1 The engineer will measure:
required for the placement of the selected mechanical splices will not be measured for additional payment.
pound [kilogram] for the quantity specified. 2 The department will pay as follows:
Pay Item
Pay Unit
Measure to the Nearest
Mechanical Splices Reinforcing Steel
LS, EA [Ea] LS, LB [LS, kg] LS, LB [LS, kg]
LS, EA [Ea] LS, lb [LS, kg] LS, lb [LS, kg]
Reinforcing Steel (Coated)
496
Pay to the Nearest LS, EA [Ea] LS, 10 LB [LS, 5 kg] LS, 10 LB [LS, 5 kg]
Removal of Bridge Deck Concrete
515.1DESCRIPTION
1 This section describes the requirements for scarifying, hydro-demolition, and removing
unsound and delaminated areas of concrete.
515.2MATERIALS--Vacant
515.3EQUIPMENT
515.3.1 Surface Preparation Equipment for Class I-A, Class I-B, Class II-A and Class II-B 1 Provide sawing, mechanical scarifying, sandblasting equipment, and all other tools
necessary to complete the work.
Provide power-driven hand tools to remove unsound concrete. With the engineer’s approval, jackhammers heavier than the nominal 30-pound [14 kg] class or 60-pound [27 kg] hammers with a spade at least 6 in [150 mm] wide may be used.
Provide self-propelled mechanical scarifying equipment capable of accurately establishing profile grades by referencing from the existing deck or from an independent grade control. Ensure that the equipment has the following:
depth of cut; and
515.3.2 Surface Preparation Equipment for Hydro-Demolition 1 Provide hydro-demolition equipment that is a computerized, self-propelled machine that
utilizes a high pressure water jet stream. Ensure the hydro-demolition equipment is capable of removing the depth of concrete shown in the contract, and specified unsound concrete. Provide vacuum cleanup equipment that is capable of removing wet debris and water.
agent to observe the initial set-up of the equipment and to assure that the removal operation is progressing to the satisfaction of the engineer. Ensure the agent has proven experience with hydro-demolition removal operations. Ensure the agent is
497
Removal of Bridge Deck Concrete