directions. Median Lane -A speed -change lane within the median to accommodate left -turning vehicles. Multiple Deficiency -A multiple deficiency is defined as a failure to meet specified requirements involving more than one characteristic of a material within the same lot. Notice To Proceed -Written notice to the Contractor to proceed with the contract work including, when applicable, the date of beginning of contract time. Park ing Lane -An auxiliary lane primarily for the purpose of vehicular parking. Parkway -An arterial highway for non -commercial traffic, with full or partial control of access, and usually located within a park or a ribbon of parklike development. 6 Pavement Stru cture -The combination of subbase, base course, and surface course placed on a subgrade to support the traffic load and distribute it to the roadbed. Plans -The approved Plans, profiles, typical cross sections, working drawings, standard drawings, and suppl emental drawings, or exact reproductions thereof, which show the location, character, dimensions and details of the work to be done. Pre-Construction Conference -A conference normally called by the District Engineer, following award and prior to start of c onstruction, to be attended by Division officials and by the responsible officials of the Contractor and other affected parties. Pre-Qualification Statement -The approved form or forms upon which Contractors shall furnish information as to their ability to perform work, their experience, personnel, equipment and financial condition. Profile Grade -The trace of a vertical plane intersecting the top surface of the proposed wearing surface, usually along the longitudinal centerline of the roadway. P rofile grade means either elevation or gradient of such trace according to the context. Project -The specific section of the highway, together with all appurtenances and construction to be performed, under the Contract. Project Engineer or Project Supervi sor-The representative of the Engineer on a project. See further 105.9. Proposal -The offer of a bidder, on the prescribed form, to perform the work and to furnish the labor and material at the prices quoted. Proposal Form -The approved form on which the Division requires a bid to be prepared and submitted for the work. Proposal Guaranty -The security furnished with a bid to guarantee that the bidder will enter into the Contract if their bid is accepted. Railway -Highway Separation -Any structure carryi ng highway traffic over or under the tracks of any railway. Ramp -A connecting roadway between two intersecting highways, usually at a highway grade separation. Right -Of-Way -A general term denoting land, property, or interest, usually in a strip, acquired for or devoted to a highway. Road -A general term denoting a public way for purposes of vehicular travel, including the entire area within the right -of-way, or needed for the maintenance of travel. See West Virginia Code, Chapter 17, Article 1, Section 3 . 7 Roadbed -The grade portion of a highway, within top and side slopes, prepared as a foundation for the pavement structure and shoulders. Roadside -A general term denoting the area adjoining the outer edge of the roadway. Extensive areas between the roadways of a divided highway may also be considered roadside. Roadside Development -Those items necessary to the complete highway which provide for the preservation of landscape materials and features; the rehabilitation and protection against erosion of all areas disturbed by construction through seeding, sodding, mulching and the placing of other ground covers; such suitable planting and other improvements as may increase the effectiveness and enhance the appearance of the highway. Roadway -The portion o f the highway within limits of construction. Seasonal Restrictions -Limitations imposed on the work which prohibit the Contractor from performing certain types of work during specific seasons of the year. Shoulders -The portion of the roadway contiguous wi th the traveled way for accommodation of stopped vehicles, for emergency use, and for lateral support of base and surface courses. Sidewalk -That portion of the roadway primarily intended for the use of pedestrians. Single Deficiency -A single deficiency is defined as a failure to meet specified requirements involving one characteristic of a material. Special Provisions -Additions and revisions to the Standard and Supplemental Specifications covering conditions peculiar to an individual project. Specialty Item -An item of work designated as “Specialty Item” in the proposal that is limited to work which requires highly specialized knowledge, craftsmanship, or equipment that is not ordinarily available in contracting organizations prequalified to b id and is usually limited to minor components of the overall Contract. Specifications -A general term applied to all directions, provisions, and requirements pertaining to performance of the work. State -The State of West Virginia. Street -A general term denoting a public way for purposes of vehicular travel, including the entire area within the right -of-way. Structures -Bridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, endwalls, buildings, sewers, service pipes, underdrains, foundation drains, and other features which may be encountered in the work and not otherwise classed. Subbase -The layer or layers of specified or selected materials of designed thickness placed on a subgrade to support a base course. 8 Subcont ractor -An individual, firm, or corporation to whom the Contractor sublets part of the Contract. Subgrade -The upper portion of a roadbed upon which the pavement structure and shoulders are constructed. Substantial Completion or Substantially Complete -The work on the Contract will be considered substantially complete when all Items of Work are complete, as determined by the Engineer; with the exception of permanent roadway striping. Substructure -All that part of the structure below the bearings of simple a nd continuous spans, skewbacks of arches and tops of footings of rigid frames, together with the backwalls, wingwalls, and wing protection railings. Superintendent -The Contractor's authorized representative in responsible charge of the work. Superstructu re-The entire structure except the substructure. Supplemental Agreement -A modification of the Contract covering changes in the Plans or quantities, or both, and establishing the basis of payment and time adjustment for the work necessitated by reason of t he modification, requiring the signature of the Commissioner, the Contractor, and the Surety, or their authorized representatives. Supplemental Specifications -Additions to and revisions of the Standard Specifications that are approved subsequent to issuance of the printed book. Supplemental Specifications prevail over Standard Specifications when in conflict therewith. Surety -The corporation, partnership, or individual, other than the Contractor, executing a bond furnished by the Contractor. Temporary Structure -A structure required for the use of traffic or other purpose while construction is in progress and not to be retained as a part of the improvement. Titles -The titles or headings of the sections and subsections are intended for convenie nce of reference and shall not be considered as having any bearing on their interpretation except those titles and headings used in conjunction with the definition of terms. Traffic Lane -The portion of the roadway for the movement of a single line of vehi cles. Traveled Way -The portion of the roadway for the movement of vehicles, exclusive of shoulders and auxiliary lanes. Work -Work shall mean the furnishing of all labor, materials, equipment, and other incidentals necessary or convenient to the successfu l completion of the project and the carrying out of all duties and obligations imposed by the contract. 9 Working Day -Every day shown on the calendar, exclusive of Saturdays, Sundays, and Holidays as set forth in definitions for Holidays in Section 101, o n which weather and other conditions not under the control of the Contractor will permit construction operations to proceed for a minimum of five hours with normal working forces engaged in performing the controlling item or items of work. Working Drawing s-The Contractor shall submit to the Engineer all stress sheets, shop drawings, erection plans, falsework plans, framework plans, cofferdam plans, bending diagrams for reinforcing steel, or any other supplemental plans or similar data for the Engineer’s use. Work Order -A written order, signed by the Engineer, requiring certain performance by the Contractor without negotiation. Such order shall not change quantities of major items beyond the twenty -five percent (25%) limitations, shall not create new items, nor make revi sions to item prices. 101.3 -INTERPRETATIONS : In order to avoid cumbersome and confusing repetition of expressions in these Specifications, it is provided that whenever anything is, or is to be done, if, a s, or, when, or where "contemplated, required, determined, directed, specified, authorized, ordered, given, designated, indicated, considered necessary, deemed necessary, permitted, reserved, suspended, established, approval, approved, disapproved, accepta ble, unacceptable, suitable, accepted, satisfactory, unsatisfactory, sufficient, insufficient, rejected, or condemned," it shall be understood as if the expression were followed by the words "by the Engineer" or "to the Engineer". 10 SECTION 102 BIDDING REQ UIREMENTS AND CONDITIONS 102.1 -ELIGIBILITY OF BIDDERS : All bidders on projects let to contract by the Division shall be prequalified as provided for by rules or regulations, or both, of the Commissioner. A Certificate of Qualification will be issued by the Commissioner indicating the categories of work for w hich the Contractor is qualified to perform for the Division. To obtain a Certificate of Qualification, the Contractor must submit, on the form provided by the Division, a Contractor Prequalification Application containing the information as required based on the categories of work for which prequalification is being requested. A completed Contractor Prequalification Application will be accepted by the Commissioner until fifteen ( 15) calendar days prior to the date set for receiving bids on projects on which the applicant may wish to submit a Proposal. Award of a certificate may be held in abeyance until such time as the Commissioner is able to verify all references and be satisfied as to the applicant's qualifications. No Contractor will be issued a Cer tificate of Qualification until the Division has had adequate time to review and verify the adequacy of the information provided in the Contractor Prequalification Application. It is the bidder’s responsibility to complete any Electronic Bidding registrat ion required by the Division, and acquire all the necessary software, hardware, and networking capabilities for the Electronic Bidding process. It should be noted that only Prequalified Contractors or their authorized representatives will be approved to o btain, at their cost, an electronic bidder ID. When more than one project is advertised, Proposals may be submitted on as many projects as the Contractor desires, providing the Contractor is qualified as described above for each individual project . In addition, the Prime Contractor must be prequalified in the categories of work indicated in the proposal in a combination of those categories of work in order to perform work amounting to not less than 30% of the contract cost. 102.2 -PROPOSAL FORMS : Proposal forms will be available on Bid Express and will show the location and description of the proposed work, the approximate estimates of the various quantities of work to be performed for materials to be furnished, the amount of the proposal guaranty, the number of working days or date on which the work is to be completed, and the date, time and place of opening of proposals. The proposal form will also include any special provisions o r requirements not contained in the Specifications. All documents included in the electronic proposal form are considered a part thereof and must not be detached or altered. Additional information not included in the proposal form including, but not limit ed to, old plans, old shop drawings, geotechnical information, environmental documents, permit applications, permits, asbestos reports, hazardous materials reports, and other documents or data may be provided as an exhibit on Bid Express. All additional do cuments are to be considered as part of the proposal documents, unless the additional document(s) specifically states that it is for informational purposes only. Documents marked “for informational purposes only” are not to be considered contract documents , and potential bidders rely upon information contained therein at their own risk. Any requests for additional information or other pre -construction data should be presented to the Division through Bid Express, as described in Section 102.9. 11 102.3 -INTERP RETATION OF APPROXIMATE ESTIMATES : The quantities appearing in the proposal form are approximate only and are prepared for the comparison of bids. Payment to the Con tractor will be made only for the work accepted, or for materials furnished in accordance with the Contract. If upon completion of the construction the actual quantities show either increase or decrease, the unit bid prices offered in the Proposal will prevail except as further provided. 102.4 -EXAMINATION OF PLANS, SPECIFICATIONS, AND SITE OF WORK : The bidder is required to carefully examine the Plans, Specifications, Supplemental Specifications, proposal forms, and the site of the work contemp lated. The submission of a bid shall be considered prima facie evidence that the bidder has made such examination and has judged for and satisfied themselves as to the character, quality, and quantity of work to be performed and material required to be furnished under the Contract. 102.5 -PROPOSAL SUBMISSION : The bidders Proposal must be submitted through Bid Express using the electronic file provided with the proposal form and documents, by the time designated in the proposal to proceed with the letting. Proposals submitted by any other means, including on paper, will be rejected. 102.5.1 -Schedule of Items: The bidder must furnish a unit price or a lump sum price as called for in the Proposal, in numerical figures, for each pay item listed, except that in the case of alternates, the bid may be made on only one alternate if so desired. 102.5.2 -DBE Utilization Certification (Section C): The bidder must acknowledge intent to submit written and signed documentation of commitment to use a DBE subcontractor whose participation the contractor submits to meet a contract goal and written and si gned confirmation from the DBE that is participating in the contract as provided in the prime contractor's commitment, by indicating the Contractor’s DBE Goal Percent. 102.5.3 -Bidding Requirements : The bidder must complete all sections contained in the Bidding Requirements and check the box indicating he or she has read, understands, and intends to comply with all documents contained in the proposal.

i.Section A: Free Competitive Bidding Affidavit – Prior to the approval of Federal -Aid Contracts, a sworn statement in the form of an affidavit shall be executed by, or on behalf of, the person, firm, association, or corporation to whom such contract is to be awarded. ii. Section B: Certification with Regard to the Performance of Previous Contracts or Subcontracts Subject to the Equal Opportunity Clause and the Filing of Required Reports. iii. Section D: Assurance Requirement Regarding Equal Employment Opportunity for Vendors, Suppliers and Contractors Engaged in Commercial Transactions with the West Vir ginia Division of Highways. iv. Section E: Contract Dates.
v.Section F: Certificate of Compliance Involving the Supplying of Aluminum, Glass, Steel or Iron Products. vi. Section H: West Virginia Contractor Licensing Act Chapter 30 Article 42 Code of West Virginia Li cense Number – The proposal shall comply with West Virginia Contractor Licensing Act, Chapter 30, Article 42 Code of West Virginia, except that 12 on Federal -Aid Projects a n unexpired Contractor’s license is not required at time of bid but will be required b efore a project will be awarded. vii. Section I: Drug and Alcohol -Free Workplace – An affidavit that the Contractor implements and maintains a written drug -free workplace policy which meets the requirements of Article 1D, Chapter 21 of the Official Code of West Virginia, as amended. The successful bidder must submit a copy of its drug -free workplace policy within ten (10) days following the letting and prior to the awarding of the contract. Any successful bidder who fails to submit the policy within the specifie d time limit will risk forfeiture of his/her proposal guaranty . The successful bidder must also ensure that its subcontractors implement and maintain a written drug-free workplace policy complying with Article 1D, a copy of which must be submitted to the Division by the Contractor prior to the start of the subcontract work. The contract may be terminated if the Contractor:
a.Fails to implement its policy;
b.Fails to provide information regarding implementation of the policy at the request of the Division; or,
c.Provides to the Division false information regarding the policy. A clearly legible copy of the written drug -free workplace policy must be kept posted in a prominent and easily accessible place at the project site by each contractor subject to the provisions of Article 1D. Every Contractor shall keep an accurate record showing the names, occupation and safety - sensitive status of all employees, i n connection with the construction on the project, and showing any drug tests or alcohol tests performed and employee education and supervisor training received, which record shall be open at all reasonable hours for inspection by the Division. The Contractor must preserve these records for three years after completion and acceptance of the project. All drug testing information specifically related to individual employee is confidential and should be treated as such by anyone authorized to review or compile program records. viii. Section J: Amendment – Bidder must acknowledge that all amendments have been reviewed and considered in the bidder’s proposal. ix. Section K: Blank.
x.Section L: Categories of Work – Bidder must acknowledge that they will perfo rm, with their own organization, work amounting to not less than 30 percent (30%) of the total contract cost, as detailed in Section 108.1. All categories of work in the contract for which the bidder is not prequalified to perform must be subcontracted to a contractor who is prequalified in those categories. Failure to meet the prequalification requirement may be basis for termination of the contract and the awarding of said contract to the next responsible bidder or readvertisement and letting of the con tract. Any additional costs for said actions shall be the responsibility of the bidder. xi. Section M: Monetary Obligations Owed to the State – Bidder must acknowledge that, pursuant to W. Va. Code § 5 -22-1(i), the bidder is not in default on any monetary obligation owed to the State of West Virginia or a political subdivision of the State of West Virginia, including, but not limited to, obligations related to payroll taxes, property taxes, sales and use taxes, fire service fees, or other fines or fees. 102.5.4 -Bid Bond : Bidders must verify his or her bid bond by completing the Bid Bond section of the electronic file. 13 102.6 -PROPOSAL GUARANTY : No proposal will be considered unless accompanied by a digitally signed proposal guaranty (bid) bond as described in Section 102.5.3 made payable to the West Virginia Division of Highwa ys. Bid bonds will be accepted only if submitted electronically as described in Section 102.5.3. Any bid bond executed on a copy, duplicate, or facsimile will be rejected. 102.7 -WITHDRAWAL OF PROPOSALS : Bidders may withdraw Proposals during the course of reading of bids prior to the actual reading of bids on the project for which the bid is withdrawn only electronically through the Bid Express automatic bid withdrawal function or by providing a written document at the site of the letting in the following form: “I, the undersigned, of ________________________, Contractor(s) hereby acknowledge that I have this day withdrawn the se aled bid of _________________________________, Contractor(s) on West Virginia Division of Highways Project No. __________________________”. Should a bidder wish to provide a written document at the site of the letting, they must notify the Division of their intent to do so via email to DOHContractProcure@wv.gov no later than 4:00 PM Eastern Time on the Friday before the scheduled letting. Additionally, the written notice (s) provided by the bidder withdrawing his or her bid(s) must be provided prior to the reading of the call(s) on which the bid is being withdrawn. No bid may be withdrawn on any call once the apparent bids have been read by the Division. 102.8 -COMBINATION PROPOSALS : If the Division so elects, Proposals may be issued for projects in combination or separately, so that bids may be submitted either on the combination or on separate units of the combination. The Division reserves the right to make awards on combination bids or separate bids to the best advantage of the Division. No combination bids other than those specifically set up in proposals by the Division will be c onsidered. Separate Contracts will be written for each individual project included in the combination. 102.9 -QUESTIONS REGARDING ADVERTISED PROPOSALS : All projects advertised by the Division will require any questions to be asked using the Bid Express Question and Answer feature in accordance with any listed req uirements. The various contact information required shall be filled out and completed with valid and applicable information which the Division may verify. If the contact information is unable to be verified, then any questions associated with this informat ion may not be answered. Questions and Answers are for informational purposes only. Any posted questions or answers do not alter the terms and conditions of the advertised Contract in question. Official changes to the Contract shall only be issued by the Division through an amendment to the applicable Contract. Potential Bidders may ask questions up until the time of the posted letting with no exceptions. However, it should be noted that any questions that may necessitate a change to the Contract should be asked seven (7) working days prior to the posted letting date to allow the Division to issue an amendment to modify the Contract, if necessary. Questions received three (3) working days or more in advance of a posted letting should be answered prior to the time of the posted letting. Questions received within three (3) working days of the posted time of letting may or may not be answered as time allows.

102.10 Public Reading of Proposals :

Proposals will be received, decrypted, read publicly, and published at the time and place indicated in the Notice to Contractors. Bidders, their authorized agents, and other interested parties are invited to be present.

102.11 Disqualification of Bidders :

Either of the following reasons may be considered as being sufficient for the disqualification of a bidder and the rejection of their Propos al or Proposals.

i.More than one Proposal for the same work from an individual, firm, or corporation under the same or different name. ii. Evidence of collusion among bidders. Participants in such collusion will receive no recognition as bidders for any future work of the Division until any such participant shall have been reinstated as a qualified bidder.

102.12 Irregular Proposals :

Proposals may be considered irregular and rejected for an y of the following reasons:

i.When the Proposal is not submitted by the electronic file furnished by the Division on Bid Express or if the form is altered. Use of a Division approved computer generated Schedule of Items shall not be considered an alteration of form or format within the meaning of these Specifications. ii. When there are unauthorized additions, conditional or alternate bids, or irregularities of any kind which may tend to make the Proposal incomplete, indefinite, or ambiguous as to its meaning. Al so, when Division approved computer generated Schedule of Items show any alteration of format, additions or amendments not called for, errors or omissions in units of measure, or erasures. iii. When the bidder adds any provisions reserving the right to accept o r reject an award, or to enter into a Contract pursuant to an award. This does not exclude a bid limiting the maximum gross amount of awards acceptable to any one bidder at any one bid letting, providing that any selection of awards will be made by the Div ision. iv. Failure to sign or properly execute the Proposal.
v.Failure to indicate a proposed goal in Section C of the Notice contained in the Proposal, when a Division determined goal is indicated in paragraph 5 of the Special Provision for Disadvantaged Busine ss Enterprise Utilization. vi. Failure to properly acknowledge receipt of amendment(s) in accordance with Section J of the notice contained in the proposal. vii. Failure to show the unexpired West Virginia Contractor’s License Number when required in Section H of the notice contained in the proposal. vii. The bidder is not prequalified in the categories of work indicated in the proposal in a combination of those categories of work in order to perform work amounting to not less than 30% of the contract cost. viii. The proposal is mathematically and materially unbalanced. A mathematically unbalanced bid contains lump sum or unit price items that do not include reasonable labor, equipment, and material costs plus a reasonable proportionate share of the Bidder’s overhead costs, other indirect costs and anticipated profit. A Materially Unbalanced Bid is when the Division determines that an award to the Bidder submitting a Mathematically Unbalanced Bid will not result in the lowest ultimate cost to the Division.
Source: West Virginia Standard Specifications for Road and Bridge Construction, 2023 Edition. Pages 924 of 1,006.