276 SECTION 306 – MILLING
306.01 Description
This work shall consist of the milling of asphalt and concrete pavements and the disposal of milled materials in accordance with 105.03. CONSTRUCTION REQUIREMENTS
306.02 General
Milling operations shall be described in the QCP in accordance with ITM 803. 10 Where the milling operation in a partial-day closure results in a longitudinal vertical or near vertical face exceeding 2 in. in height, the adjacent lane shall be milled during the same day, the milled lane resurfaced during the same day, or the vertical face tapered at a 45° angle or flatter. Where locat ed within 3 in. of a curb, surface material that cannot be removed by the cold-mil ling machine shall be removed by other approved methods. Transverse milled vertical faces greater th an 1 in. that are exposed to traffic shall be transitioned in an approved manner. 20 Castings located in milling areas that are not to be adjusted may remain in place during the milling or may be removed a nd replaced at the C ontractor’s option. Localized weak areas uncovered by the milling process shall be patched in accordance with 304 or 305. The milled material shall become the property of the Contractor, unless otherwise specified. The roadway shall be cleaned before opening to traffic. 30
306.03 Equipment
Equipment for milling shall be in accordance with the following.
306.04 Asphalt or PCCP Scarification Milling
Scarification milling shall consist of preparing a base for resurfacing by roughening the entire existing asphalt or PCCP surface. The milled pavement profile shall have a surface finish that does not vary longitudinally more than 1/4 in. from a 16 ft straightedge or as described in the QCP in accordance with 401.02. 80 A fine milling cutting drum in accordance with 306.03(a) shall be used when a single course overlay is specified with a lay rate as shown on the plans less than 165 lb/sq yd and the maximum scarification mill cut depth is expected to be less than 3/4 in. for asphalt or PCCP, otherwise, a coarse milling cutting drum in accordance with 306.03(a) shall be used. The scarified milled surface shall have a macrotexture ratio in accordance with ITM 812 as follows:
306.05 Asphalt or PCCP Profile Milling to Correct Cross Slope
Profile milling shall consist of preparing a base for resurfacing by removing the existing asphalt or PCCP material to the specified cross slope as shown on the plans. The milled pavement profile shall have a surface finish that does not vary longitudinally more than 1/4 in. from a 16 ft straightedge or as described in the QCP in accordance with 401.02. A fine milling cutting drum in accordance with 306.03(a) shall be used when a single course overlay is specified with a lay rate as shown on the plans less than 165 120 lb/sq yd and the maximum profile mill cut depth is expected to be less than or equal to 1 1/2 in. for asphalt or 3/4 in. for PCCP, otherwise, a coarse milling cutting drum in accordance with 306.03(a) shall be used. The profile milled surface shall have a macrotexture ratio in accordance with ITM 812 as follows: (a) equal to or greater than 5.0 when using a fine milling cutting drum for a single course overlay, or
306.06 Approach Milling Approach milling shall consist of milling the surface and cutting a wedge at the 150
driveways, commercial or public road a pproaches. The existing approach shall be milled a minimum depth of no less than 1/4 in. to accommodate the approach pavement. The approach milling shall be completed to provide a smooth transition from the traveled way pavement to the termini of the approach. The existing approach pavement shall be cut to provide a vertical face of 1 1/2 in. for the termini of surface. Mailbox approaches to be resurfaced shall be milled to maintain the traveled way profile and cross slope. Automatic control devices will not be required on surface milling equipment used 160 for approach milling. Milling shall not damage any pavement that is to remain in place. Approach milling shall not be performed at driveways unless it is required to meet a paved surface that continues beyond the cons truction limit. If the driveway is other than HMA or PCC beyond the construction limits , the approach milling is not required. The transverse vertical cut face for commercial or public road approaches shall be transitioned at a rate of 24:1 or as directed.
306.07 Asphalt or PCCP Milling to a Specified Average Depth 170
Milling shall consist of preparing a base for resurfacing by removing the existing asphalt material or PCCP to the specified average depth as shown on the plans. The milled pavement shall have a surface finish that does not vary longitudinally more than 1/4 in. from a 16 ft straightedge or as de scribed in the QCP in accordance with 401.02. A fine milling cutting drum in accordance with 306.03(a) shall be used when a single course overlay is specified with a lay rate as shown on the plans less than 165 lb/sq yd and the average mill cut depth is less than or equal to 1 1/2 in. for asphalt or 3/4 in. for PCCP, otherwise, a coarse milling cutting drum in accordance with 306.03(a) shall be used. 180 The milled surface shall have a macrotexture ratio in accordance with ITM 812 as follows: 306.07 280 (a) equal to or greater than 5.0 when using a fine milling cutting drum for a single course overlay, or
306.09 Transition Milling Transition milling shall consist of cutting a wedge at the beginning and ending of 230 306.08
281 projects, and paving exceptions. The existing pavement shall be cut to provide a nearly vertical face of 1 1/2 in. or the minimum finished thickness of a course in accordance with 401.14, whichever is greater, for the termini of each overlay lift of base, intermediate, and surface. The existing pavement shall be milled at a rate of 720:1 or as directed to achieve the specified cut where the pavement transition overlay lifts differ from cut depth. The transverse vertical cut face shall be transitioned by HMA or prefabricated materials at a rate of 24:1 or as directed. Automatic control devices will not be required on surface milling equipment used for transitions cut off the traveled way. Cutting shall not damage any pavement that is to remain in place.
306.10 Method of Measurement
Approach milling, asphalt milling, asphalt removal, PCCP milling, scarification milling, profile milling, and transition milling will be measured by the square yard of the milled area. 306.11 Basis of Payment 250 Approach milling, asphalt milling, asphalt removal, PCCP milling, scarification milling, profile milling, and transition milling will be paid for at the contract unit price per square yard. Payment will be made under: Pay Item Pay Unit Symbol Milling, Approach ..................................................................... SYS Milling, Asphalt, ________ in. .................................................. SYS 260 thickness Milling, Aspha lt Removal ......................................................... SYS Milling, PCCP ________ in. ..................................................... SYS thickness Milling, Pr ofile .......................................................................... SYS Milling, Scarification ................................................................. SYS Milling, Transition ..................................................................... SYS The cost for castings removed and replaced at the Contractor’s option in accordance with 306.02 shall be included in the cost of the milling. 270 Any portion of the pavement that is damaged or removed outside the milling limits shall be replaced with no additional payment. The cost of tapering of vertical faces and removal of milled material from the project site shall be included in the cost of milling. 306.11 282 The cost of cutting of the surface c ourse shall be included in the milling. Furnishing and operating the 16 ft straight edge shall be included in the cost of 280 other pay items within this section.