TEMPORARY TRAFFIC CONTROL – GENERAL
424 801.3.2 Notifications to the Engineer.
of proposed restrictions beyond those specified in the contract.
engineer approval before the start of work.
detector and immediately notify the TMC after reinstalling the loop detector.
following:
construction activities that might interfere with property access.
written confirmation of the notice. 801.3.3 Pavement Edge Drop -offs and Vertical Differences.
accordance with the DE MUTCD .
in accordance with the applicable sections of this specification.
Section 6G.20 of the DE MUTCD . Mark and protect the drop -off hazard with temporary barriers, barricades, or warning signs.
clear zone that will not receive backfill material before the end of the day.
the State of Delaware when using steel plates larger than those specified in the Standard Construction Details . Obtain approval before starting construction. Ensure that the shop drawings:
trench failure. TEMPORARY TRAFFIC CONTROL – GENERAL
425 b. Show details of the plating design, the method of fastening the plates, plate thickness, span, bearing, and the method of preventing plate movement.
without the engineer’s approval. 801.3.4 Temporary Pavement Markings.
require permanent pavement markings before returning traffic to unrestricted roadway use.
contract or as directed by the engineer.
Section .
marking Section , the DE MUTCD , and DelDOT’s Temporary Pavement Markings Policy of the DE MUTCD , when the contract does not provide a layout for temporary markings.
868. The Department will not allow painting over the conflicting pavement markings unless specifically allowed by the contract.
construction, submit detailed drawings showing the existing elements for each project location. Include lane and shoulder widths, turn lane lengths, locations of stop bars, turn arrows, crosswalks, and railroad crossings in the drawings.
801.3.5 Travel Lane and Road Closure Restrictions.
freeways, expressways, or principal arterials during the following holidays, unless otherwise noted in the contract:
Thanksgiving Day
observed holiday falls. The following schedule determines the periods of time the lanes must remain open, unless otherwise allowed by the contract: TEMPORARY TRAFFIC CONTROL – GENERAL
426 Table 801.3 -1. Holiday Lane Closure Restrictions by Day of the Week Day of Holiday or Event Time All Lanes Must be Open to Traffic Sunday 12:00 PM Friday through 5:59 AM Monday Monday 12:00 PM Friday through 11:59 PM Monday Tuesday 12:00 PM Monday through 11:59 PM Tuesday Wednesday 12:00 PM Tuesday through 11:59 PM Wednesday Thursday 12:00 PM Wednesday through 11:59 PM Thursday Thursday (Thanksgiving) 6:00 AM Wednesday through 11:59 PM Sunday Friday 12:00 PM Thursday through 5:59 AM Monday Saturday 12:00 PM Friday through 5:59 AM Monday
primary and general elections that fall during an even numbered year.
engineer. 801.3.6 Non -Compliance.
justification for suspension of work in accordance with Section 104. 2.D. The Department will continue assessing time charges until the contractor corrects the deficiencies.
traffic control.
801.4Method of Measurement.
The Department will not measure this item.
801.5Basis of Payment.
payment will constitute full compensation for:
TEMPORARY TRAFFIC CONTROL – GENERAL
427 B. The Department will consider the cost to move temporary traffic control devices in accordance with the TTCPs or as necessary to address safety issues as included in this item.
including approved time extensions, the Department will hold the contractor responsible for providing and maintaining the necessary temporary traffic control devices required to complete remaining work. The Department will not pay for providing or maintaining traffic control beyond expiration of the contract time.
construction item.
ITEM DESCRIPTION UNIT 801000 MAINTENANCE OF TRAFFIC LS ARROW BOARDS SECTION 802
428 SECTION 802 — ARROW BOARDS
802.1Description.
This work consists of providing, placing, relocating, and maintenance of portable arrow boards.
802.2Materials.
Not applicable .
802.3Construction.
Use and place arrow boards in accordance with the applicable sections of the DE MUTCD . Provide a trailer in accordance with Title 21 Motor Vehicles of the Delaware Code . Maintain arrow boards in good working order so that the arrow board meets, at a minimum, the “marginal” criteria of the brochure entitled “ Quality Guidelines for Temporary Traffic Control Devices ” in accordance with Section 801.3. Remove arrow boards from the roadway when not in use. Do not store arrow boards along the shoulder or adjacent to the edge of the roadway within the clear zone. 802.3.1 Equipment. Provide solar powered arrow boards with a double pointed arrow configuration capable of displaying a left arrow, a right arrow, a double arrow, or a 4 -corner caution mode. Do not display a sequential chevron. Equip the back panel of arrow boards with 3 ind icator lamps indicating the proper functioning of the board. Provide arrow board types as indicated in the table below: Table 802.3 -1. Arrow Board Minimum Size by Type Arrow Board Type Minimum Size A 48 x 24 inches B 60 x 30 inches C 96 x 48 inches
802.4Method of Measurement.
The Department will measure arrow boards as the number of arrow boards used each day. A day consists of any approved usage within 24 -hours of placing the device. The Department will measure each arrow board only once per 24 -hour period, regardless of how many times the contractor relocates the arrow board within the same project. When the contractor uses an arrow board for part of a day, the Dep artment will measure it as 1 each day.
802.5Basis of Payment.
arrow boards at the contract unit price for each arrow board per day, including the static arrow (W1 -6) sign, when applicable.
ITEM DESCRIPTION UNIT 802001 ARROW PANELS, TYPE A EA-DY