B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
General

412Pay Item

WY · 2021 Standard SpecificationsBook pages 00View official source ↗

Pay Unit

Measure to the Nearest

Sidewalk (Plant Mix) Spillway (Plant Mix)

SY [m2] FT [m]

0.1 ft [0.05 m] 0.1 ft [0.05 m]

Pay to the Nearest SY [m2] FT [m]

412.5.2 Referenced Sections for Direct Payment 1 When specified, the engineer will measure, pay and price adjust for:

1.Asphalt Binder (PG __-__) in accordance with Section 401, Plant Mix

Pavements.

2.Hot Plant Mix in accordance with Section 401, Plant Mix Pavements, under the

appropriate pay item, except for plant mix used for the pay item Bike Path (Plant Mix)

3.Tack Coat in accordance with Section 407, Tack Coat.
4.Hydrated Lime in accordance with Section 413, Hydrated Lime.
5.Haul in accordance with Section 204, Haul.

329

Hydrated Lime

413.1DESCRIPTION

1 This section describes the requirements for adding dry lime to a wetted aggregate.

413.2MATERIALS

1 Provide materials in accordance with the following:

Material

Subsection

Hydrated Lime Water

820 814

413.3EQUIPMENT

1 Provide a mechanical mixing device that creates a uniform and homogeneous mixture

with all aggregate particles coated with hydrated lime as approved by the engineer. 2 Equip the mixing plant with facilities to weigh check samples and to calibrate gate

openings and metering devices. Equip with weighing or metering devices (such as a vane feeder with a calibrated revolution counter) to determine the rate of hydrated lime introduced into the aggregate while the plant is in full operation. Do not use belt scales. 3 Use

a spray bar or other approved method to wet the aggregate uniformly. Equip the plant with devices that meter the water and hydrated lime into the mixer. Interlock and synchronize the metering devices and feeders to maintain a constant rate of hydrated lime and water to the aggregate.

4 To control the daily quantity of hydrated lime added to the aggregate and to facilitate

calibration of the metering devices, place the bulk storage container from which hydrated lime is metered on scales or equip with load cells to enable the accurate measurement of the remaining weight [mass] in the container at the end of each day. Do not use strain gages. 5 Use a pug mill with a mixing chamber to mix the hydrated lime and water with

the aggregate. Keep the materials in the chamber until obtaining a uniform and homogeneous mixture of lime, water, and aggregate. Do not use devices that allow the materials to drop directly through the mixing paddles.

6 Locate the pug mill to allow inspection of the mixture during mixing and after discharge

from the mixer. Make the belt from the pug mill to the dryer accessible for sampling. Provide a template of the belt for taking a sample to determine moisture content.

330

Hydrated Lime