705 - STRUCTURAL STEEL FABRICATION - BRIDGES
700-27 (16) Shop Painting. Prepare the structural steel surfaces and shop pa int the prepared surfaces according to
SECTION 714 .
700-28 ¼, +¼ inch for spans 0 through 100 feet
- ⅜, +⅜ inch for spans greater than 100 feet Permissible variations in blocking of welded gird ers and rolled beams, regardless of cross-section, shall not exceed: 0 for all supports Sign convention: (-) below, (+) a bove the detailed values or sh ape in the no-load condition. Delete paragraph 3.5.1.9 and replace with the following: The bearing ends of bearing stiffeners shall be flush and square with the web and shall have no less than 75% of the end area in contact with the flanges. “Contact” is achieved when a 0.005 inch feeler gauge cannot be inserted between stiffener and flange. The gap between stiffener and flange for the rema ining “non-contact” area shall be no greater than 1/32 inch. For steel slabs, base plates, bearing devices, cap plates of colu mns and pedestals bearings against or welded to beams and girders, no less than 75% of the common area shall be in contact with the flanges. Do not exceed a 1/32 inch gap for the 25% “non-contact” area. Add 3 new paragraphs as follows: 3.5.1.16 The permissible variation in length of beams or girders between the center line of bearing devices shall not exceed plus or minus ¼ inch for any one span or plus or minus ⅜ inch for any two or more spans. The actual centerline of any bearing device shall lie within the thickness of the bearing stiffener. 3.5.1.17 During shop assembly of horizontally curved welded beams or girders, the allowable variation in specified sweep at internal supports shall be ¼ inch. 3.5.1.18 During shop assembly of horizontally curved welded beams or girders, the allowable variation in specified sweep at any point be tween supports shall be the greater of: ⅛ inch per 10 feet of length, calculated using the distance to the nearest support, or ¼ inch. SECTION 4. TECHNIQUE. Add the following notes to Table 4.1: Only low hydrogen electrodes shall be used. E 7028 Electrodes may be used for shop fillet welds except for the attachment of gusset plates and bearing stiffeners to girders, bearing stiffeners to beams, web to flange welds and for welding floor beam truss assemblies. Welding shall be in the horizontal and flat positions only. SUBSECTION 5.2 WPS QUALIFICATION RESPONSIBILITY Replace the first sentence of paragraph 5.2.3 with the following: All welder, welding operator, and tack welder and PQR tests must be witnessed by the Engineer, another state’s representative approved by the Engineer, or an independent third party approved by the Engineer. If representatives from other states or third parties witnessed a test, provide records of the test signed by the witness. All mechanical and nondestructive tests performed by independent laboratories on qualification specimens will be at no charge to the State. Provide signed documentation of the independent lab’s test results to the Engineer. When requested by the Engineer, allow KDOT access to the test samples and the independe nt lab’s radiographs for inspection. Delete paragraph 5.2.4 and replace with the following: 5.2.4 Additional Testing. The Engineer may order tests of welders, welding operators, tack welders, or WPSs whenever there is evidence that unacceptable welds are being or ha ve been produced. This additional testing is at the fabricator’s expense. The Engineer may disquali fy personnel working for the fabricator who fail the additional testing, who commit serious violations of the specifications, or who repeatedly exhibit poor workmanship on KDOT projects. Revise paragraph 5.2.5 as follows: Replace “those authorized to exam ine them.” with ”the Engineer.” SUBSECTION 5.21 GENERAL REQUIREMENTS FOR WELDER QUALIFICATION Add the following to paragraph 5.21.6.1: All tests must be witnessed by the Engineer, another state’s representative approved by the Engineer, or an independent third party approved by the Engineer. Revise paragraph 5.21.7 as follows: Replace “those authorized to exam ine them.” with ”the Engineer.” Add the following to paragraph 5.21.7: