1023.1DESCRIPTION—This work is construction of an aluminum bridge hand railing.

1023.2MATERIAL—

(a)Railing.

• Pipe for the Rails. ASTM B241-Alloy 6061-T6, 6063-T6 or ASTM B429-Alloy 6061-T6, 6063T6.

• Plates. Alloy 6061-T6.

Certify as specified in Section 106.03(b)3.

(b)Toggle Bolts. Use an acceptable galvanized type capable of supporting a 1,000 -pound load in

tension, when tested through a 1/2-inch round hole. Toggle bolts may be cadmium-plated to conform to the requirements of ASTM B766, Class 5, in place of being galvanized. Certify as specified in Section 106.03(b)3.

(c)Aluminum Wedges, Shims, End Caps, Washers, and Nuts. Certify as specified in Section

106.03(b)3

(d)Anchor Bolts, and Nuts and Washers for Anchor Bolts. Section 1105.02(c)2, galvanized as specified

in Section 1105.02(s).

(e)Caulking Compound. Section 705.7

1023.3CONSTRUCTION—Construct as shown on the Standard Drawings and as follows:

(a)General. Before fabrication, submit shop drawings for review and acceptance.

Coat surfaces of aluminum alloys in contact with other metals, stone masonry, or concrete, using caulking compound, before erection. Use caulking compound to seal openings between metal surfaces and concrete after erection and alignment. Protect the railing from damage or accumulations of oil, grease, dirt, concrete splatter, or foreign materials. After the other bridge construction operations have been completed, clean the aluminum bridge hand railing. Remove accumulations of oil, grease, dirt, or foreign materials, using an acceptable solvent cleaner.

(b)Assembly. Assemble the rail members. Place joints as indicated.

Make cuts true, smooth, and free from burrs or ragged edges. Fillet drill all re-entrant cuts before cutting. Do not flame cut. Weld as specified in Section 1105.03(m).

1023.4MEASUREMENT AND PAYMENT—Linear Foot

Measured from center to center of end posts. The Department will not deduct gaps at lighting pole foundations.

1025 – 1

Get an email when 1023 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 1077–0 of 1,522. View official source ↗

Ask about this section

Scoped to Pennsylvania Publication 408 — Specifications, Section 1023 — ALUMINUM BRIDGE HAND RAILING. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.