h, * ........................................ TON type Widening with HMA, * ..................................................... TON type 90 * Mixture type in accordance with 402.04.
Excavation for patching will not be paid for separately but shall be included in the cost of the patching material. The cost of furnishing, storage, hauling, and placing of all materials; pavement removal as required; temporary pavement required to carry traffic; choke aggregate required to eliminate pickup; disposal; excavation; preparation of subgrade; compacting; and finishing except as otherwise provided shall be included in the cost of the patching materials. 100 The cost of excavation and disposal of existing materials required for the compacted aggregate or HMA widening material shall be included in the cost of the HMA widening material. Replacement of pavement damaged by the Contractor’s operations shall be at no additional payment.