905.04METHOD OF MEASUREMENT

RI · 2024 Standard SpecificationsBook pages 546547View official source ↗

9−14

i.Cutting and Matching Existing Concrete Sidewalks or Driveways. Where a newly constructed sidewalk and/or driveway abuts an existing sidewalk or driveway, the existing sidewalk or driveway shall be cut with a concrete saw only. The concrete saw shall conform to Subsection

501.03 2; Para. c of these Specifications.

After installation of the concrete driveway, the contractor shall match bituminous pavement adjacent to parking areas, walkways, and driveways within 14 days.

905.03.4 Bituminous Sidewalks and Driveways.

a.Excavation and Forms. Excavation and forms shall meet the requirements of Subsections 905.03.3; Paras. a and c , respectively. The limits of excavation will be as shown on the Plans, or as directed by the Engineer. All material within the limits of excavation must be removed and replaced with gravel borrow subbase.
b.Gravel Borrow Subbase . Gravel material shall be placed in layers not exceeding 6 inches in depth and each layer shall be compacted as specified in Subsection 301.03.2 of these Specifications.
c.Placing Bituminous Sidewalk and Driveway Material . Bituminous sidewalk and driveway material shall be placed on the compacted base in one or more courses as indicated to give the required depth when rolled. Compaction s hall be accomplished by means of a power roller of a type and weight acceptable to the Engineer. In areas inaccessible to the roller, hand tamping or hand roller will be permitted. In any case, the bituminous material shall be uniformly compacted. The Contractor shall simultaneously extend the binder and Type I-1 surface course from the project roadway into all driveways which are not constructed with Portland cement concrete for a length of 3 feet, thereby eliminating cold joints at the gutter line.

905.04 Method of Measurement.

905.04.1 Portland Cement Sidewalks and Driveways. "Portland Cement Concrete Sidewalks and

Driveways" will be measured by the number of cubic yards of pavement actually placed in accordance with the Plans and/or as directed by the Engineer.

905.04.2 Bituminous Concrete Sidewalks and Driveways. "Bituminous Concrete Sidewalks and

Driveways" will be measured by t he number of tons of pavement material actually placed in accordance with the Plans and/or as directed by the Engineer.

905.05 BASIS OF PAYMENT. 905.05.1 Portland Cement Concrete Sidewalks and Driveways. The accepted quantities of

"Portland Cement Concrete Sidewalks and Driveways" will be paid for at the contract unit price per cubic yard as listed in the Proposal. A maximum 5 percent overrun of the calculated quantities based on the required thickness as shown on the Plans is permissible. The price so stated constitutes full and complete compensation for all labor, materials and equipment, including expansion joint material, reinforcement, and all inci dentals required to finish the work, complete and accepted by the Engineer. Excavation and gravel borrow subbase will be paid for separately under appropriate work items. 9−15905.05.2 Bituminous Concrete Sidewalks and Driveways. The accepted quantities of "Bituminous Concrete Sidewalks and Dr iveways" will be paid for at the contract unit price per ton as listed in the Proposal. A maximum 10 percent overrun of the calculated quantities based on the required thickness as shown on the Plans is permissible in accordance with the provisions of Subsection 401.04.1(b) of these Specifications. The price so-stated constitute s full and complete compensation for all labor, materials and equipment, and all incidentals required to finish the work, complete and accepted by the Engineer. Excavation and gravel borrow subbase will be paid for separately under appropriate work items. SECTION 906 CURBING FOR ROADWAYS

906.01 DESCRIPTION. This work consists of the construction of curbing on prepared gravel

bases and/or the construction of bituminous berm on underlying pavement courses at the locations indicated on the Plans or as directed by the Engineer, all in accordance with these Specifications. 906.01.1 Types of Curbing . The following types of curbing are designated as follows:

a.Granite Curbing.
b.Precast Concrete Curbing.
c.Bituminous Curbing. d. Bituminous Berm.
e.Remove Handle, Haul, Trim and Reset Curbing and Edging, Straight and/or Circular. All Types.

906.02 Materials.

906.02.1 Granite Curbing. Granite curbing shall conform to the requirements of Subsections

M.09.01 and M.09.02; Granite Curb for Roadways and Granite Slope Curbing for Roadways , respectively, of these Specifications. 906.02.2 Precast Concrete Curbing. Concrete for curbing shall be Class Z(AE) and shall conform to the applicable requirements of SECTION 601; PORTLAND CEMENT CONCRETE , of these Specifications with the following exceptions.
a.Job Mix Formula. The Contractor shall submit for approval a job-mix formula for the concrete mix design in accordance with the provisions of Subsection 601.03.1; Proportioning , of these Specifications.
b.Tolerances. Precast concrete curbing, apron stones, inlets and related concrete curb
Source: Rhode Island Standard Specifications (Bluebook), 2024 Edition. Pages 546547 of 826.