The Department may authorize Work by other contractors and agencies within the Project Site during the Contract Time. The Contractor shall cooperate with the Engineer, utility owners, and other contractors concurrently performing Work on the Project. The Contractor shall coordinate Work with utility owners for the following:
When performing Work of separate Contracts within the limits of a Project, each Contractor shall avoid interfering and hindering the progress or completion of the W ork being performed by other contractors. Contractors working on the same Project shall cooperate with each other as required by their respective Contracts . The Contractor shall assume the risk of delay, inconvenience, or loss resulting from the presence and operations of other contractors working within the same Project Site, and shall make no c laim for such delay, inconvenience, or loss.