1516.1PARTIAL ACCEPTANCE

After completing a substantial and discrete portion of Work, the Contractor may request the Engineer to inspect that portion. If the Engineer determines that the portion of the Work is complete in accordance with the Contract requirements, the Engineer may accept the completed portion in writing . Partial acceptance relieves the Contractor of further responsibility for maintenance of that portion of Work, but does not invalidate or alter the terms of the Contract.

1516.2PROJECT ACCEPTANCE

After completing the Work, the Contractor shall notify the Engineer and request a final inspection. If the Engineer determines that the Project is complete, the inspection will constitute the final inspection and the Engineer will promptly provide written notice of Project acceptance effective on the date of the final inspection. The notice of Project acceptance relieves the Contractor of further responsibility for the Work. If the Engineer finds unacceptable or incomplete Work, the Contractor shall immediately correct the deficiencies as directed by the Engineer. After correcting the deficiencies, the Contractor shall again request a final inspection. Acceptance of the Project does not relieve the Contractor of financial liabilities imposed on the Contractor by statute and does not constitute final acceptance of the Contract.

1516.3COMPLETION OF THE WORK

The Department will consider the Work in all things completed when the Contractor has completed and submitted required documents, certifications, and affidavits including, but not limited to, the following:

(1)MN IC134 Withholding Affidavit, certified by Minnesota Department of Revenue,

demonstrating compliance with Minnesota Statutes, section 290.92

(2)Material certifications and warranties
(3)The Department’s written clearance confirming that all certified payrolls have been

submitted and determined to be compliant

(4)The Department’s written clearance confirming that all documents have been submitted

pertaining to small business, tribal, workforce and on the job training participation, as applicable

(5)Payment of moneys owed to the Department, if applicable
(6)Termination of NPDES Permit, if applicable
(7)All other forms required by the Contract

1516.4FINAL CONTRACT ACCEPTANCE

The Department will make final Contract acceptance when the following occur:

(1)Work has been in all things completed to the satisfaction of the Department
(2)All parties have executed the Certificate of Final Acceptance

Get an email when 1516 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 64–0 of 1,081. View official source ↗