846.1Description.
This work consists of providing and placing loop detectors.
846.2Materials.
846.3Construction.
846.3.1 Loop Wire Installation.
Section 762. Remove sharp edges in the saw cut and round the corners. Blow out the saw cut with compressed air to remove loose material before sealing.
cover.
the saw cut.
of the loop detector installation and before sealing saw cuts. If the resistance to ground is less than 100 megaohms, remedy the work.
the manufacturer’s directions. Protect the saw cut area from traffic until the sealer has set. Place a minimum of 1 inch of sealer on top of the loop detector wire and finish flush with the pavement. Seal any drilled holes in the pavement.
wires from the end of the saw cut to a junction well. Twist the wires a minimum of 5 wraps per
foot in a parallel direction, and tape every 12-inches to 18-inches from the end of the saw cut to a junction well up to the splice.
inch rotary drill hole between the edge-of-pavement, curb, or sidewalk and the junction well, in accordance with the contract. Install loop detector lead-in wire through the rotary drill hole into the junction well and splice accordingly.
length of 1 1/2-inch galvanized rigid metal conduit and weatherproof fitting between the rotary drill hole and junction well, in accordance with the contract. Install the loop detector lead-in wire through the rotary drill hole, 1 1/2-inch conduit, and junction well and splice accordingly.
through the saw cuts and through the conduit. 846.3.2 Home-run Wire Installation.
the contract for details. 846.3.3 Splicing.
contract. Solder conductors side-by-side, with the exposed copper aligned. Twist the copper clockwise to achieve a mechanical connection. Coat the splice with flux, heat with a soldering iron, and solder with a rosin core solder. Insulate each soldered connection with heat-shrink tubing.
splicing kit. Install an approved splice kit in accordance with the manufacturer’s instructions. The Department will perform a continuity test at the cabinet after application of the splicing kit.
Department’s ITS technician will make the determination if the splice is watertight or not or if wires are crossed or mislabeled.
shrink tube or the open end of the end cap of heat-shrink tubing after contraction.
846.4Method of Measurement.
The Department will measure the quantity of loop detector wire or conduit as the number of linear feet of saw cut where loop detector wire is placed, sealed, and accepted. The Department will include the length of loop wire installed between the saw cut and the junction well in this measurement.
846.5Basis of Payment.
accepted at the contract unit price. Price and payment constitutes full compensation for:
with loop wire provided, placed, and accepted at the contract unit price. Price and payment constitutes full compensation for:
ITEM DESCRIPTION UNIT 846001 PROVIDE AND INSTALL LOOP WIRE 1-CONDUCTOR #14 AWG ENCASED IN 1/4” FLEXIBLE TUBING IN A LOOP SAWCUT LF 846002 PROVIDE AND INSTALL A 1 1/2-INCH GALVANIZED RIGID METAL CONDUIT DETECTOR SLEEVE WITH LOOP WIRE LF