702.01 Description
Mobilization consists of costs incurred for preparatory work and operations that must be performed before beginning work on the project site.
702.02 Equipment
Reserved.
702.03 Materials
Reserved.
702.04 Construction Requirements
Prepare and move personnel, equipment, and materials to project site.
702.05 Method of Measurement
The Engineer will measure as specified in Section 109.01, “Measurement of Quantities”.
702.06 Basis of Payment
Payment for mobilization will be based on Table 702-01: Table 702-01 Original Contract Amount Earned Payment will be the Lesser of: Bid Amount Original Contract Amount 5% 25% 2.5% 10% 50% 5.0% 50% 100% 7.5% 75% 100% 10.0% Upon completion of all work on the project, the Department will make payment for any amount bid for Mobilization in excess of 10 percent of the original Contract amount. Such payment is full compensation for furnishing all materials, equipment, labor, and incidentals to complete the work as specified. Pay Item Pay Unit Mobilization Lump Sum Section 704 309 SECTION 704 TEMPORARY TRAFFIC CONTROL
704.01 Description
This work consists of furnishing, installing, and maintaining all required traffic control devices, personnel, and necessary precautions for protecting the public and workers.
704.02 Equipment
Reserved.