Pavement Surface Tolerances (in./mi.) Required Corrective Action Through Lanes Acceleration Lanes* Deceleration Lanes* Ramps* 2" Surface Recycled Asphalt/Hot In-place Recycled Asphalt Pavement Cold Recycle Asphalt Construction Profile Index per Section of 30 or less for an individual trace Profile Index per Section of 40 or less for an individual trace Correct all bumps and dips**. Profile Index per Section greater than 30 for an individual trace Correct the Profile Index of each individual trace to 30 or less per section**. Profile Index per Section greater than 40 for an individual trace. Correct the Profile Index of each individual trace to 40 or less per section**. Profile Index per Section greater than 40 for an individual trace Profile Index per Section greater than 50 for an individual trace. Suspend the paving operations until corrective actions are taken to improve the paving operations. *Acceleration/deceleration lanes include the taper. Acceleration lanes that become through lanes are limited to 500 feet from the nose of the ramp. Ramps are from the nose to the intersection of the adjoining road. **Correct all areas within each section having high or low points (bumps or dips) with deviations in excess of 0.4 inches in a length of 25 feet or less regardless of the profile index value. 603 - ASPHALT PAVEMENT SMOOTHNESS
600-36 f. Corrections. Make the required corrections for pavement smoothness before making the pavement
thickness determinations. Use these methods for corrections: diamond grinding when the layer is the final riding surface when the layer will be covered with an asphalt seal or microsurfacing micro-milling or fine-lace milling (minimum of 60 teeth per foot) may be done in a continuous 100- foot segment provided there is at least 400 feet of the surface adj acent to the segment that is not milled or diamond ground diamond grind when more than 100 feet within a 400-foot segment requires correction. The Engineer may permit micro-milling if in the opini on of the Engineer the resulting surface is not detrimental to the functionality of the asphalt seal or the microsurfacing milling if the layer will be covered by another action remove and replace the entire pavement thickness remove the surface by milling, and replace the specified surface course overlay (not patch) with the specified surface course other methods that are approved by the Engineer Apply the corrective measure to the full-lane width of the pavement. The corrected areas shall have uniform texture and appearance. The beginning and ending of the corrected areas shall be squared normal to centerline of the paved surface. When grinding is performed, use vacuum equipment or other continuous methods to remove grinding slurry and residue. Remove from the project and properly dispose of the material. Do not allow the grinding slurry to flow across lanes being used by traffic, onto shoulder slopes, into stre ams, lakes, ponds or other bodies of water, or gutters or other drainage facilities. Do not place grinding slurry on foreslopes.
g.New Construction Bid Items in SECTIO N 602, and Eligible for Pay Adjustments. After the profilograph traces have been evalua ted, make corrections according to TABLE 603-3. TABLE 603-3: GRINDI NG REQUIREMENTS Condition Action* Greater than 25% (132 feet) of the 0.1 mi. section requires correction Continuously grind the entire 0.1 mi. section.** Greater than 25% (1320 f eet) of 1.0 mi. segment require correction Continuously grind the entire 1.0 mi. segment, when the areas requiring correction are dispersed throughout the 1.0 mi. segment. If the areas re quiring correction are isolated to 1/3 or ½ mi. within the 1.0 mi. segment, then only grind that 1/3 or ½ mi. * Continuously grinding requires a minimum of 98% of the pavement be ground. **If the skip length between areas to be ground (either within a 0.1 mi. section or between 0.1 mi. sections) is less than eith er grind length, combine the grinds so the area betw een is also ground. This additional gr ound area (area between) will apply to the computation of the 25% of the 0.1 mi. section. If the Contractor elects or is required by TABLE 603-3 to continuously grind the entire project, the following apply: the areas excluded in subsection 603.3a. are not required to be ground; at intersections constructed with multiple transiti ons for drainage (especially in urban areas), if smoothness meets SECTION 603 , the intersection is not required to be ground; and when transitioning from a ground area to an ungro und area, feather the grinding a uniform distance throughout the project. Grind and texture the entire surface of the pavement in the longitudinal direction. Provide positive lateral drainage by maintaining a constant cross slope between grinding passes in each lane. Maintain a uniform transverse slope that matches the existing cross slope to the extent possible with no depressions or humps greater than 1/4 inch in 12 feet when tested with a string line or straightedge. Do not exceed by more than 1/16 inch the vertical alig nment between adjacent passes of the cutting head. Be gin and end gr inding lines normal to the direction of vehicle travel. Grind the surface so corrugations are parallel to the pavement edge with ridges 1/16 inch, ±1/32 inch higher than the valleys of the corrugations. 603 - ASPHALT PAVEMENT SMOOTHNESS 600-37
g.Profilograms. After pavement sections are corrected, re -profile the pavement surface to verify compliance with the specified pavement smoothness. Provide the Engineer with the profilograms and their evaluation within 2 working days afte r correcting the pavement surface. The Engineer may perform profilograph testing on the pavement surface for monitoring and comparison purposes. If the Engineer determines th at the Contractor’s certified test resu lts are inaccurate, the Engineer may choose to test the entire project length. The Engineer will charge the Contractor for such testing at the rate of $500 per mile per profile track, with a minimum charge of $1000. Providing inaccurate test re sults may result in de-certification of the Contractor’s certified operator. 603.4 MEASUREMENT AND PAYMENT
a.General. The Engineer will base the pay adjustment for pavement smoothness on the initial average profile index of the pavement section before any corrective work is performed. If the Contractor elects to remove and replace a pavement section, the Engineer will base the pay adjustment for pavement smoothness on the initial average profile index of the pavement section after the replacement. For reconstruction projects, if the C ontractor elects or is required by TABLE 603-3 to continuously grind the entire project, pay adjustments will be based on the average profile index determined after all grinding is performed.
b.New Construction, Bid Items in SECT ION 602, Eligible for Pay Adjustments. The Engineer will apply the contract price adjustment according to TABLE 603-4 . Payments for "Asphalt Pavement Smoothness" are an added item to the contract. TABLE 603-4: ASPHALT PAVEMENT SMOOTHNESS PAY ADJUSTMENT NEW CONSTRUCTION Average Profile Index (in./mi. per lane per 0.1 mi. section) Contract Price Adjustment (per 0.1 mi. section per lane) 6.0 or less +$1000.00 6.0 to 10.0 +$835.00 10.1 to 15.0 +$625.00 15.1 to 18.0 +$310.00 18.1 to 30.0 0.00 30.1 to 40.0 0.00* 40.1 or more -$615.00* *Correct to 30.0 in./mi. (40.0 in./mi. as noted in TABLE 603-1 ). The pay adjustments in TABLE 603-4 are for 12" thick hot mix asphalt and 8" thick portland cement concrete pavements. Pay adjustments for pavements of different thicknesses will be reduced or increased proportionally, based on the typical section for the extent. (i.e. pay adjustment for a 9" hot mix asphalt pavement is equal to the adjustment from the TABLE 603-4 multiplied by 0.75).
c.Rehabilitation Construction, for all Other Bi d Items in DIVISION 600 and Eligible for Pay Adjustments, Take the Required Correcti ve Actions According to TABLE 603-5 . The Engineer will apply the contract price adjustment according to TABLE 603-5 . Payments for "Asphalt Pavement Smoothness" are an added item to the contract. TABLE 603-5 ASPHALT PAVEMENT SMOOTHNESS PAY ADJUSTMENT REHABILITATION CONSTRUCTION Average Profile Index (in./mi. per lane per 0.1 mi. section) Contract Price Adjustment (per 0.1 mi. section per lane) 7.0 or less +$152.00 7.1 to 10.0 +$76.00 10.1 to 30.0 0.00 30.1 to 40.0 0.00* 40.1 or more -$203.00* *Correct to 30.0 in./mi. (40.0 in./mi. as noted in TABLE 603-1 ). 604 - COLD RECYCLED ASPHALT CONSTRUCTION (CIR)
600-38 Section 604
COLD RECYCLED ASPHALT CONSTRUCTION (CIR) 604.1 DESCRIPTION Mill the asphalt pavement, mix the reclaimed asphalt pavement (RAP) material with hydrated lime slurry (use a minimum of 1% hydrated lime, based on the dry weight of the RAP) and emulsified asphalt, and spread and compact the mixture as specified in the Contract Documents. B I D I T E M S U N I T S Cold Recycled Asphalt Material Station L i m e ( H y d r a t e d ) ( S l u r r y ) T o n Emulsified Asphalt (CSS) (Special) Ton Emulsified Asphalt (CSS-1H or SS-1H) Cure (Set Price) Ton Blotter Sand (Set Price) Cubic Yard 604.2 MATERIALS Provide materials that comply w ith the applicable requirements. Emulsified Asphalt ................................................................................................ DIVISION 1200 Lime ...................................................................................................................... DIVISION 2000 Water ..................................................................................................................... DIVISION 2400 Blotter sand may be any fine sand approved by the Engineer. Provide processed RAP materi al that complies with TABLE 604-1 . TABLE 604-1: RAP MATERIAL FOR CIR Sieve Size % Retained 1 ¼" 0 Manufacture the hydrated li me slurry at the jobsite by slaking pebb le quicklime. Accompany each load of quicklime with a certification stating the purity for that load. 604.3 CONSTRUCTION REQUIREMENTS
a.Mix Design. Submit to the Engineer for approval a mix design complying with 5.3.4-Mix Design Procedures for CIR Material, Part V. Provide a technical representative from the asphalt emulsi on supplier on the job site at the beginning of the CIR to obtain proper asphalt emulsion performance. When required, provide a technical representative to check on the project and make adjustments to the asphalt emulsion formulation as needed.
b.Milling Operation. Mill the required depth and width in 1 or mo re passes. Process the RAP material to the required gradation and thoroughly mix with the specified amount of binder. Water may be added to the RAP material to facilitate mixing, provided it does not adversel y affect the binder. Deposit the recycled material in a windrow, a paver or load into trucks, without segregation. When deposited in a windrow, have equipment available to equalize the windrow as directed by the Engineer. If RAP is to become the property of the Owner, deliver and stockpile at locations shown in the Contract Documents. 604 - COLD RECYCLED ASPHALT CONSTRUCTION (CIR)
600-39 c. Mixing Operations.
1.Field Mixture Testing. Take all samples according to KT-1(3.1) or (3.2). Obtain a sample from each 0.6 mile before emulsion addition, and screened using a 1¼-inch sieve (or smaller sieve if required) to determine compliance with the maximum particle size requirement. Additionally, obtain 2 gradations each day and compare to the mix design gradations using KT-4 to determine any necessary changes to the emulsion content.
2.Asphalt Emulsion. Do not accept asphalt em ulsion with a temperatur e greater than 120ºF, TABLE
601-1 Sample and accept or reject from the shipping trailers prior to unloading into the C ontractor’s storage units.
3.Asphalt Emulsion Content. Check and record th e emulsion content for each segment in which the percentage is changed. Make emulsion content changes based upon mix design recommendations, which are based upon different mix designs for road segments of varying construction. Determine asphalt emulsion content from the belt scale totalizer and asphalt pump totalizer.
4.Lime Slurry Content. Add the amount of hydrated lime to the RAP determined by the mix design or directed by the Engineer, based on the weight of the dry RAP. Add pebble quicklime by weight to the required quantity of water to provide a uniformly hydrated lime slurry having a minimum dry solids content of 30%. When requested by the Engineer, determine the solids content of the hydrated lime according to “Che ck Percent Solids of Lime Slurry Procedure” (KT-62). Check and record the lime slurry content for each segment in which the percentage is changed. Make the lime slurry changes based upon mix design recommendations or as approved by the Engineer.
5.Water Content. Verify and record the water cont ent at the milling head for each segment in which the percentage is changed. Determine water quantities from the water metering device, and compare with the belt scale totalizer to determine daily quantities used. Make the water content adjustments based on mixture consistency, coating and dispersion of the recycled materials.
d.Paving Operations. Deliver the RAP, lime and/or water and em ulsion mixture to the paver immediately after mixing. The minimum temperature of the mixed materi al when placed is 50ºF. Pave in 1 continuous pass, utilizing an asphalt paver complying with SECTION 155 or other equipment approved by the Engineer. Without tearing the surface, spread and finish th e recycled material, to the lines and grades in the Contract Documents or established by the Engineer so it is smooth, free of segregation, uniform in density, texture and free from surface irregularities. Do not heat the paver screed. A pick-up machine may be used to transfer the windrowed material into the paver hopper. Maintain the asphalt paver within 150 feet of the mixing unit. If the process does not comply with these requirements, the Engineer will susp end paving until the deficiency is corrected.
e.Compaction and Density Requirements. Compaction and density requirements for each project shall be a minimum of 97% of the target density obtained on a test strip compacted under the following conditions: The minimum mix temperature of the test strip is 50ºF; Complete a minimum of 2 test strips to determine the target density and optimum sequence of rollers. These test strips shall remain in pl ace as part of the completed work; and The depth of the lift shall be representative of the requirements of the Contract Documents. Target density shall be the highest density achieved on the test strip using the rolling procedure approved by the Engineer. The rolling procedure used on the test strip shall have a minimum of 6 roller coverages. The Engineer will use a nuclear density gauge to establish a density growth curve for each procedure. Discontinue rolling when 4 consecutive coverages of the rollers fail to increase the density 1 pound per cubic foot. As a minimum, provide the following self-propelled rollers for use on the test strips: a double drum vibratory steel roller and a pneumatic tired roller. Provid e a vibratory roller complying with the requirements for hot asphalt pavement in subsection 151.5 and having a minimum operating weight of 10 tons and a minimum drum width of 6½ feet. The vibratory roller may be used in the static mode. Use a pneumatic tired roller with a minimum weight of 30 tons and a minimum tire pressure of 90 psi. The air pressure in each of the pneumatic tires shall be within 5 psi of each other. Suppl y a suitable tire pressure gauge. Change rolling or roller patterns when major displacement and/or cracking of the recycled material occur. Start rolling a maximum of 30 minutes after paving. Complete finish rolling a maximum of 1 hour after milling is completed. When possible, begin and end rolling sequences on previously compacted material or the existing pavement. 604 - COLD RECYCLED ASPHALT CONSTRUCTION (CIR)
600-40 Before and after opening to traffic, maintain the su rface of the recycled pavement in a condition suitable for
the safe movement of the traffic. Remove all loose particles that develop on th e pavement surface by power brooming. When there is a significant change in mix proportions, weather conditions or other controlling factors, the Engineer may require construction of a new test strip to check target density.
f.Surface Treatment or Overlay. When required by the Engineer, apply a light application of asphalt material (smoke coat) on the recycled surfa ce, and blot with fine sand, as necessary. Before placing a HMA surface course , or other applicable surface treatme nt, allow the CIR asphalt material to cure until the moisture of the material is a maximum of 2.0%, or approved by the Engineer. Under dry conditions, the CIR should comply with the moisture requirements within 48 hours. Cover each day’s production of CIR material with any subsequent treatment or overlay, as designated in the Contract Documents, within 21 calendar days. If the CIR material requires patching before the 21 days have expired, and damage is not the result of the Contracto r’s operations, KDOT will pay for the patching. If the Contractor has not covered the CIR material by the end of the 21-day period and the material requires patching, the Contractor shall be responsible for the patching. Begin patching within 3 days of being notified by the Engineer of required patching.
g.Maintenance of Traffic. Perform traffic control according to DIVISION 800 .
h.Weather and Seasonal Limitations. Complete milling, adding the liquid binder and laydown between May 1 and September 30, when the ambient air temperature is greater than 50°F and rising, the weather is not rainy or foggy and the weather forecast does no t call for freezing temperat ure within 48 ho urs after placement. The above requirement may be waived, when approved in writing by the Engineer.
i.Pavement Smoothness. Evaluate pavement smoothness according to SECTION 603 . 604.4 MEASUREMENT AND PAYMENT The Engineer will measure cold recycled asphalt material by the Station, along the centerline. On divided highways, the Engineer will measure cold recycled asphalt material by the Station, along the centerline of each divided direction. This includes all widened and irregular areas and irregular variations in depth. The Engineer will measure lime (hydrated) (slurry) and th e various types of emulsified asphalt by the ton. The Engineer will measure blotter sand by the cubic yard in the truck at the point of usage. The Engineer will not measure water for separate payment. Payment for "Cold Recycled Asphalt Material", "Lime (Hydrated) (Slurry)" and "Emulsified Asphalt (CSS) (Special)" at the contract unit prices and "Blotter Sand (Set Price)" and "Emulsified Asphalt (CSS-1H or SS-1H) Cure (Set Price)" at the contract set unit prices is full compensation for the specified work.