Earthwork (200-299)

260Initial compaction equipment shall consist of a vibratory tamping-foot roller.

IN · 2024 Standard SpecificationsBook pages 1517View official source ↗

Final compaction shall be performed with a smooth drum roller.

219.10 Trimming Stabilized soil shall be prepared, and adequate drainage shall be provided at all 90

times to prevent water from standing on the subgrade. The grade and cross-section of the subgrade shall be finished within a tolerance of 1/2 in. from the subgrade elevation shown on the plans. Even though the subgrade has been prev iously accepted, the condition of the subgrade shall be in accordance with 105.03 and 207.04 at the time paving material is placed. Finishing within this tolerance by blading or other mechanical means without the use of side forms will be allowed. If these methods do not finish within this tolerance, 100 side forms shall be used. 219.11 QC Testing QC testing shall be performed as follows:

a.QC testing for compaction of cement stabilized subgrade soils shall be performed on the finished grade with an LWD in accordance with 203.24(b) with the exception that the interval for LWD testing shall be every 1,000 sq yds. Testing for the cement stabilized subgrade soils shall begin seven days after compaction. Construction traffic 110 or equipment exceeding 5 t in weight shall not be allowed on the treated soils until the area has passed LWD testing.
b.Moisture testing of soil cement mixtures shall be performed in accordance with ITM 506 at every 1,000 sq yds during cement and soils mixing.
c.One gradation test shall be performed for every 1,000 sq yds of cement modified soil. Gradation tests shall be performed in accordance with ITM 516. 120
d.Two test specimens shall be prep ared at 95% of the Standard Proctor and cured for seven days. Specimens shall be taken every 1,000 ft of length by lane width and shall be obtained by the Contractor. Unconfined compressive strength tests shall be performed in accordance with AASHTO T 208. The sample of the cement stabilized soils mixture shall be taken during pulverization and mixing. 219.10 261 (e) Cement spread rate shall be checked at every 2,000 ft of length by 130 lane width. Spread rate shall be in accordance with ITM 516.
f.The soil cement mixing depth shall be checked at every 2,000 ft of length by lane width in accordance with ITM 516 after mixing and prior to compaction.
g.All tests performed by the Contractor shall be compiled and submitted to the Engineer on a weekly basis for documentation of strengths obtained.

219.12 Quality Assurance, QA, Testing Moisture tests based on ITM 506 for soil cement mixtures will be performed at

every 2,000 sq yds during cement and soils mixing. Acceptance testing for compaction of ce ment stabilized subgrade soils will be performed on the finished grade with an LWD in accordance with 203.24(b) with the exception that the interval for LWD testing will be every 2,000 sq yds. The acceptance test for the cement stabilized subgrade soils will begin seven days after compaction. The allowable average deflection and maximum deflection for cement stabilized 150 subgrade soil shall be in accordance with the following: Material Type Allowable Average Deflection (mm) Maximum Deflection at Single Test Location (mm) Cement Stabilized Subgrade Soil ” 0.14 0.17

219.13 Curing The surface shall be maintained in a moist condition with no visible dry areas for

the first seven days after mixing with cement. Liquid membrane forming compound shall be applied in accordance with 504.04(a) to the surface and reapplied as applicable for the first seven days to aid in curing and prevent loss of moisture. 219.14 Proofrolling 160 The entire stabilized soil shall be proofrolled in accordance with 203.26. Deflection or ruts greater than 1/4 in. shall be corrected as directed.

219.15 Method of Measurement

The accepted cement stabilized subgrade soil will be measured by the square yard, complete in place.

219.16 Basis of Payment

The accepted quantity of cement stabilized subgrade soil will be paid for at the contract unit price per square yard. 170 219.16 262 Approved adjustments for cement that exceed the limit of 219.04 will be included in a change order for materials only and paid for as additional cement for subgrade soil stabilization. Payment for additional cement for subgrade soil stabilization will be made for direct delivered material costs incurred by the Contractor and will not include any other markups. Payment will be made under: Pay Item Pay Unit Symbol 180 Cement Stabilized Subgrade Soil ............................................. SYS The cost of performing mix design, services of a qualified geotechnical consultant, scarification of the soil, spreading and mixing of the cement and soil, compaction of the resultant mixture, shaping the soil, work required due to adjustments of modifier proportioning, work required due to weather conditions, correction of deficient areas, water required for the stabilization process, soil trimming, liquid membrane forming compound, and all operations needed to meet the requirements of this specification shall be included in the cost of the pay item. 190 219.16 263 DIVISION 300 – AGGREGATE PAVEMENT AND BASES