VALUE ADDED PORTLAND CEMENT CONCRETE PAVEMENT
355-1 Description.
Construct Value Added Portland Cement Concrete Pavement (Concrete Pavement), subject to a five year warranty period after final acceptance of the Contract in accordance with
5-11 This Section applies only to new pavements, including added lanes.
Submit each mix design to the Engineer at least 14 days prior to any paving work. Perform all the associated work specified in this Section including continued responsibility for performing all remedial work associated with pavement distresses exceeding threshold values determined in accordance with this Section and as to which notice was provided to the Contractor. The work specified in this Section will not be paid for directly, but will be considered as incidental to other Contract items.
355-2 Materials and C onstruction Requirements.
Meet the requirements of the following: Portland Cement Concrete ................................ ..Section 346 Cement Concrete Pavement ................................ Section 350 Grinding Concrete Pavement .............................. Section 352
355-3 Statewide Disputes Review Board.
The Statewide Disputes Review Board in effect for this Contract will resolve any and all disputes that may arise involving administration and enforcement of this Specification. The Contractor and the Department acknowledge that use of the Statewide Disputes Review Board is required, and the determinations of the Statewide Disputes Review Board for disputes arising out of this Specification will be binding on both the Contractor and the Department, with no right of appeal by either party. Meet the requirements of 8 -3.
355-4 Pavement Evaluatio n and Remedial Work.
355-4.1 General: The Department’s Pavement Condition Survey Program along with
observations by the Engineer will be used as the basis for determining the extent and the magnitude of the pavement distresses occurring on the project. In the event the level of distress exceeds any of the threshold values defined below, remedial work as described in 355 -5 by the Contractor will be required. The Department will monitor the pavement for distresses and may require remedial action at any tim e. The Department may conduct a Pavement Condition Survey of the value added pavement following the final acceptance of the project, and at intermediate times throughout the warranty period with findings provided when considered by the Department to be the obligation of the Contractor. The final survey, if determined by the Engineer to be necessary, will be conducted before the end of the warranty period with results provided to the Contractor for those conditions exceeding contract threshold values requ iring remedial action that the Department believes to be an obligation of the Contractor. The Department will be responsible for all costs associated with the surveys. FY 2023-24 Return to Table of Contents If the survey findings, intermediate or final, are to be disputed by the Contractor, written notification must be submitted to the Engineer within 30 calendar days of the date of receipt of the information from the Department. During the warranty period, the Contractor may monitor the pavement using nondestructive methods and may particip ate with the Department in the Pavement Condition Surveys upon request. Do not conduct any coring, milling or other destructive methods without prior approval by the Engineer.
355-4.2 Distress Indicators: The Department will use Ride, Spalling and Crackin g, as
distress indicators in accordance with the Rigid Pavement Condition Survey Handbook to evaluate the Concrete Pavement. Ride Number (RN) will be established by Laser Profile r in accordance with FM 5-549. For ride evaluation purposes, the project will be subdivided into LOTs of 0.1 mile per lane and partial LOTs which are segments that are less than 0.1 mile. For the purposes of threshold values and remedial work, partial LOTs and LOTs will be treated as LOTs. 355-4.3 Threshold Values and Remedial Work: Threshold values and associated remedial work for the Concrete Pavement are specified in Table 355-1. Table 355-1 Concrete Pavement Threshold Values and Remedial Work Type of Distress Threshold Values Remedial Work Ride Ride Number < 3. 50 Grind all deficient LOTs and partial LOTs in accordance with Section 352. Spalling in the wheel path Four areas in any Lane Mile exceeding 1 inch in width and exceeding 6 inches in length OR any single area exceeding 3 inches in width. Full depth slab replacement for a minimum of 6 feet in length and the full width of the slab in accordance with Section 353. Spalling outside the wheel path Four areas in any Lane Mile exceeding 1 -1/2 inches in width and 12 inches in length OR any single area exceeding 3 inches in width and 12 inches in length. Full depth slab replacement for a minimum of 6 feet in length and the full width of the slab in accordance with Section 353. Cracking Four Cracks in any Lane Mile with width exceeding 1/8 inch OR any Crack exceeding 3/16 inch. Full depth slab replacement for a minimum of 6 feet in length and the full width of the slab in accordance with Section 353. Shattered Slab Cracking patterns that divide the slab into three or mor e segments Full slab replacement in accordance with Section 353.
355-5 Remedial Work.
Perform all necessary remedial work described in this Section at no cost to the Department. Should an impasse develop in any regard as to the need for remedial work or the extent required, the Statewide Disputes Review Board will render a final decision by majority vote. FY 2023-24 Return to Table of Contents Remedial work will not be required if any one of the following conditions is found to apply:
355-6 Failure to Perform.
Failure to timely submit any disput e to the Statewide Disputes Review Board, failure to satisfactorily perform any remedial work, or failure to compensate the Department for any remedial work performed by the Department and determined to be the Contractor’s responsibility in accordance with this Specification, the Department will suspend, revoke or deny the Contractor’s certificate of qualification under the terms of Section 337.16(d)(2), Florida Statutes, for a minimum of 6 months or until the remedial work has been satisfactorily performed (or full and complete payment for remedial work performed by others made to the Department), whichever is longer. Should the Contractor choose to challenge the Department’s notification of intent for suspension, revocation or denial of qualification and t he Department’s action is upheld, the Contractor will have its qualification suspended for an additional minimum of 6 months. The remedial work is not an obligation of the Contractor’s bond required by Section 337.18, Florida Statutes. FY 2023-24 Return to Table of Contents SECTION 370 BRIDGE APPROACH EXPANSION JOINTS
370-1 Description.
For concrete pavement using the asphalt base option, construct expansion joints in accordance with Standard Plans, Index 350-001. For concrete pavement using the special select soil base option, construct special expansion joints near the bridge approach s labs that consist of a section of reinforced concrete subslab supporting the roadway concrete pavement in accordance with the details shown in Standard Plans, Index 370-001 and the Contract Documents .
370-2 Materials.
Bar Reinforcement: Use bar reinforcin g steel meeting the requirements of 931 -1.1. Concrete: For the expansion joint subslab, use concrete meeting the requirements of Section 347. Galvanized Sheet Metal: Use galvanized sheet metal meeting the requirements shown in the Plans. Seal: Use compr ession seals in accordance with Section 932 and Standard Plans, Index 370-001.
370-3 Construction Methods.
Construct the expansion joints in accordance with the applicable requirements of Sections 346, 347, 350, 415 and Standard Plans, Indexes 350-001 and 370-001.
370-4 Method of Measurement.
The quantity to be paid for will be plan quantity, in feet, calculated across the pavement at right angles to the centerline of the roadway pavement, completed and accepted.
370-5 Basis of Payment.
Price and payment will be full compensation for all work and materials specified in this Section or required for the expansion joint, including concrete subslab, sheet metal strip, reinforcing steel, compression seal and all additional excavation required. Payment will be made under: Item No. 370 - 1- Bridge Approach Expansion Joint - per foot. FY 2023-24 Return to Table of Contents