by the Engineer. Temporary fencing materials will remain the property of the Contractor.
2.Trench Excavation. When necessary, excavate a trench to line and grade in areas of irregular ground to secure clearance between the ground line and the bottom of the fence fabric, or to permit placing steel fence wire below the bottom of the fence fabric at stream crossings. In areas where rock is encoun tered, excavate the rock as necessary to the required line and grade. Backfill any ex cavation of rock below the required grade with suitable materials as directed by the Engineer. Construct trenches to provide proper dr ainage. In general, the bottom of the fence will follow the contour of the ground according to sta ndard industry practice in constructing fence of the types specified.
b.Concrete Footings. When required, construct footings of commercial grade conc rete according to the Contract Documents. Volumetric proportioning and hand mixing of concre te is permitted for concrete footings where small quantities are required. Extend the top of the footing slightly above the ground line and steel trowel to a smooth finish with a slope to drain away from the post. Center posts, braces and other units in their footings. Set the posts and braces in advance of placing the fence to allow the concrete time to obtain its strength.
c.Posts Set in Rock. Where rock occurs within the required de pth to which fence posts are to be erected, drill a hole of a diameter slightly larger than the largest di mension of the post in the rock and grout in the posts. When shown in the Contract Documents, cast in place the concrete footing as specified in subsection 828.3b. , between the top of rock and the required grade. At lin e posts, where top of rock is 8 inches or less below the required grade, remove the anchor plate. At all line posts, backfill the excavation above the top of rock with excavation materials placed in 4 to 6-inch laye rs. Thoroughly tamp each layer in place.
d.Structure Terminals. Place structure terminal assemblies at a ll stock passes, crossr oad underpasses or overpasses and major drainage structures as shown in the Contract Documents.
e.Floodgates and Channel Crossings. Construct floodgates and channel crossings as shown in the Contract Documents.
f.Intermediate or Line Posts. Erect each post plumb, and horizontally line up all posts between horizontal angle points with no perceptible variation. Erect with line post spacing as uniform as practicable under local conditions, with maximum spacing as shown in the Contract Documents and a tolerance of minus 2 feet.
g.Pull Posts. Construct pull post assemblies (to the approximate spacing shown) in straight runs and at each vertical angle point as describe d in the Contract Documents.
h.Corner Posts. Place corner post assemblies at all horizontal angle points, and erect to comply with the measurement shown in th e Contract Documents.
i.End Posts. Construct end post assemblies in the line of the fence at all terminal points. When gates and flood gates are required, use end posts to attach the gate or flood gate.
j.Identification Signs. Provide and place identification signs as shown in the Co ntract Documents.
k.Erection of Gates. Provide all materials necessary to complete the installation of pedestrian and vehicular gates as shown in the Contract Documents. Carefully align all gates with posts vertical. Tigh tly assemble clamps used for attaching hardware. Construct the bottom of each gate 3 to 5 inches above the ground when clos ed, and to clear the ground by a minimum of 3 inches at all points in its swing. Modify the existing grade within the area of swing to meet this requirement, as directed by the Engineer. Direction of swing of gates will be shown in the Contract Documents. Install all gate stops as shown in the Contract Documents. For all gates, provide st ops with latches, or other approved means for holding gates open, and place to prevent damage to the gate or fence by over-swing. Provide stops to arrest the swing of a closed gate at the centerline of the fence. 828 - FENCING 800-79
l.Removal of Existing Fence. Remove the existing fence and stor e at locations as directed by the Engineer. Reset existing fence to be removed and reset, as shown in the Contract Documents. Provide all new materials n ecessary for resetting fence.
m.Erection of Woven Fence. Unless shown otherwise in the Contract Documents, either type of woven wire fence shown may be provided, but only one type may be used on a project. Place the bottom of the fabric of wo ven wire fence a nominal distance of 3 inches above th e ground line. However, over irregular ground, a clearance of 1 to 6 inches for a distance less than 8 feet is permitted. Perform any necessary excavation and backfilling requ ired to comply as specified in subsection 828.3a.(2) . Set all metal end, corner, pull and brace posts and all br aces in concrete footings as shown in the Contract Documents. The dimensions of the footings may be varied as permitted by the Engineer, but shall provide an equal volume of concrete. Except where rock is encountered, set or drive intermediate or line posts into the ground. Provide metal posts with an approved plate or other anchor device to hold the post plumb and in proper alignment. The plate or anchor shall be satisfactorily welded or riveted (not less than 2 rivets) to the post. Wood posts may be driven or set in pre-bored holds. Remove any posts damaged by driving. After posts are permanently positione d and concrete footings are fully set, place fabric by securing or fastening one end and applying sufficient tension to remove all slack before making permanent attachments. Fasten the lateral wires to end, corner and pull posts by wrapping the wires around the posts and tying the wire back on itself with a minimum of 5 twists wrapped tightly. Perfor m tying by using tools design ed for the purpose according to the fence manufact urer’s recommendation. Apply the tension for stretching the fence by use of mechanical fence stretchers and with single wire stretchers, according to the fence ma nufacturer’s recommendations. Securely make all splices in the fabric according to the fence manufacturer’s recommendations , and using tools designe d for that purpose. Fasten fence fabric to steel intermediate or line posts with ties or clamps, and to wood posts with staples at the bottom and top 2 wires and other alternate intermediate lateral wires. Where the design of the line post incorporates satisfactory provision for supporting and s ecuring the fabric wire to the post, the Engineer may eliminate tie wires or clamps.
n.Erection of Chain Link Fence. Set the posts sufficiently in advance of the placing of the fabric to allow the concrete time to obtain its design strength. Set the bottom of the fabric 3 inches above the finished ground line. Fasten the fabric to the tension wi res as shown in the Contract Documents.
1.Post Spacing and Setting. Set posts with a maximum spacing of 10 feet and set a minimum of 2 ½ feet below the finished surface of the ground in concrete footings as shown in th e Contract Documents. Construct the concrete footings of a size and shape shown in the Contract Documents. (2) Fabric bands with fasteners. Fasten fabric to line posts with aluminum or galvanized fabric bands spaced approximately 14 inches apart. Securely fasten the fabric to the end posts by approved type metal fasteners.
o.Erection of Barbed Wire Fence. Erect the fence as shown in the Contract Documents. For intermediate or line posts, use either wood or metal posts of the type shown in the Contract Documents, but only one type may be used on the project, Excavate holes for wooden posts on line and to the depth shown in the Contract Documents, and of sufficient size to permit adequate compac tion of the backfill around the post. Set corner posts and support posts, and securely brace and wire before setting the intermediate posts. Space the intermediate posts equal distances apart, 13 ½ feet maximum. Set the posts plumb, firm and true to designated line and grade. If not set in concrete, place the backfill around the posts in thin layers and thoroughly compact. If metal posts are used for the intermediate posts, dr ive with an approved mech anical device to the depth shown in the Contract Documents. Use brace wire consisting of 2 complete loops of No . 9 smooth, galvanized wire. Twist the loops both above and below the brace post until tight. Draw barbed wire taut with an approved mechan ical device and securely fasten to each post with a minimum of 1 fence staple or approved wire clip. Loop the wire around the end and corner posts, and fasten with sufficient staples to anchor the wire securely. 828 - FENCING