A requirement appearing in one of the Contract documents is as binding as though the requirement appears in all. If discrepancies exist between the Contract documents, the following order of precedence applies:
If discrepancies exist between dimensions in the Contract documents, the following order of precedence applies:
The Department and Contractor shall inform each other as to any discrepancy or defect they discover. Neither the Contractor nor the Engineer shall take advantage of any discrepancy or defect . The Engineer will review the alleged discrepancy or defect to determine if a Contract revision is necessary in accordance with 1402, “Contract Revisions.” The Engineer will decide all issues concerning a discrepancy or defect.