A requirement appearing in one of the Contract documents is as binding as though the requirement appears in all. If discrepancies exist between the Contract documents, the following order of precedence applies:

(1)Addenda
(2)Special Provisions
(3)Project-Specific Plan Sheets
(4)Supplemental Specifications
(5)Standard Plans and Standard Plates
(6)Standard Specifications

If discrepancies exist between dimensions in the Contract documents, the following order of precedence applies:

(1)Plan dimensions
(2)Calculated dimensions
(3)Scaled dimensions

The Department and Contractor shall inform each other as to any discrepancy or defect they discover. Neither the Contractor nor the Engineer shall take advantage of any discrepancy or defect . The Engineer will review the alleged discrepancy or defect to determine if a Contract revision is necessary in accordance with 1402, “Contract Revisions.” The Engineer will decide all issues concerning a discrepancy or defect.

Get an email when 1504 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 57–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1504 — Coordination of Contract Documents. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.