Final compaction shall be performed with a smooth drum roller.
219.10 Trimming Stabilized soil shall be prepared, and adequate drainage shall be provided at all 90
times to prevent water from standing on the subgrade. The grade and cross-section of the subgrade shall be finished within a tolerance of 1/2 in. from the subgrade elevation shown on the plans. Even though the subgrade has been prev iously accepted, the condition of the subgrade shall be in accordance with 105.03 and 207.04 at the time paving material is placed. Finishing within this tolerance by blading or other mechanical means without the use of side forms will be allowed. If these methods do not finish within this tolerance, 100 side forms shall be used. 219.11 QC Testing QC testing shall be performed as follows:
219.12 Quality Assurance, QA, Testing Moisture tests based on ITM 506 for soil cement mixtures will be performed at
every 2,000 sq yds during cement and soils mixing. Acceptance testing for compaction of ce ment stabilized subgrade soils will be performed on the finished grade with an LWD in accordance with 203.24(b) with the exception that the interval for LWD testing will be every 2,000 sq yds. The acceptance test for the cement stabilized subgrade soils will begin seven days after compaction. The allowable average deflection and maximum deflection for cement stabilized 150 subgrade soil shall be in accordance with the following: Material Type Allowable Average Deflection (mm) Maximum Deflection at Single Test Location (mm) Cement Stabilized Subgrade Soil 0.14 0.17
219.13 Curing The surface shall be maintained in a moist condition with no visible dry areas for
the first seven days after mixing with cement. Liquid membrane forming compound shall be applied in accordance with 504.04(a) to the surface and reapplied as applicable for the first seven days to aid in curing and prevent loss of moisture. 219.14 Proofrolling 160 The entire stabilized soil shall be proofrolled in accordance with 203.26. Deflection or ruts greater than 1/4 in. shall be corrected as directed.
219.15 Method of Measurement
The accepted cement stabilized subgrade soil will be measured by the square yard, complete in place.
219.16 Basis of Payment
The accepted quantity of cement stabilized subgrade soil will be paid for at the contract unit price per square yard. 170 219.16 262 Approved adjustments for cement that exceed the limit of 219.04 will be included in a change order for materials only and paid for as additional cement for subgrade soil stabilization. Payment for additional cement for subgrade soil stabilization will be made for direct delivered material costs incurred by the Contractor and will not include any other markups. Payment will be made under: Pay Item Pay Unit Symbol 180 Cement Stabilized Subgrade Soil ............................................. SYS The cost of performing mix design, services of a qualified geotechnical consultant, scarification of the soil, spreading and mixing of the cement and soil, compaction of the resultant mixture, shaping the soil, work required due to adjustments of modifier proportioning, work required due to weather conditions, correction of deficient areas, water required for the stabilization process, soil trimming, liquid membrane forming compound, and all operations needed to meet the requirements of this specification shall be included in the cost of the pay item. 190 219.16 263 DIVISION 300 – AGGREGATE PAVEMENT AND BASES