Rumble Strips

418.1DESCRIPTION

1 This section describes the requirements for cutting rumble strips in plant mix pavement and concrete pavement.

418.2MATERIALS—V acant

418.3EQUIPMENT

1 Ensure that equipment meets the following:

1.For portland cement concrete pavement, provide a grinder with carbide-tipped

grinding drum. For plant mix pavement, provide a mill with steel milling head. Ensure equipment produces a smooth cut in accordance with the corrugation pattern specified.

2.A power broom or sweeper/vacuum.

418.4CONSTRUCTION

418.4.1 General

1 Repair or recut misaligned rumble strips. Repair or replace damaged pavement at no additional cost to the department. Before opening the adjacent lane or roadway to traffic each day, remove waste material resulting from the work.

418.4.2 Shoulder Rumble Strips

1 Align the shoulder rumble strip where specified and as verified by the engineer.

2 Demonstrate to the engineer on an initial test section of 500 ft [150 m] that the equipment and methods provide the desired rumble strip and surface inside each depression, without tearing or snagging the plant mix pavement. If the results do not meet the contract requirements, use new equipment or methods, or make necessary adjustments; repair or replace the test section as directed at no additional cost to the department.

418.4.3 Rumble Strip Sections

1 Align the group of rumble strip sections without deviation greater than 6 in [150 mm] from the longitudinal reference line. Do not install before the engineer verifies the alignment.

Rumble Strips SECTION 418

418.5MEASUREMENT and PAYMENT

1 The engineer will measure:

1.Rumble Strips (Asphalt) or Rumble Strips (Concrete) by the mile [kilometer],

longitudinally along the edge of travel way for each affected shoulder.

2.Rumble Strip Section by the each.

2 The department will pay as follows:

Pay Item

Pay Unit Measure to the Nearest Pay to the Nearest Rumble Strips (Asphalt) MI [km] 0.001 mi [0.005 km]

0.01MI

[0.05 km] Rumble Strips (Concrete) MI [km] 0.001 mi [0.005 km]

[0.05 km] Rumble Strip Section EA [Ea] EA [Ea] EA [Ea]

DIVISION 500

Str uctures

Get an email when 418 changes

Wyoming revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Wyoming Standard Specifications for Road and Bridge Construction, 2021 Edition. Pages 397–0 of 771. View official source ↗