214.03 CONSTRUCTION METHODS . At least thirty (30) days prior to starting hydrodemolition
operations, the Contractor shall submit for the Engineer’s approval the proposed storage area and maintenance plan for the hydrodemolition runoff. The submission shall consist of two elements: the containment/sedimentation system and the maintenance procedures. 214.03.1 Containment System for Control of Hydrodemolition Runoff . If the project is within the jurisdiction of the Rhode Island Department of Environmental Management (RIDEM) or the Coastal Resources Management Council (CRMC), the containment system must be constructed in accordance with permit conditions and approved plans. Otherwise, the Contractor shall be responsible for obtaining the necessary approvals prior to beginning hydrodemolition activities. Copies of all such approvals shall be provided to the Department.
214.04.1 “Containment System for Control of Hy drodemolition Runoff” does not require a
measurement for a lump sum payment. 214.04.2 “Maintenance and Disposal of Hydrodemolit ion Runoff” will be measured by the number of days where actual hydrodemolition takes place in accordance with the Plans and/or as directed by the Engineer. 214.05 BASIS OF PAYMENT .
214.05.1 “Containment System for Control of Hy drodemolition Runoff” will be paid for at the
contract lump sum price as set forth in the Proposal. The price so-stated constitutes full compensation for establishing a suitable sedimentation basin for the hydrodemolition runoff, all materials, labor, tools, equipment, and earthwork associated with providing the basin, erosion control, snow fence, removal of all materials and restoration of all ground surfaces disturbed in the installation and operation of the system, and all incidentals necessary for the proper completion of the work specified and shown on the Plans, complete and accepted by the Engineer. 214.05.2 “Maintenance and Disposal of Hydrodemolition Runoff” will be paid for at the contract unit price per day as listed in the Proposal. The price so-stated constitutes full compensation for transportation and disposal of the hydrodemolition wast ewater, all materials, labor, tools, vehicles, any necessary permits and approvals required to complete the disposal, and all incidentals necessary for the proper completion of the work specified and shown on the Plans, complete and accepted by the Engineer. 3−1PART 300 AGGREGATE AND GRAVEL BASE AND SUBBASE COURSES SECTION 301 AGGREGATE AND GRAVEL BASE COURSES
301.01 DESCRIPTION. This work consists of providi ng one or more courses of graded aggregate
or gravel borrow and fillers, if required, on prepared subgrade surfaces in reasonable close conformity with the dimensions and details indicated on the Plans, all in accordance with these Specifications.
301.02 MATERIALS. The following materials shall conform to the applicable requirements of the
indicated Subsections of SECTION M; MATERIALS:
301.03 CONSTRUCTION METHODS. 301.03.1 Placing. If the required compacted depth of the base course exceeds 12 inches, the
base shall be constructed in two or more layers of approximate equal thickness. The maximum compacted thickness of any one layer shall not exceed 12 inches. The maximum size of stone in the gravel borrow or aggregate placed, shall not exceed 3/4ths of the depth of the layer after compaction. This restriction determines the maximum size of stone in the gravel borrow specification of Subsection M.01.09; Gradation of Aggregate .
301.03.2 Shaping and Compaction. Compaction of each layer shall continue until a density of
not less than 95 percent of the maximum densit y determined in accordance with AASHTO T180 has been achieved. The surface of each layer shall be maintained during the co mpaction operations in such a manner that a reasonable uniformity is produced. The compacted surface shall have a tolerance of ½-inch, plus-or-minus, to the grades shown on the Plans or as directed. However, no plus or minus deviation may continue for more than 100 feet in any direction. Field moisture content for Gravel Borrow shall be adjusted, if necessary, to be no greater than two percent (+2%) above the optimum moisture content.
301.04 METHOD OF MEASUREMENT. "Aggregate Base Course" and/or "Gravel Borrow Base
Course" will be measured by the number of cubic yard s or the number of tons, as the case may be,