211.1DESCRIPTION

1 This section describes the requirements for removing, hauling, and disposing of debris, silt, and obstructions from existing culverts.

211.2MATERIALS—V acant

211.3EQUIPMENT—V acant

211.4CONSTRUCTION

1 Unplug and flush clean existing culverts as specified. Dispose of material removed at a contractor-furnished site.

2 Do not damage culverts, appurtenances, or property or create a public hazard or nuisance. If damage occurs, repair in accordance with Subsection 107.8, Protection and Restoration of Property, Markers, and Landscape.

211.5MEASUREMENT and PAYMENT

1 The engineer will measure Culvert Cleaning by the each.

2 The department will pay as follows:

Pay Item

Pay Unit Measure to the Nearest Pay to the Nearest Culvert Cleaning EA [Ea] EA [Ea] EA [Ea]

Get an email when 211 changes

Wyoming revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Wyoming Standard Specifications for Road and Bridge Construction, 2021 Edition. Pages 185–0 of 771. View official source ↗