1003.1 1003.4
1003.1DESCRIPTION —This work is the drilling of holes for dowels and the grouting of the dowels in place.
1003.2MATERIAL —
• Nonshrink Grout . Section 1001.2(e)
1003. 3 CONSTRUCTION —Drill holes for dowels at the locations and to the diameter and depth as indicated. Grout the dowels in place, using nonshrink grout to form a complete bond between the dowels and the concrete. Repair structure damage caused by dowel operations.
1003.4MEASUREMENT AND PAYMENT —Each
1005. 1 1005. 2 1005. 1 DESCRIPTION —This work is the furnishing and driving of new, unused test piles and production piles. The following definitions apply: (
and establis h the predetermined pil e tip elevation, befor e drivi ng production piles. Test piles may als o be used to per form pile l oad tests.
static load.
of a dynamic load and measuring the force and velocity response with a high strain dynamic load testing system. A dynamic pile load test may include post -driving analysis .
capacity and integrity through instrumentation of the pile with accelerometers and strain gauges during dynamic pile load t esting. (e)P roduction Pile. A pile installed to provide structural support as part of the permanent foundation. (
defined bedrock. (
in a dense or hard bearing stratum such as soft or decomposed bedrock, or hard or dense soil . (
pile shaft . (
(
of penetration. (
(
Engineer or District Geotechnical Engineer from the test pile(s) . The predetermined pile tip elevation locates the intended bearing strata for point bearing or end bearing piles or establishes the length of friction piles. Predetermined pile tip elevations are used to verify or adjust the estimated pile tip elevations indicated. ( m)Maxim