The Contractor is responsible for the following:
progress
Work subcontracted
Contract At the preconstruction meeting, the Contractor shall designate in writing a competent Superintendent and a competent individual (if different) for the Project . The competent Superintendent and the competent individual may be the same person, if constantly available in person on the Project and qualified in accordance with the requirements in this section. The Contractor may change the designated competent Superintendent or designated competent individual during the Project by submitting an authorized change in writing to the Engineer . The Engineer must receive the authorized change in writing before the designated Superintendent or competent individual performs Work on the Project.
1506.1COMPETENT SUPERINTENDENT
For the duration of the Contract, the Contractor shall act as a competent Superintendent or provide a competent Superintendent to act on the Contractor’s behalf . Ensure availability of the competent Superintendent on the Project within 24 hours’ notice to perform the following:
complete the Work
1506.2COMPETENT INDIVIDUAL
For the duration of the Contract, the Contractor shall provide a competent individual on the Project during the Work who is:
If the Contractor does not employ the competent individual, the Contractor shall authorize the competent individual, in writing, to perform the functions of the competent individual specified in this subsection.
Get an email when 1506 changes
Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.