809.05BASIS OF PAYMENT. The accepted quantities of “Precast, Prestressed Concrete

RI · 2024 Standard SpecificationsBook pages 412412View official source ↗

8−78 will not be measured separately for payment but will be considered incidental to the other items of work covered in this section.

809.05 BASIS OF PAYMENT. The accepted quantities of “Precast, Prestressed Concrete

Elements” of the sizes and types specified, will be paid for at their respective contract unit prices per item or items of work as listed in the proposal. The prices so stated shall constitute full and complete compensation for all labor, equipment, tools and materials, including but not limited to backer rods, grouting between units, post tensioning, patching of duct pockets and all incidentals necessary to finish the work as specified, complete and accepted by the Engineer.

a.Payment for Compensation for Out-of-State Inspection Services. The Contractor shall pay for such out-of-state inspection servic es by the day (per diem) for each Department Engineer and/or Technician assigned to the plant for inspection of the project. The rates, which shall be established based on the radius, in miles, from the base of operations, shall be as follows: Distance in Radial Miles Rates per Inspector/Day 51-to-100 miles $150.00 Greater than 100 miles $500.00 There will be a maximum charge of one inspector for precast operations and two inspectors for prestress operations. The Contractor will be credited 50 percent when a plant is performing operations for two or more Department contracts. The contractor will not be charged for an initial inspection of a company or a single follow-up inspection for plant approval prior to initial production. The compensation payment for out-of-state ins pection services will be paid as a progress payment deduction. SECTION 810 REINFORCING STEEL

810.01 DESCRIPTION. This work consists of providing reinforcing steel, both plain and deformed,

and uncoated and galvanized; spiral wire; and welded wire fabric of the quality, type, size and at the locations indicated on the Plans or as directed by the Engineer, all in accordance with these Specifications. This work also includes the drilling and grouting of reinforcing dowels.

810.02 MATERIALS. The following materials shall conform to the applicable requirements of the

indicated Subsections of PART M; MATERIALS:

a.Subsection M.05.01, Bar Reinforcement.
Source: Rhode Island Standard Specifications (Bluebook), 2024 Edition. Pages 412412 of 826.