Structures (1000-1099)

1045PROTECTIVE COATINGS FOR CONCRETE SURFACES

PA · 2026 Standard SpecificationsBook pages 11311135View official source ↗

1047. 2(e) 1047. 3(b)

• Have at least 95 % passing the No. 8 sieve and at least 95% retained on the No. 20 sieve when tested according to AASHTO T 27.

• Must be dry at the time of application.

• Material components are supplied collectively through the System Provider. Aggregates to be supplied by the System Provider and delivered in packaging to the site clean and dry.

(f)Certification. Certify the PPC overlay system as specified in Section 106.03(b)3. Along with the

certification , provide independent testing for the HMWM primer, PPC resin, aggregate, and PPC mixture to verify compliance with the material req uirements as specified in Tables A, B, C, D, and E. Provide i ndependent testing for the aggregate and PPC mixture from an AASHTO certified laboratory . Provide i ndependent testing for HMWM primer, PPC resin from an ISO certified laboratory. Perform testing within 12 months of furnishing materials to the project.

1047.3CONSTRUCTION

(a)Qualifications.
1.Installer. Submit up to three projects demonstrating experience installing PPC. For installers with

no PPC installation experience, list a minimum of three projects demonstrating bridge deck or latex overlay placement experience .

2.System Provider. Submit documented evidence of having successfully supplied a complete PPC

overlay system on at least five projects of similar size and scope within the last 5 years.

3.System Provider Technical Representative . Submit documented evidence having successfully

provided technical support on at least five projects of similar size and scope within the last 5 years.

(b)Submittals .
1.Quality Control (QC) Plan. As specified in Section 106.03(a)2.a, submit a project specific QC

Plan for approval a minimum of 30 calendar days before material placement. The onsite System Provider's Technical Representative is required to review and approve the plan. Deviations from the approved QC Plan are to be approved by the Representative. Discuss the QC Plan at the pre-placement meeting. Deviation from the approved QC Plan will be cause for immediate suspension of operations. The QC Plan is to include key personnel, equipment, materials, mixing procedures, safety, proposed methods of installation and operation, and the following :

1.a QC Plan Administrator . Provide name of person having f ull authority to institute action necessary for the successful operation of the QC Plan. The QC Plan Administrator is responsible for the following:

1.a.1 Procedures. Identify and provide procedures in the QC Plan for the following:

• Safety Procedures.

• Documenting the storage procedures for PPC resin, HMWM primer and aggregates.

• Documenting areas and quantities used of PPC resin and aggregate at

Source: Pennsylvania Department of Transportation Specifications, 2026 Edition. Pages 11311135 of 1,522.