necessary to determine the length of each sign post. Provide the Engineer with the vertical and horizontal measurements from the top of the pavement edge to: the ground line (for posts with no footings) the top of the footing (for posts with footings) the top of the stub post base plate (for steel beam breakaway posts) If the Contract does not include the item of Contractor Construction Staking, the Engineer will obtain the measurements necessary to determine the length of each sign post.
1.Footings.
a.Post Holes for Wood Posts. Excavate the post holes to the shape and dimensions shown in the Contact Documents. Prevent water from entering the excavated holes.
b.Concrete Footings for Wood Posts and Steel Beam Stub Posts. Excavate the footings to the shape and dimensions shown in the Contract Documents. Remove all non-compacted material from the excavation. Form the t op 12 inches of the footings. Pl ace the reinforcing steel and post sleeves or stub posts in the footings as shown in the Contract Documents. Vibrate the concrete placed in the footings and finish the footings as detailed in the Co ntract Documents. Backfill the footings as detailed in the Contract Document s, placing the backfill soil in uniform layers (maximum layer of 8 inches, loose measurem ent), and compact each layer until no further consolidation is observed.
c.Perforated Square Steel Tube Post Footings. Install the perforated square steel tube post footings plumb as shown in the Contract Documents. Do not damage the galvanized coating during installation or alter the cross-sectional dimensions of the perforated square steel tubes. Remove and replace any footing damaged during the perforated square stee l tube installation.
d.Expanded Foam Foundations. When a concre te footing is not specified, expanded foam foundations may be used on Sign Post (4" x 6"), Sign Post (4" x 6" Wood) ( * 2), and Sign Post ( *5 Perforated Square Steel Tube). The post hole must be dry or damp with no standing water. Install the foam foundation and post according to the manufactur er’s instructions. Do not substitute a concrete footing with expanded foam.
2.Post Installation. Install the posts as shown in the Contract Documents. Plumb the sign posts as they are installed. The maximum allowable tole rance from vertical is 1 inch (from the top of the post to the ground line).
a.Wood Posts in Soil. Place the posts in the post holes, plumb the posts and backfill with the soil from the post hole excavation in uniform layers (maximum layer of 8 inches, loose measurement) around the posts, and compact each layer to the or iginal ground line until no further consolidation is observed. After backfilling, drill breakaway holes in the posts as shown in the Contract Documents. Treat the breakaway ho les with preservative materials.
b.Wood Posts in Concrete Footings. After curi ng, place the posts into the post sleeves, plumb the posts, secure the po sts with wedges and seal the gaps be tween the posts and the post sleeves with asphalt material. Drill breakaway holes in the posts as shown in the Contract Documents after the posts are secured. Treat all field cuts and drilled holes in wood posts with materials for preservative treatment.
c.Steel Beam Breakaway Posts. After curing, place the steel beam post with base plate onto the stub post base plate, plumb the post and tighten the base plate bolt assemblies as detailed in the Contract Documents. Att ach the structural tubing to the steel posts.
d.Perforated Square Steel Tube Posts. Install and attach the perforated square steel posts in the footings as detailed in the Contract Documents.
e.Steel "U" Posts. Install the posts by driving. Do not alter the cross-sectional dimensions of the posts or damage the coating during insta llation. Remove and replace damaged posts.
f.Assemble the sign post square couplers according to the manufacturer’s instructions.
e.Sign Installation. Mount the signs as shown in the Contract Documents. Position the signs so the sign face is vertical. If required for inst allation, drill the holes in the fabricated signs from the sign face sheeting side. After the sign is installed, the post shall be plumb and secure in the ground. 812 - PERMANENT SIGNING